1644_DPH 451 Vanderbilt 1st Floor Buildout-Construction Plans _ Specs.pdf
PDF 41 MB Posted
- Attached to
- 1644 DPH 451 Vanderbilt 1st Floor Buildout
- Solicitation number
- ANE223-ANE2C-6410
- Issued by
- San Bernardino County, California
About this file
This document is a set of construction plans and specifications for a tenant improvement project at 451 E Vanderbilt Way, San Bernardino, California 92408, prepared by LPA Design Studios for San Bernardino County's Department of Public Health (DPH). The project involves the buildout of the first floor suite, including construction of new interior partitions, ceilings, and restrooms within the existing 24,784 square foot suite, along with associated electrical, mechanical, and plumbing work. The scope is limited to the interior suite and excludes site upgrades, building lobby, elevator lobby, and common area restrooms. The project is classified as occupancy type B with type III-1 hour construction in a four-story building with a total area of 120,538 square feet. The plans were submitted for city review on August 25, 2025, and approved by the county on April 10, 2026 (TI-2025-00170), spanning 88 pages for building code compliance review only. The project includes comprehensive architectural, electrical, mechanical, plumbing, and technology systems, with fire sprinkler and fire alarm drawings to be submitted by the general contractor after award.
The specifications establish detailed requirements for all construction materials, products, and installation standards in compliance with 2022 California Building Code and related standards including California Administrative Code, Electrical Code, Mechanical Code, Plumbing Code, Energy Code, Fire Code, Existing Building Code, and Green Building Standards Code. The contractor is responsible for accurate placement of all new construction, protection of existing work to remain, site safety, dust and noise control, debris removal, and compliance with all applicable federal, state, and local regulations. Key requirements include submittal procedures for products and materials, requests for information with three to five-day review periods, shop drawing compliance with specified standards, and provisions for deferred submittals. The contractor must maintain existing active building systems in operation during construction, coordinate all trade work, provide structural observation by the structural engineer, and complete work in compliance with fire safety requirements including sprinkler system installation, fire door assemblies, and emergency egress provisions. The project includes custom architectural casework, aluminum and steel frames, glazing systems, concrete work, insulation, joint sealants, and finish materials all subject to specific quality standards and industry certifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOT FOR REGULATORY APPROVAL,
PERMITTING OR CONSTRUCTION
ARCHITECTURE ENGINEERING INTERIORS
LANDSCAPE ARCHITECTURE PLANNING
949-261-1001 Office
LPADesignStudios.com
5301 California Avenue, Suite 100
Irvine, California 92617
PROJECT NUMBER
Submittal Date
CITY SUBMITTAL 08/25/2025
32468
DPH - FIRST FLOOR T.I.
451 E Vanderbilt Way, San Bernardino, CA 92408
G0.00
TITLE SHEET
Approved
Approved As Noted
Signature: Date:
CITY SUBMITTAL
08/25/2025
PCC-1
11/20/2025 JLee Engineering, Inc.
Approved By Jae Lee
04/06/2026 This set of plans and specifications MUST be kept on the job site at all times and it is unlawful to make any changes or alterations on these plans without written permission from the local Jurisdictions or Agencies.
The stamping of these plan and specifications shall NOT be held to permit or be an approval of the violations of the applicable codes, any provisions of any Local Ordinances or State law.
04/10/2026
COUNTY REVIEWED
PLANS FOR 88 PAGES
FOR BUILDING CODE
COMPLIANCE ONLY.
TI-2025-00170
COLUMN LINES
SURFACE DRAINAGE
ARROW INDICATES
DIRECTION OF FLOW
N
PROJECT NORTH
BUILDING SECTION
A101
TYP
SECTION ID
SHEET NUMBER
A101
TYP
WALL SECTION
SECTION ID
SHEET NUMBER
DETAIL CALLOUTS
DETAIL ID
SHEET NUMBER
A101
SIM
DETAIL SECTION
DETAIL ID
SHEET NUMBER
A101
SIM
DETAIL REFERENCE
DETAIL ID
SHEET NUMBER
A101
SIM
INTERIOR ELEVATIONS
DETAIL ID
SHEET NUMBER
A
C
SIM
D BA101
DOOR DESIGNATION
ROOM DESIGNATION
ROOM NUMBER
ROOM AREA
1REVISION CLOUD &
TAG (OPTIONAL)
SA2U
1t
SHADED PORTION POINTS
TO SIDE REFERENCED
DATUM POINT
KEYNOTE
WALL TYPE
OPENNING DESIGNATION
TYP.
MATCH LINE
SEE SHEET A101
LEVEL NAME
ELEVATION
LEVEL LINE, CONTROL POINT
EL: 12'-8" = ELEVATION/SECTION
STAIR DIRECTION
DN
UP
CENTER LINES, LEVEL LINES
HIDDEN CONSTRUCTION FEATURE
BREAK LINE
FINISH TAG
EQUIPMENT TAG 1i
N
TRUE NORTH
NORTH ARROW
EXTERIOR ASSEMBLY
REFER TO A8.11 R1
Room
150 SF
CAB CABINET
CB CATCH BASIN
CEM CEMENT
CER CERAMIC
CI CAST IRON
CIP CAST IN PLACE
CIV ENG CIVIL ENGINEER
CG CORNER GUARD
CJ CONTROL JOINT
CLG CEILING
CLKG CAULKING
CLO CLOSET
CLR CLEAR
CNTR COUNTER
CO CASED OPENING
COL COLUMN
CONC CONCRETE
CONN CONNECTION
CONSTR CONSTRUCTION
CONT CONTINUOUS
CORR CORRIDOR
CT CERAMIC TILE
CTR CENTER
CTSK COUNTERSUNK
DA DISABLED ACCESS
DBL DOUBLE
DEPT DEPARTMENT
DESC DESCRIPTION
DF DRINKING FOUNTAIN
DET DETAIL
DIA DIAMETER
DIM DIMENSION
DISP DISPENSER
DN DOWN
DO DOOR OPENING
DR DOOR
DWR DRAWER
DS DOWNSPOUT
DSP DRY STANDPIPE
DWG DRAWING
E EAST
EA EACH
EJ EXPANSION JOINT
EL ELEVATION
ELEC ELECTRICAL
ELEV ELEVATOR
EMER EMERGENCY
ENCL ENCLOSURE
EP ELECTRICAL PANELBOARD
EQ EQUAL
EQUIP EQUIPMENT
EWC ELECTRIC WATER COOLER
EXIST EXISTING
EXPO EXPOSED
EXP EXPANSION
EXT EXTERIOR
FA FIRE ALARM
FB FLAT BAR
FD FLOOR DRAIN
FDN FOUNDATION
FE FIRE EXTINGUISHER
FEC FIRE EXTINGUISHER
CABINET
FHC FIRE HOSE CABINET
FIN FINISH
FLR FLOOR
FLASH FLASHING
FLUOR FLUORESCENT
FOC FACE OF CONCRETE
FOF FACE OF FINISH
FOM FACE OF MASONRY
FOS FACE OF STUD
FOV FACE OF VENEER (BRICK OR
PRECAST)
FOW FACE OF W ALL
FR FIRE RETARDANT
FPRF FIREPROOF
FS FINISH SURFACE
FT FOOT OR FEET
FTG FOOTING
FURR FURRING
FUT FUTURE
GA GAUGE
GALV GALVANIZED
GB GRAB BAR
GC GENERAL CONTRACTOR
GI GALVANIZED IRON
GL GLASS
GND GROUND
GR GRADE
GYP GYPSUM
HB HOSE BIB
HC HOLLOW CORE
HDWD HARDWOOD
HDW HARDWARE
HM HOLLOW METAL
HORIZ HORIZONTAL
HR HOUR
HGT/HT HEIGHT
ID INSIDE DIAMETER
INSUL INSULATION
INT INTERIOR
JAN JANITOR
JT JOINT
KIT KITCHEN
LAB LABORATORY
LAM LAMINATE
LAND ARCH LANDSCAPE
ARCHITECT
LAV LAVATORY
LKR LOCKER
LT LIGHT
MATL MATERIAL
MAX MAXIMUM
MC MEDICINE CABINET
MECH MECHANICAL
MEMB MEMBRANE
MET METAL
MFR MANUFACTURER
MH MANHOLE
MIN MINIMUM
MIR MIRROR
MISC MISCELLANEOUS
MO MASONRY OPENING
MTD MOUNTED
MUL MULLION
N NORTH
NIC NOT IN CONTRACT
NO/# NUMBER
NOM NOMINAL
NTS NOT TO SCALE
OA OVERALL
OA OUTSIDE AIR
OBS OBSCURE
OC ON CENTER
OD OUTSIDE DIAMETER
OFF OFFICE
OPNG OPENING
OPP OPPOSITE
OSA OUTSIDE AIR
PA PLANTING AREA
PRCST PRECAST
PH PANIC HARDWARE
PL PLATE
P LAM PLASTIC LAMINATE
PLAS PLASTER
PLYW D PLYW OOD
POT PATH OF TRAVEL
PR PAIR
PT PAINT
PTD PAPER TOWEL
DISPENSER
PTD/R COMBINATION PAPER
TOWEL DISPENSER
& RECEPTACLE
PTN PARTITION
PTR PAPER TOWEL
RECEPTACLE
QT QUARRY TILE
R RISER
RAD RADIUS
RD ROOF DRAIN
REF REFERENCE
REFR REFRIGERATOR
RGTR REGISTER
REINF REINFORCED
REQD REQUIRED
RESIL RESILIENT
RM ROOM
RO ROUGH OPENING
ROW RIGHT OF WAY
RWD REDWOOD
RWL RAIN WATER LEADER
S SOUTH
SC SOLID CORE
SCD SEAT COVER
DISPENSER
SCHED SCHEDULE
SD SOAP DISPENSER
SECT SECTION
SF SQUARE FEET
SH SHELF
SHR SHOW ER
SHT SHEET
SIM SIMILAR
SND SANITARY NAPKIN
DISPENSER
SNR SANITARY NAPKIN
RECEPTACLE
SPEC SPECIFICATION(S)
SQ SQUARE
SS STAINLESS STEEL
S SK SERVICE SINK
STA STATION
STD STANDARD
STL STEEL
STOR STORAGE
STR STRUCTURAL
SUSP SUSPENDED
SYM SYMMETRICAL
T TREAD
TB TOWEL BAR
TC TOP OF CURB
TEL TELEPHONE
TER TERRAZZO
T&G TONGUE & GROOVE
THK THICK
TOB TOP OF BEAM
TOC TOP OF CONCRETE
TOW TOP OF WALL
TOP TOP OF PARAPET
TPD TOILET PAPER
DISPENSER
TS TOP OF SLOPE
TV TELEVISION
TYP TYPICAL
UNF UNFINISHED
UNO UNLESS NOTED
OTHERWISE
UR URINAL
VCT VINYL COMPOSITION
TILE
VERT VERTICAL
VEST VESTIBULE
W WEST
W/ WITH
WC WATER CLOSET
WD WOOD
W/O WITHOUT
WP WATERPROOF
WR WATER RESISTANT
WSCT WAINSCOT
WT WEIGHT
WWF WELDED WIRE FABRIC
& AND
∠ ANGLE
@ AT
℄ CENTERLINE
∅ DIAMETER OR ROUND
# POUND OR NUMBER
(E) EXISTING
(P) PAINT
(R) REMOVE
+/- DIM TOLERANCE
AC ASPHALTIC CONCRETE
ACC ACCESSIBLE
ACOUS ACOUSTICAL
ACM ALUM COMPOSITE MATERIAL
ACT ACOUS CLG TILE
AD AREA DRAIN
AED AUTO EXT DEFIBRILLATOR
ADJ ADJUSTABLE
AFF ABOVE FINISH FLOOR
AGGR AGGREGATE
AHJ AUTHORITY HAVING
JURISDICTION
ALUM ALUMINUM
APPROX APPROXIMATE
ARCH ARCHITECTURAL
ASF ASSIGNABLE SF
ASPH ASPHALT
BD BOARD
BITUM BITUMINOUS
BLDG BUILDING
BLK BLOCK
BLK'G BLOCKING
BM BEAM
BOC BACK OF CURB
BOT BOTTOM
BO BOTTOM OF
BOC BACK OF CURB
BOW BOTTOM OF WALL
BS BOTTOM OF SLOPE
N
PROJECT NORTH
PROJECT LOCATION
ADDRESS:
451 E Vanderbilt Way, San Bernardino, CA 92408
N
TRUE NORTH
11B-201.4 CONSTRUCTION SUPPORT FACILITIES. These requirements shall apply to temporary or permanent construction support facilities for uses and activities not directly associated with the actual processes of construction, including but not limited to offices, meeting rooms, plan rooms, other administrative or support functions. When provided, toilet and bathing facilities serving construction support facilities shall comply with 11B-213. When toilet and bathing facilities serving construction support facilities are provided by portable units, at least one of each type shall be accessible and connected to the construction support facilities it serves by an accessible route.
