Turbidity_Protocol_Details_0001.pdf

PDF 90 KB Posted

Attached to
WA-ABERNATHY FTC REHAB INTAKE STRUCTURE Federal contract opportunity
Solicitation number
140F0322R0013
Issued by
Department of the Interior Fish and Wildlife Service

About this file

This document outlines turbidity monitoring protocol requirements for an in-water construction project and details a related federal contract opportunity. The protocol mandates taking background and downstream turbidity samples before and during work to ensure increases do not exceed 5 NTU above background levels. Samples must be taken once per hour during work, reducing to every two hours if impacts are minimal. Extra monitoring 200 feet downstream can provide early warning of increases. The related federal contract opportunity is for rehabilitating the intake structure at the WA-Abernathy Fish Technology Center, solicited by the Department of the Interior Fish and Wildlife Service.

View the file

Other files for this federal contract opportunity

Other files attached to WA-ABERNATHY FTC REHAB INTAKE STRUCTURE, newest first.
File Type Posted
NWP_Verification_Letter__09-23-2022_0007.pdf PDF
NWP_Terms_and_Conditions_for_NWP_No__3__05-11-2022_0007.pdf PDF
AFTC__Questions_and_Responses__Amend_7__10-12-2022_0007.pdf PDF
Sol_140F0322R0013_Amd_0007.pdf PDF
Permit_Drawings__06-15-2021_0007.pdf PDF
List_of_Attachments__Nationwide_Permit_No__3_0007.pdf PDF
Amendment_No__6__REVISED_Statement_of_Work__09-20-2022_0006.pdf PDF
Amendment_No__6__REVISED_Proposal_Schedule__09-20-2022_0006.xlsx XLSX spreadsheet
Sol_140F0322R0013_Amd_0006.pdf PDF
Sol_140F0322R0013_Amd_0005.pdf PDF
B12_AFTC__Questions_and_Responses__Amend_5__09-09-2022_0005.pdf PDF
B12_AFTC__Questions_and_Responses__Amendment__09_01_2022_0004.pdf PDF
Sol_140F0322R0013_Amd_0004.pdf PDF
Sol_140F0322R0013_Amd_0003.pdf PDF
B12_AFTC__Questions_and_Responses__Amendment_08-31-2022_0003.pdf PDF
Sol_140F0322R0013_Amd_0002.pdf PDF
B12_Certificate_of_Compliance_0001.pdf PDF
Permit_Authorization_and_Conditional_Approval_0001.pdf PDF
Wetland_Delineation_Report_0001.pdf PDF
Safety_and_Design_Checklists_0001.pdf PDF
Endangered_Species_Act_and_Section_7(a)(2)_Biological_Opinion_(1)_0001.pdf PDF
Cultural_Resources_Survey_and_Report_0001.pdf PDF
B12_AFTC_Nationwide_Permit_3_T___C_s_0001.pdf PDF
Turbidity_Plan_0001.pdf PDF
State_Environmental_Policy_Act_Letter_0001.pdf PDF
JARPA_Application_0001.pdf PDF
Pre-Work_Safety_Checklist_0001.pdf PDF
NEPA_Compliance_Checklist_0001.xlsx XLSX spreadsheet
HPA_Conditional_Approval_Letter_and_Requirements_(1)_0001.pdf PDF
B12_Proposal_Schedule_0001.xlsx XLSX spreadsheet
Sol_140F0322R0013_Amd_0001.pdf PDF
A04_AFTC_Statement_of_Work_7-18-2022.pdf PDF
A06_AFTC_Permit_Drawings.pdf PDF
A06_AFTC__100__Final_Draft_Specifications__07-26-2022.pdf PDF
A06_AFTC_Technical_Requirements__7-18-2022.pdf PDF
A06_AFTC__100__Final_Draft_Drawings__07-26-2022.pdf PDF
Sol_140F0322R0013.pdf PDF
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Protocol Details

All in-water work must comply with the Washington State Clean Water Act. This means;

1. At the 500 foot downstream station, if turbidity samples show an increase of more than 5 NTU above background level, equipment operator should be contacted immediately. In-water work should stop, and immediate action should be taken to correct the surge of turbidity. Work activities can commence when turbidity samples are compliant.

2. Before work activities start, background turbidity samples are taken two hundred feet upstream of the in-water work activities.

3. Turbidity samples are taken at a 500 foot downstream station from the work activities, and should be taken once every ½ hour if work activities are in or near a waterbody.

Turbidity samples should be taken immediately if excessive turbidity is observed. If turbidity samples are not compliant, follow step number 1 above, and continue sampling once every 15 minutes. Once compliant, continue once every ½ hour.

4. If extra staff is available, take turbidity samples 200 feet downstream. They can warn the sampler at the 500 foot station of excessive turbidity, watch project activities, provide feedback to staff at the 500 foot station, and should be able to provide easier contact to the equipment operator.

5. Samples can be reduced to once every two hours if staffs are certain the project activities will not increase turbidity levels.

File details come from the government source that posted it. Updated .