B12_Proposal_Schedule_0001.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
WA-ABERNATHY FTC REHAB INTAKE STRUCTURE Federal contract opportunity
Solicitation number
140F0322R0013
Issued by
Department of the Interior Fish and Wildlife Service

About this file

This document contains a proposal schedule for construction services related to federal contract opportunity number 140F0322R0013 from the Department of the Interior Fish and Wildlife Service. The proposal schedule outlines ten base tasks and two option tasks for improvements to the Abernathy Fish Technology Center intake and fish ladder structures. Base tasks include site visits, permitting, mobilization and demobilization, dewatering system installation, erosion control, demolition, site restoration, electrical work, inspections, and miscellaneous work. Option tasks cover fish ladder and intake structure modifications. Offerors are instructed to provide pricing for all items and backups for labor, materials, equipment, and tools. The schedule requires contractors to assume material quantities in their proposals. Incomplete bids will not be considered.

View the file

Other files for this federal contract opportunity

Other files attached to WA-ABERNATHY FTC REHAB INTAKE STRUCTURE, newest first.
File Type Posted
Permit_Drawings__06-15-2021_0007.pdf PDF
List_of_Attachments__Nationwide_Permit_No__3_0007.pdf PDF
NWP_Verification_Letter__09-23-2022_0007.pdf PDF
Sol_140F0322R0013_Amd_0007.pdf PDF
NWP_Terms_and_Conditions_for_NWP_No__3__05-11-2022_0007.pdf PDF
AFTC__Questions_and_Responses__Amend_7__10-12-2022_0007.pdf PDF
Amendment_No__6__REVISED_Statement_of_Work__09-20-2022_0006.pdf PDF
Amendment_No__6__REVISED_Proposal_Schedule__09-20-2022_0006.xlsx XLSX spreadsheet
Sol_140F0322R0013_Amd_0006.pdf PDF
B12_AFTC__Questions_and_Responses__Amend_5__09-09-2022_0005.pdf PDF
Sol_140F0322R0013_Amd_0005.pdf PDF
B12_AFTC__Questions_and_Responses__Amendment__09_01_2022_0004.pdf PDF
Sol_140F0322R0013_Amd_0004.pdf PDF
B12_AFTC__Questions_and_Responses__Amendment_08-31-2022_0003.pdf PDF
Sol_140F0322R0013_Amd_0003.pdf PDF
Sol_140F0322R0013_Amd_0002.pdf PDF
JARPA_Application_0001.pdf PDF
Pre-Work_Safety_Checklist_0001.pdf PDF
NEPA_Compliance_Checklist_0001.xlsx XLSX spreadsheet
HPA_Conditional_Approval_Letter_and_Requirements_(1)_0001.pdf PDF
Sol_140F0322R0013_Amd_0001.pdf PDF
B12_Certificate_of_Compliance_0001.pdf PDF
Turbidity_Protocol_Details_0001.pdf PDF
Safety_and_Design_Checklists_0001.pdf PDF
Endangered_Species_Act_and_Section_7(a)(2)_Biological_Opinion_(1)_0001.pdf PDF
Cultural_Resources_Survey_and_Report_0001.pdf PDF
B12_AFTC_Nationwide_Permit_3_T___C_s_0001.pdf PDF
Turbidity_Plan_0001.pdf PDF
State_Environmental_Policy_Act_Letter_0001.pdf PDF
Permit_Authorization_and_Conditional_Approval_0001.pdf PDF
Wetland_Delineation_Report_0001.pdf PDF
Sol_140F0322R0013.pdf PDF
A04_AFTC_Statement_of_Work_7-18-2022.pdf PDF
A06_AFTC_Permit_Drawings.pdf PDF
A06_AFTC__100__Final_Draft_Specifications__07-26-2022.pdf PDF
A06_AFTC_Technical_Requirements__7-18-2022.pdf PDF
A06_AFTC__100__Final_Draft_Drawings__07-26-2022.pdf PDF
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Form Schedule

ABERNATHY FISH TECHNOLOGY CENTER
Construct and Install Intake Structure Improvements, Fish Ladder Structure
Improvements, and All Associated Appurtenances

PROPOSAL SCHEDULE

INSTRUCTIONS:
The Offeror shall edit this Proposal Schedule and may provide a detailed breakdown of their
Proposal (including support documentation) and all associated line item pricing. It is the
responsibility of the Offeror to ensure all requirements are met and all support documentation
is provided. The purpose of the Proposal Schedule Document is to organize Base Bid Tasks
and Option Bid Tasks for U.S. Fish and Wildlife Service Price Evaluation. Contractor
shall show pricing for items. Failure to provide pricing for all items may result in bid not being
considered for award.