EXCEPTION: During construction an accessible route shall not be required between site arrival points or the boundary of the area of construction and the entrance to the construction support facilities if the only means of access between them is a vehicular way not providing pedestrian access.
ACCESSIBLE CONSTRUCTION SUPPORT
FACILITIES
SEE "G" SERIES SHEETS FOR ACCESSIBLE REQUIREMENTS.
LPA, INC.
5301 CALIFORNIA AVE, SUITE 100
IRVINE, CA 92617
TEL: 949-261-XXXX
TEL: (909) 387-5000
DIRECTOR OF FACILITY
San Bernardino, CA 92408
ARCHITECT
MECHANICAL ENGINEER
ELECTRICAL ENGINEER
CLIENT INFORMATION
PLUMBING ENGINEER
SAN BERNADINO COUNTY
TECHNOLOGY CONSULTANT
451 E Vanderbilt Way
CONTACT: LILIANA AUBERT E-MAIL: Liliana.Aubert@pfm.sbcounty.gov
CONTACT: SONALY DUDHEKER E-MAIL: sdudheker@lpadesignstudios.com
TEL: (323) 482-0720
LP CONSULTING ENGINEERS, INC.
3200 EAST GUASTI ROAD, SUITE 106
CONTACT: MIKE MORENO
E-MAIL:
mmoreno@lpengineers.com
LPA, INC.
5301 CALIFORNIA AVE, SUITE 100
IRVINE, CA 92617
TEL: 949-261-1001
CONTACT: JARED PLUMMER E-MAIL: jplummer@lpadesignstudios.com
LPA, INC.
5301 CALIFORNIA AVE, SUITE 100
IRVINE, CA 92617
TEL: 949-261-1001
CONTACT: MAUREN MCSHANE E-MAIL: mmcshane@lpadesignstudios.com
LPA, INC.
5301 CALIFORNIA AVE, SUITE 100
IRVINE, CA 92617
TEL: 949-261-1001
CONTACT: KRISTY NELSON E-MAIL: knelson@lpadesignstudios.com
ONTARIO, CA 91761
TENANT IMPROVEMENTS OF EXISTING SUITE TO INCLUDE CONSTRUCTION OF
NEW INTERIOR PARITIONS, AND CEILING PER LAYOUT AND RESTROOMS W ITHING
EXISTING SUITE. ASSOCIATED ELECTRICAL, MECHANICAL, AND PLUMBING
INCLUDED AS WELL.
SCOPE IS LIMITED TO WITHIN EXISTING SUITE. SITE UPGRADES, BUILDING LOBBY,
ELEVATOR LOBBY AND RESTROOMS IN THE LOBBY ARE NOT IN SCOPE.
1.FIRE SPRINKLER / FIRE ALARM - FIRE SPRINKLER DRAWINGS TO BE SUBMITTED
BY GENERAL CONTRACTOR ONCE AWARED.
1. ALL CONSTRUCTION & MATERIALS SHALL BE AS SPECIFIED & IN
ACCORDANCE WITH ALL APPLICABLE CODES, ORDINANCES, LAWS, PERMITS
& THE CONTRACT DOCUMENTS.
2. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE ACCURATE
PLACEMENT OF ALL NEW CONSTRUCTION ON THE SITE.
3. THE CONTRACTOR IS RESPONSIBLE FOR ALL EXG SURVEY MONUMENTS
WHICH MAY BE DISTURBED THROUGH CONSTRUCTION ACTIVITIES DEEMED
NECESSARY FOR PRESERVATION BY THE CIVIL ENGINEER. IF SUCH
MONUMENTS WERE DISTURBED, THE APPLICANT SHALL HAVE A LICENSED
LAND SURVEYOR QUALIFIED CIVIL ENGINEER REESTABLISH ANY SUCH
MONUMENTATION DAMAGED OR DESTROYED DURING THE CONSTRUCTION
OF THE PROJECT & SUBMIT "PRELIMINARY CORNER RECORDS" TO THE CIVIL
ENGINEER AFTER REPLACEMENT. AFTER APPROVAL BY THE CIVIL
ENGINEER, THE APPLICANT SHALL FILE THE CORNER RECORDS WITH THE
COUNTY SURVEYOR. PRIOR TO THE EXONERATION OF ANY SECURITY,
EVIDENCE OF SUCH FILING SHALL BE FURNISHED TO THE CIVIL ENGINEER.
4. THE CONTRACTOR IS RESPONSIBLE TO INSURE THAT TRUCK ROUTES
SHALL BE STEERED AWAY FROM RESIDENTIAL AREAS.
5. THE CONTRACTOR SHALL ENSURE THAT TRUCKS HAULING DIRT ON PUBLIC
ROADS TO & FROM THE SITE SHALL BE COVERED OR WILL MAINTAIN A 6"
DIFFERENTIAL BETWEEN THE MAX HGT OF ANY HAULED MATERIAL & THE
TOP OF THE HAUL TRAILER. HAUL TRUCK DRIVERS SHALL W ATER THE LOAD
PRIOR TO LEAVING THE SITE TO PREVENT SOIL LOSS DURING TRANSPORT.
6. THE CONTRACTOR SHALL ENSURE THAT GRADED SURFACES USED FOR
OFF ROAD PARKING, MATERIALS LAY-DOWN, OR AW AITING FUTURE
CONSTRUCTION SHALL BE STABILIZED FOR DUST CONTROL AS NEEDED.
FREQUENTLY ACCESSED UNPAVED AREAS SHALL BE PAVED AS EARLY AS
POSSIBLE TO MINIMIZE DIRT TRACKOUT TO PUBLIC RIGHTS-OF-WAY.
7. THE CONSTRACTOR SHALL COORDINATE ANY LANE CLOSURES OR
DETOURS WITH THE CITY/COUNTY. FLAG PERSONS & APPROPRIATE
TRAFFIC CONTROL DEVICES SHALL BE USED AS NEEDED TO MINIMIZE
CONSTRUCTION ACTIVITY INTERFERENCE WITH OFF-SITE-TRAFFIC.
8. THE CONTRACTOR SHALL VERIFY ALL DIMENSIONS & SITE CONDITIONS
BEFORE STARTING WORK. SHOULD A DISCREPANCY APPEAR IN THE
CONTRACT DOCUMENTS OR BETWEEN THE CONTRACT DOCUMENTS &
EXISTING CONDITIONS, NOTIFY THE ARCHITECT AT ONCE FOR INSTRUCTION
ON HOW TO PROCEED.
9. SHOULD A CONFLICT OCCUR BETWEEN DWGS & SPECIFICATIONS, THE
MORE COSTLY CONDITION SHALL TAKE PRECEDENCE, UNLESS A WRITTEN
DECISION FROM THE ARCHITECT HAS BEEN OBTAINED WHICH DESCRIBES A
CLARIFICATION OR ALTERNATE METHOD AND/OR MATERIALS.
10. THE CONTRACTOR SHALL CONFINE HIS OPERATION ON THE SITE TO AREAS
PERMITTED BY OW NER.
11. THE JOBSITE SHALL BE MAINTAINED IN A CLEAN, ORDERLY CONDITION FREE
OF DEBRIS & LITTER & SHALL NOT BE UNREASONABLY ENCUMBERED W ITH
ANY MATERIALS OR EQUIPMENT. EACH SUBCONTRACTOR IMMEDIATELY
UPON COMPLETION OF EACH PHASE OF HIS W ORK SHALL REMOVE ALL
TRASH & DEBRIS AS A RESULT OF HIS OPERATION.
12. ALL MATERIAL STORED ON THE SITE SHALL BE PROPERLY STACKED &
PROTECTED TO PREVENT DAMAGE & DETERIORATION. FAILURE TO
PROTECT MATERIALS MAY BE CAUSE FOR REJECTION OF WORK.
13. THE CONTRACTOR SHALL DO ALL CUTTING, FITTING, AND/OR PATCHING OF
HIS WORK THAT MAY BE REQ TO MAKE ITS SEVERAL PARTS FIT TOGETHER
PROPERLY & SHALL NOT ENDANGER ANY OTHER WORK BY CUTTING,
EXCAVATING, OR OTHERWISE ALTERING THE TOTAL WORK OR ANY PART OF
IT. ALL PATCHING, REPAIRING AND REPLACING OF MATERIALS AND
SURFACES, CUT OR DAMAGED IN EXECUTION OF WORK, SHALL BE DONE
WITH APPLICABLE MATERIALS SO THAT SURFACES REPLACED WILL, UPON
COMPLETION, MATCH SURROUNDING SIMILAR SURFACES.
