Revised Schedule of Items.pdf

PDF 95 KB Posted

Attached to
Multnomah Falls Lodge Electrical Upgrades
Solicitation number
1240BH21R0011-1
Issued by

About this file

This document provides details for a federal contract opportunity to upgrade the electrical system at Multnomah Falls Lodge. The USDA Forest Service intends to issue a Request for Proposals to demolish and install new electric components including replacement of all electric panels, installation of an automatic transfer switch, emergency shut-off switch and strobe lights, as well as new distribution panels, main switchboard, lighting, and other electrical equipment. The site work will include installation of the main switchboard and automatic transfer switch. The project is located at Multnomah Falls Lodge in Bridal Veil, Oregon. The anticipated start date is October 2021. The government estimates the value of the project to be between $1,000,000 and $5,000,000 including base items and options. A site visit was scheduled for April 28, 2021 and a pre-bid proposal conference call is scheduled for May 4, 2021. Offerors must be registered in the System for Award Management database to be eligible for award.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA Forest Service

1/22/2021 Multnomah Falls Electrical Upgrade & Emergency Generators Page 1/1

PART I – THE SCHEDULE

SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

SCHEDULE OF ITEMS – REVISED 05/07/2021

Item Number Item Description Unit of

Measurement Price

Base Bid Items

1 Multnomah Falls Electrical System Lump Sum $ 2 Install Panel C Lump Sum $ 3 Install Panel R Lump Sum $ 4 Install Panel J Lump Sum $ 5 Install Panel Q Lump Sum $

TOTAL BASE ITEMS $

Bid Options

6 BO #1 - Install Panel H Lump Sum $ 7 BO #2 - Install Panel M Lump Sum $ 8 BO #3 - Install Panel SB1 Lump Sum $ 9 BO #4 - Install Panel SB2 Lump Sum $

10 BO #5 – Install Panel SB3 Lump Sum $ 11 BO #6 - Install Panel N Lump Sum $ 12 BO #7 - Replace Outlet Receptacles Lump Sum $ 13 BO #8 - Install New HVAC Disconnects Lump Sum $

TOTAL OPTION ITEMS $

TOTAL ALL ITEMS $

PART I – THE SCHEDULE
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
SCHEDULE OF ITEMS – REVISED 05/07/2021

File details come from the government source that posted it. Updated .