Services - Base and Option Tasks:

TASK

(Base or

Option)DescriptionAmount
1
(Base)Field Verification Site Visit. Review of Existing Site Features and Existing Site Conditions. Document Review, Planning, Development, Preparation, and Submittal of Project Documents.

To include but not be limited to:

Incidentals.

All Associated Electronic and Hard Copy Deliverables.

2
(Base)Permitting.

To include but not be limited to:

Incidentals.

All Associated Electronic and Hard Copy Deliverables.

3
(Base)Mobilization and De-Mobilization.

To include but not be limited to:

Incidentals.

All Associated Electronic and Hard Copy Deliverables.

4
(Base)Construct and Install De-watering System and determine locations for Construction Staging Areas.

To include but not be limited to:

Incidentals.

All Associated Electronic and Hard Copy Deliverables.

5
(Base)Provide and Install Site, Sediment, and Erosion Control Measures.

To include but not be limited to:

Incidentals.

All Associated Electronic and Hard Copy Deliverables.

6
(Base)Perform Selective Demolition and Protect Existing Site Features and Structures.

To include but not be limited to:

Incidentals.

All Associated Electronic and Hard Copy Deliverables.

A
(Option)Construct and Install Fish Ladder Structure Construction Modifications.

To include but not be limited to:

Incidentals.

All Associated Electronic and Hard Copy Deliverables.

B
(Option)Construct and Install Intake Structure and Screen Structure Construction Modifications.

To include but not be limited to:

Incidentals.

All Associated Electronic and Hard Copy Deliverables.

7
(Base)Perform Site Restoration.

To include but not be limited to:

Incidentals.

All Associated Electronic and Hard Copy Deliverables.

8
(Base)Construct and Install Electrical Service Connections for Controls Cabling, Power Cabling, and New Flow Meter.

To include but not be limited to:

All Associated Electrical Equipment and Appurtenances for a Complete and Fully Functional Electrical System.

Incidentals.

All Associated Electronic and Hard Copy Deliverables.

9
(Base)Perform Special Inspections and Testing for the Full Duration of the Project / Contract.

To include but not be limited to:

Incidentals.

All Associated Electronic and Hard Copy Deliverables.

10
(Base)All Other Necessary Work for a Complete and Operable Project In Accordance With All The Requirements of the PE's Stamped and Signed Bid Documents (Drawings and Specifications) and Contractor's Manufacturer's Design Drawings and Specifications developed under this Ancillary Design and Build Contract.

To include but not be limited to:

Incidentals.

All Associated Electronic and Hard Copy Deliverables.

Total (Base TASKS 1 - 10) $0.00

Total (Base TASKS 1 - 10, and Option TASKS A and B) $0.00

The Offeror may provide a detailed breakdown of their bid and all associated line item pricing.
The above Proposal Schedule Description column is not intended to be comprehensive.
It is the responsiblilty of the Offeror to ensure all requirements are met.
As part of the Proposal Schedule, and at the Offeror's discretion, Prepare and
Submit Back-Up Documents for the Proposal Schedule including Number of Labor Categories,
Labor Rates, Number of Labor Hours, Material Quantities, Equipment Quantities,
Equipment Rates, and Required Tools. Include All Items Required and Anticipated
to successfully deliver the Project.
As the Contractor is preparing their Proposal, Material Quantities require Contractor assumptions.
The Contractor may submit their assumptions about Material Quantities as part of their Offer.
Whether the Contractor chooses to submit their assumptions about Material Quantities to USFWS
for review and as part of their Offer is at the discretion of the Contractor.

Incomplete Bids Will Not Be Considered.

Name of Bidder and Company:

Address (Include Zip Code):

File details come from the government source that posted it. Updated .