14. STRUCTURAL OBSERVATION WILL BE PERFORMED BY THE STRUCTURAL
ENGINEER. W HEN REQ, A STATEMENT IN WRITING SHALL BE GIVEN TO THE
BUILDING OFFICIAL, STATING THAT THE SITE VISITS HAVE BEEN MADE &
WHETHER OR NOT ANY OBSERVED DEFICIENCIES HAVE BEEN CORRECTED
TO CONFORM TO THE APPROVED PLANS & SPECIFICATIONS.
15. SUBMITTAL DOCUMENTS FOR DEFERRED SUBMITAL ITEMS SHALL BE
SUBMITTED TO THE ARCHITECT OR ENGINEER OF RECORD, WHO SHALL
REVIEW THEM & RETURN THEM TO THE CONTRACTOR (WITH A
NOTIFICATION INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS
HAVE BEEN REVIEWED & THAT THEY HAVE BEEN FOUND TO BE IN GENERAL
CONFORMANCE WITH THE DESIGN OF THE BUILDING) FOR PLAN CHECK
APPROVAL. THE DEFERRED SUBMITTAL ITEMS SHALL NOT BE INSTALLED
UNTIL THEIR DESIGN & SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY
THE AUTHORITY HAVING JURISDICTION.
16. PROVIDE ALL ACCESS PANELS AS REQ BY GOVERNING CODES TO ALL
CONCEALED SPACES, VOIDS, ATTICS, ETC. VERIFY TYPE REQ WITH
ARCHITECT PRIOR TO INSTALLATION.
17. NO PORTION OF W ORK REQ A SHOP DWG OR SAMPLE SUBMISSION SHALL
BE COMMENCED UNTIL THE SUBMISSION HAS BEEN REVIEWED BY THE
ARCHITECT. ALL SUCH PORTIONS OF THE WORK SHALL BE IN ACCORDANCE
WITH CORRECTED SHOP DWGS. AND SAMPLES.
18. DIMENSIONS:
A. ALL DIMS SHALL TAKE PRECEDENCE OVER SCALE.
B. ALL DIMS ARE TO FACE OF STUD / CONCRETE / MASONRY UNO
C. CLG HGT DIMS ARE FROM FACE OF SLAB TO FACE OF FIN CLG MATERIAL
UNO
19. DO NOT SCALE DRAW INGS
20. PROVIDE ALL NECESSARY BLOCKING, BACKING, & FRAMING FOR LIGHT
FIXTURES, ELECTRIC UNITS, AC EQUIP, RECESSED ITEMS, AND ALL OTHER
ITEMS AS REQ.
21. WHERE LARGER STUDS OR FURRING ARE REQ TO COVER PIPING AND
CONDUITS, THE LARGER STUD SIZE OR FURRING SHALL EXTEND THE FULL
SURFACE OF THE WALL WIDTH AND LENGTH WHERE THE FURRING
OCCURS, UNO.
22. ALL DOORS SHALL BE OPERABLE FROM THE INSIDE W/O THE USE OF A KEY
OR SPECIAL KNOWLEDGE OF EFFORT. EXIT SIGNS SHALL BE PROVIDED AT
ALL EXITS AS REQ BY THE APPLICABLE CODES. ALL DOOR SWINGS SERVING
AN OCCUPANT LOAD OF 50 OR GREATER SHALL SWING IN THE DIRECTION
OF TRAVEL.
23. ALL GLASS AND GLAZING SHALL COMPLY W ITH THE APPLICABLE CODES.
24. WALL AND CLG MATERIALS SHALL NOT EXCEED THE FLAME SPREAD
CLASSIFICATIONS IN THE APPLICABLE CODES.
25. SURVEYORS CERTIFICATE REQ PRIOR TO FINAL COMPLETION.
26. THE CONTRACTOR SHALL COMPLY WITH THE APPLICABLE CODES FOR FIRE
SAFETY DURING CONSTRUCTION AND DEMOLITION.
1. PLANS FOR THE FIRE SPRINKLER SYSTEMS MUST BE APPROVED BY THE
AUTHORITY HAVING JURISDICTION (AHJ) PRIOR TO INSTALLATION. SUBMIT
PLANS IN A MANNER WHICH W ILL NOT IMPEDE THE PROGRESS OF
CONSTRUCTION.
2. FIRE SPRINKLER SYSTEMS & INSTALLATION SHALL CONFORM W/ THE
APPLICABLE STANDARDS AND CODES.
3. FIRE SPRINKLER SYSTEMS TO BE TIED INTO THE ALARM SYSTEM PER THE
APPLICABLE CODES.
4. AUTOMATIC SPRINKLER SYSTEM(S) SHALL BE SUPERVISED BY AN APPROVED
CENTRAL OR REMOTE STATION SERVICE, AND/OR SHALL BE PROVIDED W/ A
LOCAL ALARM WHICH W ILL GIVE AN AUDIBLE SIGNAL.
5. FIRE SPRINKLER SYSTEM(S) & ALL CONTROL VALVES SHALL BE SUPERVISED
BY A U.L. LISTED CENTRAL ALARM STATION OR PER THE APPLICABLE CODES.
6. FIRE HYDRANT & FIRE SPRINKLER SYSTEM(S) SHALL BE FLUSHED
THOROUGHLY BEFORE CONNECTION IS MADE TO EXISTING SYSTEM
STUBOUTS & WITNESSED BY THE PROJECT INSPECTOR.
7. A HYDROSTATIC TEST (200 PSI PRESSURE FOR 2 HRS. OR @ 50 PSI IN
EXCESS OF THE MIN. STATIC PRESSURE WHEN IT IS IN EXCESS OF 150 PSI)
SHALL BE WITNESSED BY THE PROJECT INSPECTOR PRIOR TO COVERING
PIPING JOINTS.
8. A 3' CLR SPACE SHALL BE MAINTAINED AROUND THE CIRCUMFERENCE OF
FIRE HYDRANTS EXCEPT AS OTHERWISE REQ OR APPROVED PER THE
APPLICABLE CODES.
9. THRUST BLOCKS SHALL BE PROVIDED WHEREVER PIPE CHANGES
DIRECTION.
10. ALL PIPE SHALL BE UL LISTED FOR FIRE SERVICE SYSTEMS, CLASS 200 MIN.
11. FIRE DEPARTMENT CONNECTIONS SHALL BE LOCATED W /I 100' FROM A
PUBLIC FIRE HYDRANT PER THE APPLICABLE STANDARDS AND CODES.
12. FIRE SPRINKLER RISER SHALL BE LOCATED WITHIN 5 FT OF THE EXT WALL
(OR AS REQ BY THE AHJ) AND TERMINATE 6" ABV FF
13. AN ALL-WEATHER FIRE ACCESS ROAD SHALL BE IN PLACE BEFORE ANY
COMBUSTIBLE MATERIALS ARE PLACED ON THE SITE OR AS REQ BY THE AHJ.
14. STORAGE, DISPENSING, OR USE OF ANY FLAMMABLE & COMBUSTIBLE
LIQUIDS, FLAMMABLE & COMPRESSED GASES & OTHER HAZARDOUS
MATERIALS SHALL COMPLY W/ THE APPLICABLE CODES.
15. EXIT SIGNS SHALL BE POSTED OVER EXIT DOORS & DIRECTIONAL EXIT SIGNS
SHALL BE LOCATED TO DIRECT PERSONS TOWARD EXIT DOORS.
16. EXIT SIGNS SHALL BE SELF-LUMINOUS TYPE OR ELECTRONICALLY
ILLUMINATED & ENERGIZED FROM SEPARATE CIRCUITS, ONE OF WHICH
SHALL BE FROM STORAGE BATTERIES OR AN ON-SITE GENERATOR, FOR A
DURATION OF 90 MINUTES PER THE APPLICABLE CODES.
17. EXIT DOORS SHALL BE OPENABLE FROM THE INSIDE WITHOUT THE USE OF A
KEY OR ANY SPECIAL KNOWLEDGE OR EFFORT.
18. ACCESS GATE(S) SHALL BE OPENABLE W/ FIRE DEPT MASTER KEY FROM THE
EXTERIOR.
19. CURBS ALONG FIRE LANES SHALL BE PAINTED SAFETY RED & MARKED "FIRE
LANE NO PARKING" W/ 3" W HITE LETTERS ON THE TOP OF CURBING EVERY
30' AS INDICATED ON THE APPROVED DRAW INGS.
20. APPROVED NUMBERS OR ADDRESSES SHALL BE PROVIDED FOR ALL NEW &
EXG BLDGS IN SUCH A POSITION AS TO BE PLAINLY VISIBLE & LEGIBLE FROM
THE STREET OR ROAD FRONTING THE PROPERTY PER THE APPLICABLE
CODES.
21. PROVIDE PERMANENT OR TEMPORARY STANDPIPES WHILE BUILDING IS
UNDER CONSTRUCTION PER THE APPLICABLE CODES.
22. PROVIDE FIRE EXTINGUISHERS PER THE REQ THE APPLICABLE STANDARDS
AND CODES.
23. SPRINKLERS: ALL GYPSUM BOARD CEILINGS / SOFFITS AND
SPECIALTY CEILING TILE [SEE LEGEND], TO HAVE FULLY RECESSED
CONCEALED SPRINKLER HEADS WITH CAPS. ALL OTHER SPACES TO HAVE
STANDARD SPRINKLER HEADS PER INDICATED CEILING CONDITION, U.N.O.
24. SPRINKLERS: PROVIDE NEW AS REQUIRED BY REMODEL. DO NOT REUSE
SPRINKLER HEADS AT ALL LOCATIONS WHERE SPRINKLER/SPRINKLER PIPES
CONFLICT WITH NEW WORK. REMOVE, RELOCATE, AND/OR REPLACE
EXISTING SPRINKLER PIPING. NOTIFY ARCHITECT OF ANY FIELD CONFLICTS
PRIOR TO PROJECT BID.
25. SPRINKLERS: PROVIDE FULLY RECESSED CONCEALED SPRINKLER HEADS
WITH CAPS AT ALL SIDE WALL LOCATIONS.
2022 CALIFORNIA ADMINISTRATIVE CODE (CAC), PART 1, TITLE 24 CCR
2022 CALIFORNIA BUILDING CODE (CBC), PART 2, TITLE 24 CCR
2022 CALIFORNIA ELECTRICAL CODE (CEC), PART 3, TITLE 24 CCR
2022 CALIFORNIA MECHANICAL CODE (CMC), PART 4, TITLE 24 CCR
2022 CALIFORNIA PLUMBING CODE (CPC), PART 5, TITLE 24 CCR
2022 CALIFORNIA ENERGY CODE, PART 5 TITLE 24 CCR
2022 CALIFORNIA FIRE CODE (CFC), PART 9, TITLE 24 CCR
2022 CALIFORNIA EXISTING BUILDING CODE (CEBC), PART 10, TITLE 24 CCR
2022 CALIFORNIA GREEN BUILING STANDARDS CODE (CALGREEN), PART 11,
TITLE 24 CCR
2022 CALIFORNIA REFERENCED STANDARDS CODE, PART 12, TITLE 24 CCR
TITLE 19 CCR, PUBLIC SAFETY, STATE FIRE MARSHAL REGULATIONS
CURRENT CITY OF SAN BERNARDINO REGULATIONS AND ORDINANCES
APPLICABLE STANDARDS
FOR A LIST OF APPLICABLE STANDARDS, INCLUDING CALIFORNIA AMENDMENTS
TO THE NFPA STANDARDS, REFER TO CBC CHAPTER 35 AND CFC CHAPTER 80.
