This document contains an amendment to a request for proposal for bridge replacement construction services on the Middle Fork Parker Creek Bridge within the Modoc National Forest. The Forest Service seeks proposals to replace the existing bridge for a cost between $500,000 and $1,000,000. The amendment extends the proposal due date to April 20, 2023 and provides additional responses to offerors' requests for information. It clarifies that only a prime contractor's prior experience and past performance will be considered during evaluation, and that subcontractors' experience cannot be proposed. A site visit is also available to offerors prior to submitting their proposals. The opportunity is designated as a small business set-aside and will be awarded by the Department of Agriculture Forest Service.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
127EAW23R0004
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
7EAW
CONTRACT SPECIALIST
TANYA TORRES
PPS FPO SW ZONE CSA-6
USDA FOREST SERVICE
GAOA03/21/2023
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.
Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
02/07/2023
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
JEREMY B. BEDNER
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
USDA Forest Service Request for Proposal.
PROJECT: Middle Fork Parker Creek Bridge Replacement, Modoc National Forest.
Amendment 2 provides additional answers to RFIs and associated revisions to the RFP document and attachments. Refer to continuation page.
Proposal due date is extended to NLT April 20, 2023, 1500 PST.
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
SAME AS ITEM 6.
7EAW
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers X is extended, Amendment 2
RFP no. 127EAW23R0004 FY23 Middle Fork Parker Creek
Bridge Replacement, Modoc National Forest
Amendment 2 Additional Requests for Information [RFIs] 1-5
Question 1. Can you increase the page limitations for the Technical Approach?
Answer: No. Per section L.3 (page 43) of the RFP, the Technical Approach shall not exceed 10 pages. The contractor's technical approach shall concisely address all required information / document submissions while not exceeding 10 pages.
Question 2 . Can you add my company to the Interested Vendor List (IVL) on SAM.gov?
Answer: No, the Government cannot add companies to the IVL. Each contractor must have an account in SAM.gov and the account must be associated with the entity's Unique Entity Identifier (UEI) number. The IVL is tied to the solicitation notice and the contractor must take action in SAM.gov if they want to be added to the IVL.
Question 3. Is it acceptable for the offeror to use a subcontractor's experience for past performance prior projects for the RFP in lieu of the prime contractors?
Answer: No. For prior experience and past performance (Evaluation Factor 1), only your company's prior project experience as a prime contractor – OR – your company's prior experience as a subcontractor shall be considered.
The contractor/offeror shall NOT propose prior experience and past performance examples of subcontractors or teammates. Offerors who included prior experience/past performance examples of subcontractors or teammates may be rated “unacceptable” for Evaluation Factor 1 and determined ineligible for award.
Question 4. Can you please tell me where I can find plan holders list?
Answer: The FS does not maintain a “Plan Holder’s List” for this project.
Question 5. Can the solicitation due date be extended so that contractors will be able to safely visit the site?
Answer: Yes. This amendment extends the the proposal due date to NLT April 20, 2023, 1500 PST.
| SF 30 - Amendment 1 - 127EAW23R0004 - Bridge Modoc |
| 127EAW23R0004 - SF 30 - Amendment 1 |
| RFI QnAs |
RFI QnAs. JB EDIT