SF 30 - Amendment 4 - 127EAW23R0004 - Bridge Modoc.pdf.pdf
PDF 1 MB Posted
- Solicitation number
- 127EAW23R0004
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is an amendment to a solicitation for a bridge replacement construction project on the Modoc National Forest. Amendment 4 extends the proposal due date to May 25, 2023 at 5:00 PM Pacific Time. It also provides an additional answer to requests for information. The project involves replacing the Middle Fork Parker Creek Bridge with a total estimated value between $500,000 and $1,000,000. The solicitation is a 100% small business set aside issued by the USDA Forest Service for a construction project requiring the replacement of the bridge located on the Modoc National Forest in accordance with FAR 32.204.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
127EAW23R0004
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
7EAW
CONTRACT SPECIALIST
TANYA TORRES
PPS FPO SW ZONE CSA-6
USDA FOREST SERVICE
GAOA05/05/2023
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.
Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
02/07/2023
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
JEREMY B. BEDNER
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
USDA Forest Service Request for Proposal.
PROJECT: Middle Fork Parker Creek Bridge Replacement, Modoc National Forest.
The purpose of Amendment 4 is to extend the proposal due date and provide an additional RFI answer. Refer to continuation page.
Proposal due date is extended to NLT May 25 2023, 5PM (1700) PST.
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
SAME AS ITEM 6.
7EAW
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers X is extended, Amendment 4
RFP 127EAW23R0004
FY23 Middle Fork Parker Creek
Bridge Replacement, Modoc National Forest
Amendment 4
Additional Request for Information [RFI] 1
Question 1. Time to complete is 145 days from NTP. If project awarded and NTP received by mid-June, does the Forest Service still think project could be completed in 2023? Taking into consideration submittals, manufacturing, and the high altitude of the location and historic inclement weather in the region.
Answer: Yes. The Government anticipates completion in 2023.