PROJECT LOCATION: 351 E VANDERBILT WAY,
SAN BERNARDINO, CA 92408
BUILDING OCCUPANCY: B
TYPE OF CONSTRUCTION: III - 1 HOUR
NUMBER OF STORIES: 4
AS-BUILT TOTAL BUILDING AREA: 120,538 SF
AREA OF SCOPE (FIRST FLOOR): 24,784 SF
R e v is io n
D a te
NOT FOR REGULATORY APPROVAL,
PERMITTING OR CONSTRUCTION
ARCHITECTURE ENGINEERING INTERIOR DESIGN
LANDSCAPE ARCHITECTURE PLANNING
949-261-1001 Office
LPADesignStudios.com
5301 California Avenue, Suite 100
Irvine, California 92617
D e v e lo p e d f o r
Checked By
Scale
Job Number
S u b m it ta l D a te
C
IT
Y S
U B
M
IT
T A
L
/2
/2
This document and all other project documents, ideas, aesthetics and designs incorporated therein are instruments of service. All project documents are copyright protected, are the property of LPA, Inc. (LPA) and cannot be lawfully used in whole or in part for any project or purpose except as set forth in the contractual agreement between LPA and its Client. The unauthorized disclosure and/or use of the project documents (including the creation of derivative works), may give rise to liability for copyright infringement, unlawful disclosure, use or misappropriation of property rights held by LPA. The unauthorized use of the project documents will give rise to the recovery of monetary losses and damages including attorney fees and costs for which the unauthorized user will be held liable.
Project documents describe the design intent of the work and are not a representation of as-built or existing conditions. LPA is not responsible for any discrepancies between the project documents and the existing conditions.
© LPA, Inc.
As indicated
E
V a n d e rb ilt W a y
S a n B e rn a rd in o
C
A
S A
N B
E R
N A
R D
IN
O
C O
U N
T Y
D P
H
F
IR
S T
F L
O O
R T
.I
S A
N B
E R
N A
R D
IN
O
C O
U N
T Y
E
V a n d e rb ilt W a y
S a n B e rn a rd in o
C
A
GENERAL INFORMATION
SHEET
G0.20
32468
SD/NF/KR
SHEET INDEX
S H
E E
T N
U M
B E
R
SHEET NAME
GENERAL
G0.00 TITLE SHEET
G0.20 GENERAL INFORMATION SHEET
G0.21 GENERAL CONDITIONS & NOTES
G0.22 GENERAL CONDITIONS & NOTES
G0.31 ACCESSIBILITY DETAILS
G0.32 ACCESSIBILITY DETAILS
G0.40 CAL GREEN (CA)
G0.41 CAL GREEN (CA)
G0.42 CAL GREEN (CA)
G0.43 CAL GREEN (CA)
G2.01 01 - FLOOR - CODE ANALYSIS
ARCHITECTURE
A1.01 01 - FLOOR DEMO PLAN
A2.01 01 - FLOOR FLOOR PLAN
A2.21 01 - FLOOR FINISHES PLAN
A2.31 01 - FLOOR REFLECTED CEILING PLAN
A2.41 01 - FLOOR POWER & COMMUNICATION
A4.01 ENLARGED RESTROOM PLANS
A5.01 ENLARGED PLANS AND INTERIOR ELEVATIONS
A5.02 ENLARGED PLANS AND INTERIOR ELEVATIONS
A5.03 INTERIOR ELEVATIONS
A5.04 INTERIOR ELEVATIONS
A5.05 INTERIOR ELEVATIONS
A6.00 DOOR TYPES & SCHEDULES
A6.31 SCHEDULES
A9.01 PARTITION DETAILS
A9.10 TYPICAL LIGHT GAUGE METAL STUD DETAIL
A9.11 INTERIOR DETAILS
A9.12 INTERIOR DETAILS
A9.13 DOOR DETAILS
A9.21 CEILING DETAILS
A9.22 CEILING DETAILS
A9.31 MILLWORK DETAILS
A9.32 MILLWORK DETAILS
A9.41 RESTROOM DETAILS
SYMBOLSABBREVIATIONS
VICINITY MAP
ACCESSIBILITY NOTES PROJECT SCOPE
T8.3 RATED ASSEMBLY PENETRATION
T8.2 AUDIO-VIDEO DETAILS
T8.1 TECHNOLOGY DETAILS
T4.1 TECHNOLOGY ONE-LINE DIAGRAM
T2.2 TECHNOLOGY FIRST FLOOR CEILING PLAN
T2.1 TECHNOLOGY FIRST FLOOR PLAN
T0.2 TECHNOLOGY LEGENDS
T0.1 TECHNOLOGY NOTES
TECHNOLOGY
E9.01 LIGHTING PHOTOMETICS PLAN
E8.01 ENERGY COMPLIANCE FORMS
E7.02 LIGHTING DETAILS
E7.01 ELECTRICAL DETAILS
E6.10 ELECTRICAL FIXTURE SCHEDULE
E6.03 ELECTRICAL MECHANICAL SCHEDULES
E6.02 ELECTRICAL PANEL SCHEDULES
E6.01 ELECTRICAL SINGLE LINE DIAGRAM AND PANEL SCHEDULES
E5.13 LIGHTING CONTROL BUTTON ENGRAVING DIAGRAMS
E5.12 LIGHTING CONTROL DIAGRAMS
E5.11 LIGHTING CONTROL DIAGRAMS
E5.10 LIGHTING FIXTURE & CONTROL NOTES
E2.21 LIGHTING PLAN
E2.11 ELECTRICAL POWER/MECH PLAN
E2.01 ELECTRICAL POWER PLAN
E1.01 ELECTRICAL DEMOLITION PLAN
E0.04 ELECTRICAL SPECIFICATIONS
E0.03 ELECTRICAL SPECIFICATIONS
E0.02 ELECTRICAL LEAD SHEET
E0.01 ELECTRICAL LEGEND & GENERAL NOTES
ELECTRICAL
P9.01 PLUMBING SPECIFICATIONS
P7.01 PLUMBING DETAILS
P6.01 PLUMBING SCHEDULES
P4.01 PLUMBING ENLARGED PLANS
P3.01 PLUMBING DOMESTIC WATER & GAS PLANS
P2.01 PLUMBING DRAINAGE PLANS
P1.01 PLUMBING DEMOLITION PLANS
P0.10 PLUMBING LEGEND & GENERAL NOTES
PLUMBING
M9.01 MECHANICAL SPECIFICATIONS
M8.04 MECHANICAL ENERGY COMPLIANCE DOCUMENTATION
M8.03 MECHANICAL ENERGY COMPLIANCE DOCUMENTATION
M8.02 MECHANICAL ENERGY COMPLIANCE DOCUMENTATION
M8.01 MECHANICAL ENERGY COMPLIANCE DOCUMENTATION
M7.01 MECHANICAL DETAILS
M6.01 MECHANICAL SCHEDULES
M5.10 MECHANICAL CONTROL DIAGRAMS
M5.01 MECHANICAL ZONING PLANS
M2.11 MECHANICAL PIPING & CONTROLS PLANS
M2.01 MECHANICAL HVAC PLANS
M1.01 MECHANICAL DEMOLITION PLANS
M0.01 MECHANICAL LEGEND & GENERAL NOTES
MECHANICAL
DEFERRED APPROVALS
CONSTRUCTION NOTES
FIRE AND LIFE SAFETY NOTES
APPLICABLE CODES
PROJECT INFORMATION
JLee Engineering, Inc.
Approved By Jae Lee
04/06/2026 This set of plans and specifications MUST be kept on the job site at all times and it is unlawful to make any changes or alterations on these plans without written permission from the local Jurisdictions or Agencies.
The stamping of these plan and specifications shall NOT be held to permit or be an approval of the violations of the applicable codes, any provisions of any Local Ordinances or State law.
1.01 DEFINITIONS
A. FOR PURPOSES OF CONTRACT DOCUMENTS AND THESE SPECIFICATIONS, “OWNER” AND “TENANT” ARE REFERENCED ENTITIES WITH CONTRACTUAL OBLIGATIONS BETWEEN THE TWO PARTIES SEPARATE
FROM THESE SPECIFICATIONS. SAID CONTRACTUAL OBLIGATIONS TAKES PRECEDENCE OVER THESE SPECIFICATIONS WHEN THERE IS A CONFLICT BETWEEN THE CONTRACTUAL OBLIGATIONS AND THE
SPECIFICATIONS. “OWNER” IN THESE SPECIFICATIONS GENERALLY REFERS TO THE LANDLORD OR BUILDING OWNER. TENANT REFERS TO ENTITY LEASING THE PREMISES. IT IS POSSIBLE THEY ARE ONE IN THE
SAME AND ANY CONFLICTS SHOULD BE ADDRESSED IN AN RFI.
1.02 SUBSTITUTION PROCEDURES
A. SUBMIT REQUEST FOR SUBSTITUTION FOR CAUSE WITHIN 5 DAYS OF DISCOVERY OF NEED FOR SUBSTITUTION AND / OR PRIOR TO BID AWARD, BUT NOT LATER THAN 5 DAYS PRIOR TO TIME REQUIRED FOR
REVIEW AND APPROVAL BY ARCHITECT, IN ORDER TO STAY ON APPROVED PROJECT BID AND / OR CONSTRUCTION SCHEDULE.
B. DOCUMENT EACH REQUEST WITH COMPLETE DATA SUBSTANTIATING COMPLIANCE OF PROPOSED SUBSTITUTION WITH CONTRACT DOCUMENTS. BURDEN OF PROOF IS ON PROPOSER. INCLUDE:
1. REASON WHY THE SPECIFIED ITEM CANNOT BE PROVIDED.
2. DIFFERENCES BETWEEN PROPOSED SUBSTITUTION AND SPECIFIED ITEM.
3. WARRANTIES.
4. PRODUCT DATA/ DESCRIPTION, CERTIFICATES, TESTS OR SIMILAR QUALIFICATION DATA.
5. SAVINGS TO OWNER FOR ACCEPTING SUBSTITUTION WHETHER COST, LEAD TIME OR ENERGY CONSERVATION.
6. DOCUMENT MEANS OF COORDINATING OF SUBSTITUTION ITEM WITH OTHER PORTIONS OF THE WORK, INCLUDING WORK BY AFFECTED SUBCONTRACTORS.
7. CHANGE TO CONTRACT TIME DUE TO ACCEPTING SUBSTITUTION.
C. OWNER / ARCHITECT WILL NOTIFY CONTRACTOR IN WRITING OF DECISION TO ACCEPT OR REJECT REQUEST UPON OWNER’S / TENANT REVIEW ACCEPTANCE.
2.01 REQUESTS FOR INFORMATION (RFI)
A. WHENEVER POSSIBLE, COMBINE RFI AND ITS ATTACHMENTS INTO A SINGLE ELECTRONIC FILE. PDF FORMAT IS PREFERRED.
B. REASON FOR THE RFI: PRIOR TO INITIATION OF AN RFI, CAREFULLY STUDY ALL CONTRACT DOCUMENTS TO CONFIRM THAT INFORMATION SUFFICIENT FOR THEIR INTERPRETATION IS DEFINITELY NOT
INCLUDED IN RFI.
C. ARCHITECT RESERVES RIGHT TO RETURN RESPONSE UNANSWERED IF MISSING KEY INFORMATION REQUIRED TO RENDER AN ACTIONABLE RESPONSE OR REQUESTS REGARDING INFORMATION THAT IS
CLEARLY INDICATED ON, OR REASONABLY INFERRED FROM CONTRACT DOCUMENTS, WITH NO ADDITIONAL INPUT REQUIRED TO CLARIFY THE QUESTION.
D. CONTENT: INCLUDE IDENTIFIERS NECESSARY FOR TRACKING THE STATUS OF EACH RFI, AND INFORMATION NECESSARY TO PROVIDE AN ACTIONABLE RESPONSE. PROJECT NAME, CONTRACTOR'S NAME, CONSECUTIVE RFI NUMBER, AND DESCRIPTIVE SUBJECT/TITLE, ISSUE DATE AND REQUESTED REPLY DATE, DRAWING AND DETAIL NUMBER, FIELD DIMENSIONS AND / OR DESCRIPTION OF CONDITIONS WHICH
HAVE CAUSED THE REQUEST. INCLUDE SKETCHES, COORDINATION DRAWINGS, DESCRIPTIONS, PHOTOS, SUBMITTALS, AND OTHER INFORMATION NECESSARY TO SUBSTANTIATE THE REASON FOR THE
REQUEST.
E. CONTRACTOR'S SUGGESTED RESOLUTION: A WRITTEN AND / OR A GRAPHIC SOLUTION, IS REQUIRED IN CASES WHERE CLARIFICATION OF COORDINATION ISSUES IS INVOLVED. IF APPLICABLE, STATE THE
LIKELY IMPACT OF THE SUGGESTED RESOLUTION ON CONTRACT TIME OR THE CONTRACT SUM.
F. REVIEW TIME: ARCHITECT WILL RESPOND AND RETURN RFIS TO CONTRACTOR WITHIN THREE (3) TO FIVE (5) CALENDAR DAYS OF RECEIPT. FOR THE PURPOSE OF ESTABLISHING THE START OF THE MANDATED
RESPONSE PERIOD, RFIS RECEIVED AFTER 5:00 PM (FIVE O’CLOCK) WILL BE CONSIDERED AS HAVING BEEN RECEIVED ON THE FOLLOWING REGULAR WORKING DAY.
G. RESPONSES: CONTENT OF ANSWERED RFIS WILL NOT CONSTITUTE IN ANY MANNER A DIRECTIVE OR AUTHORIZATION TO PERFORM EXTRA WORK OR DELAY THE PROJECT. IF IN CONTRACTOR'S BELIEF IT IS
LIKELY TO LEAD TO A CHANGE TO CONTRACT SUM OR CONTRACT TIME, PROMPTLY ISSUE A NOTICE TO THIS EFFECT, AND FOLLOW UP WITH AN APPROPRIATE CHANGE ORDER REQUEST TO OWNER.
1. RESPONSE MAY INCLUDE A REQUEST FOR ADDITIONAL INFORMATION, IN WHICH CASE THE ORIGINAL RFI WILL BE DEEMED AS HAVING BEEN ANSWERED, AND AN AMENDED ONE IS TO BE ISSUED FORTHWITH.
IDENTIFY THE AMENDED RFI WITH AN R SUFFIX TO THE ORIGINAL NUMBER.
2. DO NOT EXTEND APPLICABILITY OF A RESPONSE TO SPECIFIC ITEM TO ENCOMPASS OTHER SIMILAR CONDITIONS, UNLESS SPECIFICALLY SO NOTED IN THE RESPONSE.
3. NOTIFY ARCHITECT WITHIN THREE (3) CALENDAR DAYS IF AN ADDITIONAL OR CORRECTED RESPONSE IS REQUIRED BY SUBMITTING AN AMENDED VERSION OF THE ORIGINAL RFI, IDENTIFIED AS SPECIFIED
ABOVE.
3.01 SUBMITTAL SCHEDULE
A. SUBMIT TO OWNER / ARCHITECT FOR REVIEW A SCHEDULE FOR SUBMITTALS IN TABULAR FORMAT, NUMBER, TITLE, CATEGORY, DATE SUBMITTED TO ARCHITECT AND ARCHITECT RESPONSE DUE DATE.
B. FOR ASSEMBLIES, EQUIPMENT, SYSTEMS COMPRISED OF MULTIPLE COMPONENTS AND / OR REQUIRING DETAILED COORDINATION WITH OTHER WORK, ALLOW FOR ADDITIONAL TIME TO MAKE CORRECTIONS
OR REVISIONS TO INITIAL SUBMITTALS, AND TIME FOR THEIR REVIEW.
C. FOR EACH SUBMITTAL FOR REVIEW, ALLOW FIVE (5) TO SEVEN (7) DAYS EXCLUDING DELIVERY TIME TO AND FROM THE CONTRACTOR. FOR SEQUENTIAL REVIEWS INVOLVING ARCHITECT'S CONSULTANTS, OWNER, OR ANOTHER AFFECTED PARTY, ALLOW AN ADDITIONAL TWO (2) DAYS. FOR SEQUENTIAL REVIEWS INVOLVING APPROVAL FROM AUTHORITIES HAVING JURISDICTION (AHJ), IN ADDITION TO
ARCHITECT'S APPROVAL, ALLOW AN ADDITIONAL 30 DAYS.
3.02 SUBMITTAL PROCEDURES
A. SUBMIT ELECTRONIC PDF FORMAT TO ARCHITECT FOR REVIEW FOR THE LIMITED PURPOSE OF CHECKING FOR COMPLIANCE WITH INFORMATION GIVEN AND THE DESIGN CONCEPT -AESTHETIC, COLOR, OR
FINISH SELECTION -EXPRESSED IN CONTRACT DOCUMENTS. INCLUDE PRODUCT DATA, CERTIFICATES/TEST REPORTS, MANUFACTURER’S INSTRUCTIONS, SHOP DRAWINGS, AND THREE (3) HARD COPY SAMPLES
FOR VERIFICATION.
B. USE A SINGLE TRANSMITTAL FOR RELATED ITEMS; SEQUENTIALLY IDENTIFY EACH ITEM. IDENTIFY PROJECT; CONTRACTOR; SUBCONTRACTOR OR SUPPLIER; PERTINENT DRAWING AND DETAIL NUMBER; AND
CSI SPECIFICATION SECTION NUMBER AND ARTICLE/PARAGRAPH, AS APPROPRIATE ON EACH COPY.
C. APPLY CONTRACTOR'S STAMP, SIGNED OR INITIALED CERTIFYING THAT REVIEW, APPROVAL, VERIFICATION OF PRODUCTS REQUIRED, FIELD DIMENSIONS, ADJACENT CONSTRUCTION WORK, AND
COORDINATION OF INFORMATION IS IN ACCORDANCE WITH THE REQUIREMENTS OF THE WORK AND CONTRACT DOCUMENTS.
D. CONTRACTOR TO SUBMIT RFI PRIOR TO SUBMITTING PRODUCT SUBMITTAL WHEN VARIATIONS FROM CONTRACT DOCUMENTS AND PRODUCT OR SYSTEM LIMITATIONS THAT MAY BE DETRIMENTAL TO
SUCCESSFUL PERFORMANCE OF THE COMPLETED WORK. PROVIDE SPACE FOR CONTRACTOR AND ARCHITECT REVIEW STAMPS. WHEN REVISED FOR RESUBMISSION, IDENTIFY ALL CHANGES MADE SINCE
PREVIOUS SUBMISSION.
E. SUBMIT ONLY INFORMATION REQUIRED BY INDIVIDUAL SPECIFICATION SECTIONS, COLLECT REQUIRED INFORMATION INTO A SINGLE SUBMITTAL, SUBMIT CONCURRENTLY WITH RELATED SHOP DRAWING
SUBMITTAL AND DO NOT SUBMIT (MATERIAL) SAFETY DATA SHEETS FOR MATERIALS OR PRODUCTS.
F. SHOP DRAWING PROCEDURES: PREPARE ACCURATE, DRAWN-TO-SCALE, ORIGINAL SHOP DRAWING DOCUMENTATION BY INTERPRETING CONTRACT DOCUMENTS AND COORDINATING RELATED WORK. DO NOT
REPRODUCE CONTRACT DOCUMENTS TO CREATE SHOP DRAWINGS.
G. SAMPLES PROCEDURES: TRANSMIT RELATED ITEMS TOGETHER AS SINGLE PACKAGE. IDENTIFY EACH ITEM TO ALLOW REVIEW FOR APPLICABILITY IN RELATION TO SHOP DRAWINGS SHOWING INSTALLATION
LOCATIONS AND INCLUDE WITH TRANSMITTAL HIGH-RESOLUTION IMAGE FILES OF SAMPLES TO FACILITATE ELECTRONIC REVIEW AND APPROVAL ALONG WITH PHYSICAL SAMPLES.
3.03 SUBMITTAL REVIEW
A. SUBMITTALS FOR REVIEW: ARCHITECT WILL REVIEW EACH SUBMITTAL AND TAKE APPROPRIATE ACTION PER BELOW.
B. ARCHITECT'S ACTIONS WILL BE REFLECTED BY MARKING EACH RETURNED SUBMITTAL USING VIRTUAL STAMP ON ELECTRONIC SUBMITTALS. NOTATIONS MAY BE MADE DIRECTLY ON SUBMITTED ITEMS AND /
OR LISTED ON APPENDED SUBMITTAL REVIEW COVER SHEET.
C. ARCHITECT'S AND CONSULTANTS' ACTIONS ON ITEMS SUBMITTED FOR REVIEW:
1. "REVIEWED", OR LANGUAGE WITH SAME LEGAL MEANING.
2. "MAKE CORRECTIONS NOTED", OR LANGUAGE WITH SAME LEGAL MEANING
AT CONTRACTOR'S OPTION, SUBMIT CORRECTED ITEM, WITH REVIEW NOTATIONS ACKNOWLEDGED AND INCORPORATED.
3. "REVISE AND RESUBMIT"
A. RESUBMIT REVISED ITEM, WITH REVIEW NOTATIONS ACKNOWLEDGED AND INCORPORATED.
B. NON-RESPONSIVE RESUBMITTALS MAY BE REJECTED.
4. "SUBMIT SPECIFIED ITEMS"
SUBMITTAL WAS NON-COMPLIANT WITH PRODUCT OR INTENT OF CONTRACT DOCUMENTS SCOPE.
5. "REJECTED"
SUBMIT ITEM COMPLYING WITH REQUIREMENTS OF CONTRACT DOCUMENTS.
SECTION 013000 - ADMINISTRATIVE REQUIREMENTS
1.01 EXISTING PRODUCTS
A. DO NOT USE MATERIALS AND EQUIPMENT REMOVED FROM EXISTING PREMISES UNLESS SPECIFICALLY REQUIRED OR PERMITTED BY CONTRACT DOCUMENTS. SEE DEMOLITION SECTION 024100 FOR FURTHER
CRITERIA.
B. EXISTING PRODUCT AS NOTED ON CONTRACT DOCUMENTS TO BE REUSED WILL BE SURVEYED BY CONTRACTOR AND SUBCONTRACTOR FOR PRODUCT INTEGRITY AND APPLICATION. SITE PRODUCT TO BE
PROTECTED, REFINISHED, REPAIRED TO “LIKE NEW” APPEARANCE AND INCLUDED IN BID SCOPE.
C. IF CONTRACTOR AND SUB-CONTRACTOR DETERMINE THAT THE PRODUCT OR INSTALLATION IS NOT USEABLE, NOTIFY OWNER / ARCHITECT THROUGH RFI PROCESS FOR DIRECTION.
1.02 NEW PRODUCTS
A. PROVIDE NEW PRODUCTS UNLESS SPECIFICALLY REQUIRED OR PERMITTED BY CONTRACT DOCUMENTS.
B. USE OF PRODUCTS HAVING ANY OF THE FOLLOWING CHARACTERISTICS IS NOT PERMITTED: MADE USING OR CONTAINING CFC'S OR HCFC'S, MADE OF WOOD FROM NEWLY CUT OLD GROWTH TIMBER, CONTAINING LEAD, CADMIUM OR ASBESTOS. SOME PRODUCTS MAY BE REQUIRED TO MEET MORE STRINGENT ENVIRONMENTAL CODES, BASED ON PROJECT SCOPE IN CONTRACT DOCUMENTS.
C. INDOOR-EMISSIONS-RESTRICTED PRODUCTS: COMPLY WITH INDOOR EMISSIONS STANDARD AND TEST METHOD PER FEDERAL, STATE AND /OR LOCAL REQUIREMENTS, EXCEPT FOR:
1. COMPOSITE WOOD, WOOD FIBER, AND WOOD CHIP PRODUCTS: COMPLY WITH COMPOSITE WOOD EMISSIONS STANDARD OR CONTAIN NO ADDED FORMALDEHYDE RESINS.
2. INHERENTLY NON-EMITTING MATERIALS.
D. VOC-CONTENT-RESTRICTED PRODUCTS INCLUDE BUT NOT LIMITED TO ADHESIVES, INCLUDING FLOORING ADHESIVES, JOINT SEALANTS/CAULK, PAINTS AND COATINGS, CARPET AND RESILIENT FLOORING
SYSTEMS AS MANDATED BY LOCAL, STATE AND FEDERAL REQUIREMENTS.
1.03 OWNER / TENANT-SUPPLIED PRODUCTS
A. SEE CONTRACT DOCUMENTS FOR OWNER / TENANT SUPPLIED PRODUCTS / EQUIPMENT, WHERE REQUIRED.
B. OWNER / TENANT'S RESPONSIBILITIES, IF NOT SPECIFICALLY CALLED OUT ON CONTRACT DOCUMENTS, PROVIDE THE FOLLOWING SCOPE: ARRANGE FOR AND DELIVER OWNER / TENANT REVIEWED SHOP
DRAWINGS, PRODUCT DATA, AND SAMPLES, TO CONTRACTOR. ARRANGE AND PAY FOR PRODUCT DELIVERY TO SITE. ON DELIVERY, INSPECT PRODUCTS JOINTLY WITH CONTRACTOR. SUBMIT CLAIMS FOR
TRANSPORTATION DAMAGE AND REPLACE DAMAGED, DEFECTIVE, OR DEFICIENT ITEMS. ARRANGE FOR MANUFACTURERS' WARRANTIES, INSPECTIONS, AND SERVICE.
C. CONTRACTOR'S RESPONSIBILITIES, IF NOT SPECIFICALLY CALLED OUT ON CONTRACT DOCUMENTS, PROVIDE THE FOLLOWING SCOPE: REVIEW OWNER / TENANT REVIEWED SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. RECEIVE AND UNLOAD PRODUCTS AT SITE; INSPECT FOR COMPLETENESS OR DAMAGE JOINTLY WITH OWNER. HANDLE, STORE, INSTALL AND FINISH PRODUCTS. REPAIR OR REPLACE ITEMS
DAMAGED AFTER RECEIPT.
2.01 EXAMINATION
A. VERIFY THAT EXISTING SITE CONDITIONS, [OPENINGS, BACKING, PREP WORK AND SUBSTRATE SURFACES] ARE ACCEPTABLE FOR SUBSEQUENT WORK. START OF WORK MEANS ACCEPTANCE OF EXISTING
CONDITIONS.
B. VERIFY THAT EXISTING SUBSTRATE IS CAPABLE OF STRUCTURAL SUPPORT OR ATTACHMENT OF NEW WORK BEING APPLIED OR ATTACHED.
C. TAKE FIELD MEASUREMENTS BEFORE CONFIRMING PRODUCT ORDERS OR BEGINNING FABRICATION, TO MINIMIZE WASTE DUE TO OVER-ORDERING OR MIS FABRICATION.
D. PRIOR TO CUTTING: EXAMINE EXISTING CONDITIONS PRIOR TO COMMENCING WORK, INCLUDING ELEMENTS SUBJECT TO DAMAGE OR MOVEMENT DURING CUTTING AND PATCHING. AFTER UNCOVERING
EXISTING WORK, ASSESS CONDITIONS AFFECTING PERFORMANCE OF WORK. BEGINNING OF CUTTING OR PATCHING MEANS ACCEPTANCE OF EXISTING CONDITIONS.
2.02 PREPARATION
A. PREPARE SURFACES IN ACCORDANCE WITH MANUFACTURER'S INSTRUCTIONS.
B. CLEAN SUBSTRATE SURFACES PRIOR TO APPLYING NEXT MATERIAL OR SUBSTANCE.
C. SEAL CRACKS OR OPENINGS OF SUBSTRATE PRIOR TO APPLYING NEXT MATERIAL OR SUBSTANCE.
D. APPLY MANUFACTURER REQUIRED OR RECOMMENDED SUBSTRATE PRIMER, SEALER, OR CONDITIONER PRIOR TO APPLYING ANY NEW MATERIAL OR SUBSTANCE IN CONTACT OR BOND.
2.03 TRANSPORTATION AND HANDLING
A. TRANSPORT AND HANDLE NEW PRODUCTS IN ACCORDANCE WITH MANUFACTURER'S INSTRUCTIONS. PROMPTLY INSPECT SHIPMENTS TO ENSURE THAT PRODUCTS COMPLY WITH REQUIREMENTS, QUANTITIES
ARE CORRECT, AND PRODUCTS ARE UNDAMAGED. ARRANGE FOR THE RETURN OF PACKING MATERIALS, SUCH AS WOOD PALLETS, WHERE ECONOMICALLY FEASIBLE.
2.04 STORAGE AND PROTECTION
A. PROVIDE PROTECTION, IN ACCORDANCE WITH MANUFACTURER’S INSTRUCTIONS AND WARRANTIES, OF STORED MATERIALS AND PRODUCTS AGAINST CONSTRUCTION OPERATIONS, DUST, THEFT, CASUALTY, MOISTURE, CORROSION, DISCOLORATION, STAINING, OR DETERIORATION. DO NOT STORE DIRECTLY ON THE GROUND.
B. BASED ON PROJECT SCOPE AND AGENCY REGULATIONS LISTED IN CONTRACT DOCUMENTS, CONFIRM IF ANY ADDITIONAL STORAGE AND PROTECTION ENVIRONMENTAL REQUIREMENTS MAYBE REQUIRED.
2.05 GENERAL INSTALLATION REQUIREMENTS
A. IN ADDITION TO COMPLIANCE WITH REGULATORY REQUIREMENTS, CONDUCT CONSTRUCTION OPERATIONS IN COMPLIANCE WITH NFPA 241, INCLUDING APPLICABLE RECOMMENDATIONS IN APPENDIX A.
B. INSTALL PRODUCTS AS SPECIFIED IN INDIVIDUAL SECTIONS, IN ACCORDANCE WITH MANUFACTURER'S INSTRUCTIONS AND RECOMMENDATIONS, AND SO AS TO AVOID WASTE DUE TO NECESSITY FOR
REPLACEMENT.
C. MAKE VERTICAL ELEMENTS PLUMB AND HORIZONTAL ELEMENTS LEVEL, UNO.
D. INSTALL EQUIPMENT AND FITTINGS PLUMB AND LEVEL, NEATLY ALIGNED WITH ADJACENT VERTICAL AND HORIZONTAL LINES, UNLESS OTHERWISE INDICATED.
E. INSTALL PRODUCTS IN AMBIENT TEMPERATURES, ACCORDING TO MANUFACTURER’S REQUIREMENTS.
F. DO NOT INSTALL SOLVENT BASED PRODUCTS IN AN UNVENTILATED ENVIRONMENT.
SECTION 016000 - PRODUCT REQUIREMENTS
1.01 GENERAL
A. IN THE EVENT OF CONFLICT BETWEEN THE CONTRACT FOR CONSTRUCTION (AGREEMENT, GENERAL AND SUPPLEMENTAL CONDITIONS) AND REQUIREMENTS HEREIN, THE CONTRACT FOR CONSTRUCTION WILL
GOVERN.
B. ALL WORK PERFORMED BY THE CONTRACTOR AND THEIR SUBTRADES, SHALL CONFORM TO THE REQUIREMENTS OF MUNICIPAL, LOCAL, FEDERAL AND STATE LAWS, AS WELL AS OTHER GOVERNING
REQUIREMENTS, WHETHER OR NOT SPECIFIED ON THE DRAWINGS.
C. ALL DRAWINGS AND CONSTRUCTION NOTES ARE COMPLEMENTARY, AND WHAT IS CALLED FOR BY EITHER, WILL BE BINDING AS IF CALLED FOR BY ALL, INCLUDING ENGINEERING DISCIPLINES. ANY WORK
SHOWN OR REFERRED TO ON ANY ONE SET OF DRAWINGS, SHALL BE PROVIDED AS THOUGH SHOWN ON ALL RELATED DRAWINGS.
D. THE CONTRACTOR SHALL NOTIFY OWNER / ARCHITECT IMMEDIATELY OF DISCREPANCIES OR OMISSIONS BETWEEN THE DRAWINGS, GENERAL NOTES HEREIN, AND FIELD CONDITIONS BEFORE COMMENCING
ANY WORK AND REQUEST FOR CLARIFICATION.
E. EACH CONTRACTOR AND SUBTRADE SHALL CHECK AND VERIFY ALL DIMENSIONS AND CONDITIONS AT JOB SITE AS IT RELATES TO THEIR WORK AND NOTIFY THE ARCHITECT VIA RFI. IF THERE ARE
OBSTRUCTIONS, AND WORK THAT CANNOT BE ACCOMPLISHED, AS REFLECTED IN THE CONTRACT DOCUMENTS. CONTRACTOR/SUBTRADE SHALL OBTAIN CLARIFICATION/DIRECTIVE FROM THE ARCHITECT
PRIOR TO THE START OF ANY WORK.
F. THE CONTRACTOR AND THE SUBTRADES SHALL SUBMIT A LIST OF LONG LEAD ITEMS WITHIN THE FIRST TWO WEEKS THAT PREVENT COMPLETION OF THE PROJECT AT MOVE-IN DATE. PROPOSE AN AVAILABLE
SUBSTITUTION, INCLUDING COST PER SUBSTITUTION PROCEDURES 013000 FOR APPROVAL BY OWNER / ARCHITECT.
G. THE USE OF THE WORDS “PROVIDE” OR “PROVIDED” IN CONNECTION WITH ANY ITEM SPECIFIED, IS INTENDED TO MEAN, UNO, THAT WHICH SHALL BE FURNISHED, INSTALLED AND CONNECTED WHERE SO
REQUIRED.
H. THE CONTRACTOR SHALL MAINTAIN A COMPLETE AND CURRENT SET OF CONTRACT DOCUMENTS ON THE SITE DURING ALL PHASES OF CONSTRUCTION FOR USE OF ALL TRADES AND OWNER / ARCHITECT
DURING FIELD SITE WALK.
I. THE CONTRACTOR SHALL VERIFY SIZE, ELECTRICAL REQUIREMENTS, LOCATION AND CHARACTERISTICS OF ALL WORK AND / OR EQUIPMENT SUPPLIED BY THE OWNER OR TENANT, WITH THE MANUFACTURER
OR SUPPLIER PRIOR TO THE START OF RELATED WORK.
1.02 PROJECT CONDITIONS
A. VENTILATE ENCLOSED AREAS TO ASSIST CURE OF MATERIALS, TO DISSIPATE HUMIDITY, AND TO PREVENT ACCUMULATION OF DUST, FUMES, VAPORS, OR GASES.
B. DUST CONTROL: PROVIDE A DUST PROOF BARRIER (S) BETWEEN CONSTRUCTION AREAS AND AREAS CONTINUING TO BE OCCUPIED BY TENANT TO PREVENT AIR-BORNE DUST FROM DISPERSING INTO
INTERIOR ATMOSPHERE.
C. NOISE CONTROL: MINIMIZE NOISE PRODUCED BY CONSTRUCTION OPERATIONS. EXCESSIVELY NOISY TOOLS AND OPERATIONS WILL NOT BE TOLERATED INSIDE THE BUILDING AT ANY TIME OF DAY; INCLUDES
JACKHAMMERS. COORDINATE AFTER HOURS APPROVAL WITH OWNER/ PROPERTY MANAGER. COORDINATE WITH LANDLORD BUILDING RULES / REGULATIONS.
D. POLLUTION CONTROL: PROVIDE METHODS, MEANS, AND FACILITIES TO PREVENT CONTAMINATION OF WATER AND ATMOSPHERE FROM DISCHARGE OF NOXIOUS, TOXIC SUBSTANCES, AND POLLUTANTS
PRODUCED BY CONSTRUCTION OPERATIONS. COMPLY WITH FEDERAL, STATE, AND LOCAL REGULATIONS.
E. DISPOSAL REGULATORY REQUIREMENTS: CONTRACTOR IS RESPONSIBLE FOR KNOWING AND COMPLYING WITH REGULATORY REQUIREMENTS, INCLUDING BUT NOT LIMITED TO FEDERAL, STATE AND LOCAL
REQUIREMENTS, PERTAINING TO LEGAL DISPOSAL OF ALL CONSTRUCTION AND DEMOLITION WASTE MATERIALS.
F. JOB SITE SAFETY : THESE PLANS AND SPECIFICATIONS DO NOT PROVIDE ANY DIRECTION OR INSTRUCTIONS TO THE CONTRACTOR OR SUBCONTRACTORS OR THEIR EMPLOYEES OR AGENTS RELATED TO
CONSTRUCTION MEANS, METHODS, TECHNIQUES, SEQUENCES OR PROCEDURES, OR FOR SAFETY PRECAUTIONS INCLUDING JOB SITE SAFETY AND PROGRAMS IN CONNECTION WITH THE WORK. THIS IS
SOLELY THE CONTRACTOR'S RESPONSIBILITY UNDER THE CONTRACTOR’S CONTRACT FOR CONSTRUCTION. THE ARCHITECT HAS NOT CONDUCTED AN EVALUATION OF SAFETY PROCEDURES FOR THE
PROPER MANNER OF ACCESSING THE JOB SITE DURING THE COURSE OF CONSTRUCTION AND HAS NOT UNDERTAKEN ANY RESPONSIBILITY ON WHETHER OR NOT THE USE OF EXISTING LADDERS, DOORS, RAILINGS, INGRESS AND INGRESS ROUTES OR THE LIKE ARE IN COMPLIANCE WITH OSHA REQUIREMENTS DURING THE COURSE OF CONSTRUCTION OF THE IMPROVEMENTS.
1.03 COORDINATION
A. COORDINATE SCHEDULING, SUBMITTALS, AND WORK OF THE VARIOUS SECTIONS OF THE PROJECT SPECIFICATIONS TO ENSURE EFFICIENT AND ORDERLY SEQUENCE OF INSTALLATION OF INTERDEPENDENT
CONSTRUCTION ELEMENTS, WITH PROVISIONS FOR ACCOMMODATING ITEMS INSTALLED LATER.
B. NOTIFY AFFECTED UTILITY COMPANIES WHEN APPLICABLE AND COMPLY WITH THEIR REQUIREMENTS.
C. VERIFY THAT UTILITY REQUIREMENTS AND CHARACTERISTICS OF NEW OPERATING EQUIPMENT ARE COMPATIBLE WITH BUILDING UTILITIES. COORDINATE WORK OF VARIOUS SECTIONS HAVING
INTERDEPENDENT RESPONSIBILITIES FOR INSTALLING, CONNECTING TO, AND PLACING IN SERVICE, SUCH EQUIPMENT.
D. COORDINATE SPACE REQUIREMENTS, SUPPORTS, AND INSTALLATION OF MECHANICAL, PLUMBING, AND ELECTRICAL WORK THAT ARE INDICATED DIAGRAMMATICALLY ON DRAWINGS. FOLLOW ROUTING
INDICATED FOR PIPES, DUCTS, AND CONDUIT, AS CLOSELY AS PRACTICABLE. UTILIZE SPACES EFFICIENTLY TO MAXIMIZE ACCESSIBILITY FOR OTHER INSTALLATIONS, FOR MAINTENANCE, AND FOR REPAIRS.
E. COORDINATE LOCATIONS OF FIXTURES AND OUTLETS WITH FINISH ELEMENTS. IN FINISHED AREAS EXCEPT AS OTHERWISE INDICATED, CONCEAL PIPES, DUCTS, AND WIRING WITHIN THE CONSTRUCTION.
F. COORDINATE COMPLETION AND CLEAN-UP OF WORK OF SEPARATE SECTIONS.
G. AFTER OCCUPANCY OF PREMISES, COORDINATE ACCESS TO SITE FOR CORRECTION OF DEFECTIVE WORK AND WORK NOT IN ACCORDANCE WITH CONTRACT DOCUMENTS, TO MINIMIZE DISRUPTION OF
OCCUPANT ACTIVITIES.
2.01 ALTERATIONS
A. FOR DEMOLITION, REFER TO SECTION 024100.
1. WHERE NEW SURFACE FINISHES ARE TO BE APPLIED TO EXISTING WORK, PERFORM REMOVALS, PATCH, AND PREPARE EXISTING SURFACES AS REQUIRED TO RECEIVE NEW FINISH; REMOVE EXISTING
FINISH IF NECESSARY, FOR SUCCESSFUL APPLICATION OF NEW FINISH.
B. SERVICES (INCLUDING BUT NOT LIMITED TO HVAC, PLUMBING, FIRE PROTECTION, ELECTRICAL AND TELECOMMUNICATIONS, WHERE OCCURS AND AS NOTED ON CONTRACT DOCUMENTS OR OWNER RFP
DIRECTION): REMOVE, RELOCATE, AND EXTEND EXISTING SYSTEMS TO ACCOMMODATE NEW CONSTRUCTION.
1. MAINTAIN EXISTING ACTIVE SYSTEMS THAT ARE TO REMAIN IN OPERATION; MAINTAIN ACCESS TO EQUIPMENT AND OPERATIONAL COMPONENTS; IF NECESSARY, MODIFY INSTALLATION TO ALLOW ACCESS
OR PROVIDE ACCESS PANEL. COORDINATE LOCATIONS SIZE AND TYPE OF ACCESS PANEL WITH ARCHITECT PRIOR TO INSTALLATION.
2. WHERE EXISTING ACTIVE SYSTEMS SERVE OCCUPIED FACILITIES BUT ARE TO BE REPLACED WITH NEW SERVICES, MAINTAIN EXISTING SYSTEMS IN SERVICE UNTIL NEW SYSTEMS ARE COMPLETE AND
READY FOR SERVICE. MINIMIZE DURATION OF OUTAGES AND PROVIDE TEMPORARY CONNECTIONS TO MAINTAIN SERVICE WHERE REQUIRED.
3. VERIFY THAT ABANDONED SERVICES SERVE ONLY ABANDONED FACILITIES. REQUEST DIRECTION THROUGH RFI PROCESS.
C. PROTECT EXISTING WORK TO REMAIN. IF NOT SECURE, PROVIDE SHORING/BRACING. REPAIR ADJACENT CONSTRUCTION AND FINISHES DAMAGED DURING REMOVAL WORK.
D. ANY NEW REPAIR WORK OR ANY EXISTING SCOPE TO REMAIN THAT IS DISCOVERED TO BE NON CODE COMPLIANT, SHALL BE BROUGHT TO ARCHITECT/ENGINEER/CLIENTS ATTENTION TO RENDER A DECISION
ON WHETHER UPGRADE IS REQUIRED TO LATEST CODE COMPLIANCE
E. ADAPT EXISTING WORK TO FIT NEW WORK: MAKE AS NEAT AND SMOOTH OF A TRANSITION AS POSSIBLE.
SECTION 017000 - EXECUTION AND CLOSEOUT REQUIREMENTS
SECTION 024100 - DEMOLITION
1.01 SELECTIVE DEMOLITION FOR ALTERATIONS
A. EXISTING MATERIALS AND EQUIPMENT INDICATED TO BE REMOVED, BUT NOT TO BE RE-USED, RELOCATED, REINSTALLED, DELIVERED TO THE OWNER, OR OTHERWISE INDICATED AS TO REMAIN THE
PROPERTY OF THE OWNER, BECOME THE PROPERTY OF THE CONTRACTOR; REMOVE FROM SITE.
B. REMOVE/ RELOCATE EXISTING WORK AS INDICATED AND AS REQUIRED TO ACCOMPLISH NEW WORK PER DOCUMENTS.
C. PROTECT EXISTING WORK TO REMAIN. PREVENT MOVEMENT OF STRUCTURE; PROVIDE SHORING AND BRACING IF NECESSARY. PERFORM CUTTING TO ACCOMPLISH REMOVALS NEATLY AND AS SPECIFIED
FOR CUTTING NEW WORK.
D. DRAWINGS SHOWING EXISTING CONSTRUCTION AND UTILITIES COULD BE BASED ON, IF AVAILABLE, CASUAL FIELD OBSERVATION, AUDITS AND / OR EXISTING RECORD DOCUMENTS.
1. VERIFY THAT CONSTRUCTION AND UTILITY ARRANGEMENTS ARE AS INDICATED.
2. REPORT DISCREPANCIES TO OWNER / ARCHITECT BEFORE DISTURBING EXISTING INSTALLATION.
3. BEGINNING OF DEMOLITION WORK CONSTITUTES ACCEPTANCE OF EXISTING CONDITIONS THAT WOULD BE APPARENT UPON EXAMINATION PRIOR TO STARTING DEMOLITION.
E. SEPARATE AREAS IN WHICH DEMOLITION IS BEING CONDUCTED FROM OTHER AREAS THAT ARE STILL OCCUPIED BY PROVIDING AND MAINTAINING A TEMPORARY DUSTPROOF PARTITION OR BARRIER AS
DETERMINED BY OWNER / TENANT.
F. WHEN APPLICABLE PER SCOPE, MAINTAIN WEATHERPROOF EXTERIOR BUILDING ENCLOSURE EXCEPT FOR INTERRUPTIONS REQUIRED FOR REPLACEMENT OR MODIFICATIONS; TAKE CARE TO PREVENT
WATER AND HUMIDITY DAMAGE.
G. IF ROTTED WOOD, DETERIORATED MASONRY/CONCRETE OR DEFECTIVE, NON-CODE COMPLIANT CONDITIONS ARE OBSERVED IN THE FIELD BY CONTRACTOR AND /OR SUBTRADES, NOTIFY OWNER /
ARCHITECT PRIOR TO REMOVING FOR DIRECTION.
H. IF HAZARDOUS MATERIALS ARE DISCOVERED DURING REMOVAL OPERATIONS, STOP WORK AND NOTIFY OWNER / ARCHITECT; HAZARDOUS MATERIALS INCLUDE REGULATED ASBESTOS CONTAINING
MATERIALS, LEAD, PCB'S, AND MERCURY.
1.02 SERVICES
A. SERVICES (INCLUDING BUT NOT LIMITED TO HVAC, PLUMBING, FIRE PROTECTION, ELECTRICAL AND TELECOMMUNICATIONS, WHERE OCCURS AND AS NOTED ON CONTRACT DOCUMENTS OR OWNER RFP
DIRECTION): REMOVE EXISTING SYSTEMS AND EQUIPMENT AS INDICATED.
B. MAINTAIN EXISTING ACTIVE SYSTEMS THAT ARE TO REMAIN IN OPERATION; MAINTAIN ACCESS TO EQUIPMENT AND OPERATIONAL COMPONENTS.
C. WHERE EXISTING ACTIVE SYSTEMS SERVE OCCUPIED FACILITIES BUT ARE TO BE REPLACED WITH NEW SERVICES, MAINTAIN EXISTING SYSTEMS IN SERVICE UNTIL NEW SYSTEMS ARE COMPLETE AND READY
FOR SERVICE.
D. VERIFY THAT ABANDONED SERVICES SERVE ONLY ABANDONED FACILITIES BEFORE REMOVAL.
E. REMOVE ABANDONED PIPE, DUCTS, CONDUITS, AND EQUIPMENT, INCLUDING THOSE ABOVE DEMOLISHED ACCESSIBLE CEILINGS; REMOVE BACK TO SOURCE OF SUPPLY WHERE POSSIBLE, OTHERWISE CAP
STUB AND TAG WITH IDENTIFICATION, EXCEPT WHERE NOTED ON CONTRACT DOCUMENTS.
1.03 EXISTING UTILITIES
A. PROTECT EXISTING UTILITIES TO REMAIN FROM DAMAGE.
B. DO NOT DISRUPT PUBLIC UTILITIES WITHOUT PERMIT FROM AUTHORITY HAVING JURISDICTION (AHJ).
C. DO NOT CLOSE, SHUT OFF, OR DISRUPT EXISTING UTILITY AND /OR LIFE SAFETY SYSTEMS THAT ARE IN USE WITHOUT AT LEAST 3 DAYS PRIOR WRITTEN NOTIFICATION TO OWNER.
D. PREPARE BUILDING DEMOLITION AREAS BY DISCONNECTING AND CAPPING UTILITIES OUTSIDE THE DEMOLITION ZONE; IDENTIFY AND MARK UTILITIES TO BE SUBSEQUENTLY RECONNECTED, IN SAME MANNER
AS OTHER UTILITIES TO REMAIN.
1.04 DEBRIS AND WASTE REMOVAL
A. REGULATORY REQUIREMENTS: CONTRACTOR IS RESPONSIBLE FOR KNOWING AND COMPLYING WITH REGULATORY REQUIREMENTS, INCLUDING BUT NOT LIMITED TO FEDERAL, STATE AND LOCAL
REQUIREMENTS, PERTAINING TO LEGAL DISPOSAL OF ALL CONSTRUCTION AND DEMOLITION WASTE MATERIALS.
B. REMOVE DEBRIS, JUNK, TRASH, AND ALL MATERIALS NOT TO BE REUSED ONSITE; DO NOT BURN OR BURY.
C. LEAVE SITE IN CLEAN CONDITION, READY FOR SUBSEQUENT WORK.
D. SOME DEMOLITION PROCESSES AND PRODUCTS MAY BE REQUIRED TO MEET MORE STRINGENT ENVIRONMENTAL CODES, BASED ON PROJECT SCOPE IN CONSTRUCTION DOCUMENTS.
SECTION 064100 - ARCHITECTURAL CASEWORK
1.01 REFERENCE STANDARDS / QUALITY ASSURANCE
PROVIDE AND INSTALL CASEWORK PER THE FOLLOWING INDUSTRY STANDARDS:
A. AWMAC / WI / WI (NAAWS) - NORTH AMERICAN ARCHITECTURAL WOODWORK STANDARDS, U.S. VERSION 3.1 2016, WITH ERRATA (2017).
B. BHMA / ANSI A156.9 – MANUFACTURERS ASSOCIATION/AMERICAN NATIONAL STANDARD FOR CABINET HARDWARE 2015.
C. HPVA HP-1 - AMERICAN NATIONAL STANDARD FOR HARDWOOD AND DECORATIVE PLYWOOD 2016.
D. NEMA LD 3 - HIGH-PRESSURE DECORATIVE LAMINATES (HPDL) 2005.
E. ANSI A208.1 AMERICAN NATIONAL STANDARD FOR MEDIUM DENSITY FIBERBOARD.
F. CPA / ANSI A135.4 – COMPOSITE PANEL ASSOCIATION/AMERICAN NATIONAL STANDARD INSTITUTE BASIC HARDBOARD PRODUCT.
G. HVPA / ANSI – HP-1-2000- AMERICAN STANDARD FOR HARDWOOD AND DECORATIVE PLYWOOD.
H. ASTM INTERNATIONAL (ASTM): D 1037-12 – TEST METHOD FOR EVALUATING THE PROPERTIES OF WOOD-BASE FIBER AND PARTICLE PANEL MATERIALS.
2.01 CABINETS
A. QUALITY STANDARD: CUSTOM GRADE, IN ACCORDANCE WITH AWMAC / WI / WI (NAAWS), UNO. CONFIGURATION AS SHOWN ON CONTRACT DOCUMENT ELEVATION VIEWS.
B. CONSTRUCTION: UNO, PROVIDE TYPE A- FRAMELESS STYLE 1 FLUSH OVERLAY, UNO ON CONTRACT DOCUMENTS.
C. CORE AND SUBSTRATES: MEDIUM DENSITY FIBERBOARD: ANSI A208.2 GRADE MDF. PHYSICAL PROPERTIES CONFORM TO ASTM D 1037 PART A 3 / 4 ” THICKNESS UNO. CONCEALED AREAS BACKER SHEETS
CONFORM TO NEMA TYPE BKM (0.039 INCH NOMINAL THICKNESS WITH NO DECORATIVE FACE, FOR USE AS A BALANCING SHEET AT CONCEALED SURFACES ONLY). CABINET LINER: LOW PRESSURE
DECORATIVE LAMINATE MATERIAL INTENDED FOR USE IN CABINET INTERIORS EQUAL TO KORTRON, MELAMINE OR POLYESTER OVERLAY.
D. COUNTERTOP SUBSTRATE AT WET AREAS: NON-FIRE-RETARDANT TYPE: MOISTURE RESISTANT PARTICLE BOARD, ANSI 208.1, GRADE M-3 (EXTERIOR GLUE) MR-10, COMPOSED OF WOOD CHIPS MATRIX BOUND
WITH HIGH MOISTURE RESISTANT UREA-FREE RESIN BINDERS PER ASTM D 1037.
E. THERMOSET DECORATIVE PANELS (HPDL): PARTICLEBOARD OR MEDIUM-DENSITY FIBERBOARD FINISHED WITH THERMALLY FUSED, MELAMINE-IMPREGNATED…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .