01-CHRI-217021-244555_Technical_Specifications_Amended_06-2020.pdf

PDF 3 MB Posted

Attached to
Construct new bulkhead at Christiansted VI Federal contract opportunity
Solicitation number
140P2020R0054
Issued by
Department of the Interior National Park Service National Office

About this file

This document provides technical specifications for the construction of a new bulkhead at Christiansted National Historic Site in St. Croix, U.S. Virgin Islands. The project includes installing a 700-foot long steel sheet pile bulkhead and concrete cap, as well as restoring the existing concrete wharf apron. The work is funded by the National Park Service under two separate sources, with Line Item Construction funding covering the new bulkhead and Hurricane Irma and Maria funding covering wharf slab rehabilitation. The specifications define 18 contract line items and provide requirements for site protection, demolition, sheet pile installation, concrete work, landscaping repairs, and vibration monitoring. The contractor must also comply with environmental permits and coordinate work with the National Park Service's environmental monitor.

View the file

Other files for this federal contract opportunity

Other files attached to Construct new bulkhead at Christiansted VI, newest first.
File Type Posted
501_B08_2020R0054-Amend05_0005.pdf PDF
502_Solicitation-14P2020R0054-CHRI 217021-244555-Bidder QA-AMEND05_0005.pdf PDF
504_52.247-64 _0005.pdf PDF
Sol_140P2020R0054_Amd_0005.pdf PDF
503_SpecialClause03-COVID19_0005.pdf PDF
Sol_140P2020R0054_Amd_0004.pdf PDF
2020R0054Amend04QandA_0004.pdf PDF
B08_2020R0054-Amend04_0004.pdf PDF
2020R0054CHRIPrepropMeetingRecord_0004.pdf PDF
Sol_140P2020R0054_Amd_0003.pdf PDF
A301_B08_Solit_PSP_Vol_I_PastPerf_R1_0003.docx DOCX document
A302_CHRI217021ContractingPreProposalPresentation_0003.pdf PDF
A304_CHRI217021-244555PreProposalPresentation-SiteLogistics_0003.pdf PDF
A303_CHRI217021-244555PreProposalPresentation-ProjectReqts_0003.pdf PDF
Sol_140P2020R0054_Amd_0002.pdf PDF
Sol2020R0054Am2_0002.docx DOCX document
B08_Amendment01_070620_0001.pdf PDF
03-CHRI-217021-244555_Contruction_Drawings_399-147281A_Unsigned-Unstamped.pdf PDF
14-CHRI_217021-244555_Bulkhead_Inspection_Report_Collins-Engineers_10-25-18.pdf PDF
13-CHRI_217021-244555_Concrete_Bulkhead_Investigation_Memo_HDR_10-25-18.pdf PDF
16-CHRI_217021-244555_Concrete_Apron_Void_and_Rebar_Detection_Report-GPRS_09-10-18.pdf PDF
17-CHRI_217021-244555_Waterfront_Facility_Assessment-Moffatt-Nichol_09-17-2014.pdf PDF
07-Permit_Attachment_Turbidity_and_Water_Quality_Monitoring_Plan_NPS_05-2019.pdf PDF
11-CHRI_Wharf_Bulkhead_Finding_of_No_Significant_Impact-FONSI-NPS_09-2019.pdf PDF
08-Permit_Attachment_SeagrassandCoral_ SurveyandMitigation_Plans_NPS_05-2020.pdf PDF
02-CHRI-217021-244555_Contruction_Drawings_399-147281A_Signed-Stamped.pdf PDF
06-Permit_Water_Quality_Certificate_WQC-19-006-LandW_USVI_DPNR.pdf PDF
Sol_140P2020R0054.pdf PDF
18-B08_Solit_PSP_Cover.docx DOCX document
22-B08_Solit_PSP_Vol_II_GenRefs.doc DOC document
15-CHRI_217021-244555_Wharf_Slab_Investigation_Memo_HDR_10-25-18.pdf PDF
09-Permit_Nationwide_ Permit-3-SAJ-2019-02388_USACE.pdf PDF
23-B08_Solit_PSP_Vol_II_SubKPlanForm_REQD.doc DOC document
12-CHRI_217021-244555_Final_Geotechnical_Report_Jaca-Sierra_07-17-18.pdf PDF
B08_Solicitation_140P2020R0054-CHRI 217021-S.pdf PDF
05-Permit_Federal_Consistency_Determination_CZX-1-19-FC-USVI_DPNR.pdf PDF
21-B08_Solit_PSP_Vol_II_Equals.doc DOC document
04-CHRI-217021-244555_Final_Statement_of_Structural_Tests.pdf PDF
24-B08_Solit-PSP_Vol_II_BidBond.pdf PDF
20-B08_Solit_PSP_Vol_I_PastPerf_REQD.docx DOCX document
10-CHRI_Wharf_Bulkhead_Final_Environmental_Assessment_EA-NPS_05-2019.pdf PDF
25-B03_DOL-Wage_ Determination_Heavy.pdf PDF
19-B08_Solit_PSP_Vol_I_Exp_REQD.docx DOCX document
Show all 43

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CHRISTIANSTED NHS

ST. CROIX, U.S.V.I

REPLACE WHARF BULKHEAD

CHRI 217021

REPAIR WHARF

CHRI 244555

TECHNICAL SPECIFICATIONS

FINAL CONSTRUCTION DOCUMENTS

NATIONAL PARK SERVICE

DENVER SERVICE CENTER

December, 2019 Amended June, 2020 (NPS DSC)

TABLE OF CONTENTS

CHRI - 217021 TOC - 1

091015

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Line Items 01 31 00 Project Management & Coordination 01 32 16 Construction Schedule 01 32 33 Photographic Documentation 01 33 23 Submittal Procedures 01 35 13.22 Archeological Protection 01 35 23 Safety Requirements 01 35 91 Historic Preservation Treatment Procedures 01 40 00 Quality Requirements 01 42 00 Reference Standards 01 45 29 Testing Laboratory Services 01 50 00 Temporary Facilities and Controls 01 57 19.12 Noise & Acoustics Management 01 57 23 Temporary Storm Water Pollution Prevention 01 67 00 Product Requirements 01 73 29 Cutting and Patching 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data

DIVISION 02 – EXISTING CONDITIONS

02 22 13 Vibration Monitoring 02 41 00 Demolition

DIVISION 03 – CONCRETE

03 01 00.71 Rehabilitation of Concrete 03 30 00 Cast-in-Place Concrete 03 30 01 Latex Modified Concrete

DIVISION 05 – METALS

05 05 19 Post-Installed Concrete Anchors 05 12 53 Welding

DIVISION 06 – HEAVY TIMBER CONSTRUCTION

06 13 00 Heavy Timber Construction

DIVISION 09 – FINISHES

09 97 13.23 Coating of Waterfront Steel Structures

TABLE OF CONTENTS

CHRI - 217021 TOC - 2

091015

DIVISION 13 – SPECIAL CONSTRUCTION

13 47 13 Cathodic Protection

DIVISION 31 – EARTHWORK

31 62 16 Steel Sheet Piling

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 92 00 Sodding

DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION

35 59 33 Marine Bollards and Cleats

DIVISION 44 – POLLUTION AND WASTE CONTROL EQUIPMENT

44 22 50 Turbidity and Sediment Monitoring

CHRI - 217021 01 11 00 - 1

091015 SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Government Furnished Materials.

5. Contractor use of premises.

6. Public use of site.

7. Occupancy requirements for buildings.

8. Work Restrictions.

9. Special Construction Requirements.

10. Soils Investigation Report.

11. Additional Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Christiansted National Historic Site in Christiansted, St. Croix, U.S. Virgin Islands.

The project is located directly west of Fort Christiansvearn, and northeast of Hospital Street.

B. The Work consists of the following:

1. The Work includes installation of a new ±700-ft long bulkhead that will lie waterward of the existing bulkhead. The new bulkhead will consist of steel sheet pile and concrete construction. The work also includes restoration/repair of the existing concrete wharf apron.

C. Project will be constructed under a single prime contract.

D. The funding for the project will come from two separate sources based on the work to be performed.

1. All work relating to the construction of the new permanent bulkhead and associated fixtures will be covered under Line Item Construction (LIC) funding. These are Contract Line Items 1 through 14.

2. Work relating to upland wharf slab rehabilitation will be covered under Hurricane Irma and Maria (HIM) funding. These are Contract Line Items 15 through 18.

3. Funding from one source may not be used to cover overages in the other component of the project; however, the total project cost will be the sum of Contract Line Items 1 through 18.

CHRI - 217021 01 11 00 - 2

1.3 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to work in areas indicated in the Drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to the concrete wharf apron and to barge work located waterward of the bulkhead.

2. Limit site disturbance. Ground disturbance is not permitted, except where required for excavations as shown in the Drawings. Seabed disturbance is not permitted without prior coordination with and continuous monitoring by the NPS provided Environmental Monitor.

B. Storage of Materials: Confine storage of materials to the Designated Staging Area and within the Construction Limits as indicated on the Drawings.

C. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with

Contracting Officer and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to authorized users and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

3. Schedule deliveries to avoid prolonged traffic interruptions.

E. Construction Camp: Establishment of a camp within the park will not be permitted.

F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. Refer to the park Superintendent’s Compendium online at:

https://www.nps.gov/chri/learn/management/lawsandpolicies.htm

A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

CHRI - 217021 01 11 00 - 3

1.4 PUBLIC USE OF SITE

A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.

Road closures will not be permitted.

1.5 CONDUCT OF OPERATIONS

A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent. Refer to the park Superintendent’s Compendium online at:

https://www.nps.gov/chri/learn/management/lawsandpolicies.htm

B. Work on Saturdays Sundays, or at night may not be performed without prior consent from the Contracting Officer. Submit requests three (3) work days in advance of the work to the Contracting Officer for approval.

1. Work may be performed during local (island) holidays, provided the work does not interfere with local festivities (traffic, noise, etc.) and falls within allowable work days/hours as specified in this Section.

2. Work shall not be performed during Federal holidays.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.6 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 8:00 a.m. to 5:00 p.m AST, Monday through Friday, unless indicated/directed otherwise by the Contracting Officer.

1. Work on Weekends and outside of On-Site Work Hours: The Park is open to the public on weekends. The Contractor must request and receive Contracting Officer approval of any work performed outside of the specified On-Site Work Hours, including weekend work.

Request must be submitted three (3) work days in advance, and the Contractor must obtain approval from the Contracting Officer before scheduling.

2. Early Morning Hours: Park hours are 8am to 5pm AST. Work outside these hours must be approved by the Contracting Officer prior to scheduling.

3. Hours for sheet piling/pre-drilling activities: Shall commence only after 9:00 a.m. AST unless otherwise indicated by the Contracting Officer or local agenc(ies) having jurisdiction.

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer, utility companies and utility owners of proposed locations and times for excavation.

CHRI - 217021 01 11 00 - 4

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than three (3) work days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. Hours for Utility Shutdowns: To be determined on a case-by-case basis by the Contracting

Officer.

D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes. Properly dispose of all cigarette butts in appropriate receptacles to be provided, emptied and disposed of by the Contractor.

E. Contractor Use of Parking Lot:

1. Contractor is allowed the use of six (6) parking spaces for the duration of the Work as shown in the Plans.

2. Contractor use of the parking lot shall not impede or restrict regular use of the lot by park staff or park visitors.

3. Contractor shall open/close lot gates per Contracting Officer direction in accordance with designated work hours. Contractor shall notify Contracting Office if work schedule differs from allowed working hours.

1.7 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.

1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.

B. Contractor to confirm seasonal shutdown times, park activities, limited access periods, and government furnished permit requirements, as appropriate, prior to scheduling work.

1.8 SOILS INVESTIGATION (GEOTECHNICAL) REPORT

A. A soils investigation (geotechnical) report entitled “Geotechnical Report on the Exploration Performed at the Site of the Proposed Wharf Replacement at Christiansted, St. Croix, USVI”, July 2018 has been prepared by Jaca & Sierra Testing Laboratories.

B. A copy of the report is available to all plan holders with this package.

CHRI - 217021 01 11 00 - 5

C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

1.9 ADDITIONAL REPORTS

A. The following reports are hereby provided as attached to this contract package:

1. Technical Report: “Concrete Bulkhead Investigation Memo” by HDR Engineering, Inc., October 2018.

2. Technical Report: “Bulkhead Inspection Report” by Collins Engineers, Inc., October 2018.

3. Technical Report: “Wharf Slab Investigation Memo” by HDR Engineering, Inc., October

2018.

4. Technical Report: “Concrete Apron Void and Rebar Detection Report” by GPRS, Inc., September 2018.

5. Technical Report: “Waterfront Facility Assessment and Recommendations” by Moffatt &

Nichol, September 2014.

B. A copy of these reports are available to all plan holders with this package.

C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

CHRI - 217021 01 26 01 - 1

031414 CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

CHRI - 217021 01 26 01 - 2

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:

1) Social Security

2) Medicare

3) Workers Compensation– Policy and company calculation to be made available.

4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.

5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.

CHRI - 217021 01 26 01 - 3

6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.

Contractor may utilize the government provided Contractor Estimate Form, or their http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#ct

CHRI - 217021 01 26 01 - 4

own form, provided that it contains the same information and level of detail as the Gov’t provided form.

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.

Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.

Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

CHRI - 217021 01 26 01 - 5

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.

Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10% Profit………………7.50%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

CHRI - 217021 01 26 01 - 6

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 012601

CHRI - 217021 01 27 00 - 1

082714 DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

C. The funding for the project will come from two separate sources based on the work to be performed.

1. All work relating to the construction of the new permanent bulkhead and associated fixtures will be covered under Line Item Construction (LIC) funding. These are Contract Line Items 1 through 14.

2. Work relating to upland wharf slab rehabilitation will be covered under Hurricane Irma and Maria (HIM) funding. These are Contract Line Items 15 through 18.

3. Funding from one source may not be used to cover overages in the other component of the project; however, the total project cost will be the sum of Contract Line Items 1 through 18.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS – LINE ITEM CONSTRUCTION (LIC)

A. Contract Line Item No. 1 — LIC: General Conditions

1. This item consists of mobilizing equipment and personnel to the Project site, costs for bonds and insurance, costs project management, quality control related tasks throughout the duration of the Project, costs for compliance with environmental permit requirements and environmental monitoring and protection measurements, and costs for demobilization of equipment and personnel from the Project site.

2. Measurement for payment: No measurement required.

3. Payment will be made at the contract lump sum price.

B. Contract Line Item No. 2 – LIC: Site Protection

1. This item consists of providing necessary materials and labor to preserve and protect existing park infrastructure according to protection measures detailed in the Contract Drawings. Work includes furnishing construction fencing and hardened protective measures to prevent damage to park infrastructure.

2. Measurement for payment: No measurement required.

3. Payment will be made at the contract lump sum price.

CHRI - 217021 01 27 00 - 2

C. Contract Line Item No. 3 — LIC: Demolition and Removal

1. This item consists of demolishing the timber fender system, mooring cleats, select portions of the existing concrete cap and concrete curb, and select areas of the existing timber boardwalk. The cost for this contract line item shall include costs associated with storing demolition materials on-site for re-use, or for barging to the U.S. mainland or Puerto Rico at the end of the Project. All items designated for removal and disposal shall be disposed of off the island. No items are to be disposed of on the island, although on-island recycling and/or salvage is permitted at the Contractor’s discretion per the Contractor’s Waste Management Plan. Costs shall also include the cost of hauling the materials by barge, offloading the materials, hauling the materials to an approved construction debris landfill, and associated landfill tipping fees.

2. Measurement for payment: No measurement required.

3. Payment will be made at the contract lump sum price.

D. Contract Line Item No. 4 – LIC: Steel Sheet Pile Bulkhead Predrilling

1. Contractor is advised that difficult driving is expected due to the site geotechnical conditions. This item covers the cost associated with any predrilling efforts engaged by the contractor to install the steel sheet pile bulkhead.

2. Measurement for payment: No Measurement required.

3. Payment will be made at the contract lump sum price.

E. Contract Line Item No. 5 — LIC: Steel Sheet Pile (0+00 to 4+97)

1. This item consists of furnishing and installing steel sheet pile as required by the Drawing and Specifications. Price will include the cost associated with furnishing materials at site, driving, templates, and sheet pile coating.

2. Measurement for payment: Payment will be measured by the running linear feet of sheet pile delivered and installed. Payment will not be made for sheet pile material that is delivered but not incorporated into the Project. Payment will be as measured by the Contractor’s surveyor, with depth verified by the required installation records, and submitted with the payment application.

3. Payment will be made at the contract unit price per linear foot of bulkhead.

F. Contract Line Item No. 6 — LIC: Bulkhead Cap and Fascia (0+00 to 4+97)

1. This item consists of supplying formwork, form-liner, steel reinforcing, required samples and mock-ups, concrete, expansion joint materials, and other ancillary materials to install the bulkhead cap and fascia as required by the Drawing and Specifications.

2. Measurement for payment: Payment will be measured by the linear feet of bulkhead cap installed. Payment will not be made for waste concrete that is not incorporated into the Project. The Contractor shall submit concrete batch tickets with each payment application as proof for payment.

3. Payment will be made at the contract unit price per linear foot.

G. Contract Line Item No. 7— LIC: Granular Backfill Between Existing/Proposed Bulkhead

1. This item consists of furnishing and installing granular backfill between the existing and proposed bulkhead after sheet pile installation.

2. Measurement for payment: Payment will be measured by the volume of granular fill (cubic yards) delivery by truck to the site and incorporated into the Project. Payment will not be

CHRI - 217021 01 27 00 - 3

made for waste material that is not incorporated into the Project. The Contractor shall submit delivery tickets with each payment application as proof for payment.

3. Payment will be made at the contract unit price per cubic yard.

H. Contract Line Item No. 8 — LIC: Concrete Gravity Wall Extension (Sta 4+97 to 7+00)

1. This item consists of supplying formwork, steel reinforcing, concrete, expansion joint materials, and other ancillary materials including the epoxy dowels to install the gravity wall extension as required by the Drawing and Specifications. Work shall also include installing the concrete drainage pipe extension to connect the existing pipe to the waterside opening of the new gravity wall.

2. Measurement for payment: Payment will be measured by the linear feet of wall installed Payment will not be made for waste concrete that is not incorporated into the Project. The Contractor shall submit concrete batch tickets with each payment application as proof for payment.

3. Payment will be made at the contract unit price per linear foot.

I. Contract Line Item No. 9 — LIC: Mooring Cleats

1. This item consists of furnishing and installing mooring cleats as required by the Drawing and Specifications.

2. Measurement for payment: Payment will be by the number (each) of cleats installed as counted by the Contractor, and verified by the Contracting Officer.

3. Payment will be made at the contract unit price per each.

J. Contract Line Item No. 10 — LIC: Sacrificial Alum. Anodes

1. This item consists of furnishing and installing aluminum anodes as required by the Drawing and Specifications.

2. Measurement for payment: Payment will be by the number (each) of anodes installed as counted by the Contractor, and verified by the Contracting Officer.

3. Payment will be made at the contract unit price per each.

K. Contract Line Item No. 11 — LIC: Timber Boardwalk Reconstruction and Extension

1. This item consists of removing and reconstructing the timber boardwalk applying similar materials to match existing and extending the boardwalk waterward to match the face of the proposed concrete bulkhead cap as required by the Drawing and Specifications.

2. Measurement for payment: No measurement required.

3. Payment will be made at the lump sum contract price.

L. Contract Line Item No. 12 – LIC: Site Furnishings

1. This item consists of replacing, in-kind, the existing timber bollards located along the wharf apron. Contractor is to match general size and style for replacement.

2. Measurement for payment: Payment will be per each bollard replaced

3. Payment will be made at the contract unit price per each

M. Contract Line Item No. 13 – LIC: Vibration Monitoring

CHRI - 217021 01 27 00 - 4

1. This item consists of developing and implementing a vibration monitoring plan as described in Section 02 22 13.

2. Measurement for payment: No measurement required.

3. Payment will be made at the lump sum contract price.

N. Contract Line Item No. 14 — LIC: Landscape Repairs

1. This item consists of furnishing and installing sod and making miscellaneous landscape repairs (as a result of damage during construction) at Project closeout. Contractor is responsible for providing a bid value that will cover the costs of all damaged sod/landscape at the project site as determined by the Contracting Officer.

2. Measurement for payment: No measurement required.

3. Payment will be made at the contract lump sum price.

3.2 LIST OF CONTRACT LINE ITEMS – HURRICANE IRMA/MARIA REPAIR WORK (HIM)

A. Contract Line Item No. 15 — HIM: General Conditions

1. This item consists of mobilizing equipment and personnel to the Project site, costs for bonds and insurance, costs project management, quality control related tasks throughout the duration of the Project, costs for compliance with environmental permit requirements and environmental monitoring and protection measurements, and costs for demobilization of equipment and personnel from the Project site. Note that this Contract Line Item is only as required for repairs to the wharf apron slab and concrete curb repairs. General Conditions for Line Item Construction (LIC) are to be considered separate.

2. Measurement for payment: No measurement required.

3. Payment will be made at the contract lump sum price.

B. Contract Line Item No. 16 — HIM: New Wharf Apron Topping Slab:

1. This item consists of furnishing materials and installing the new wharf apron toping overlay including all required samples and mock-ups. Work shall include surface cleaning and measures to prepare the existing slab to receive the new overlay.

2. Measurement for payment: Payment will be by square (feet) of overlay poured as field measured by the Contractor, and verified by the Contracting Officer.

3. Payment will be made at the contract unit price per square foot

C. Contract Line Item No. 17 — HIM: Curb Repairs:

1. This item consists of furnishing materials and repairing broken/damaged sections of the existing concrete curb as required in the Drawings and Specifications.

2. Measurement for payment: Payment will be by the number (each) of concrete curb repairs as counted by the Contractor, and verified by the Contracting Officer.

3. Payment will be made at the contract unit price per each.

D. Contract Line Item No. 18 — HIM: Concrete Drainage Pipe Repair:

1. This item consists of furnishing materials and repairing broken/damaged section of the existing concrete drainage pipe and installing new drain termination and grating as required in the Drawings and Specifications.

CHRI - 217021 01 27 00 - 5

2. Measurement for payment: No measurement required.

3. Payment will be made at the contract lump sum price.

END OF SECTION 01 27 00

CHRI - 217021 01 31 00 - 1

091015 PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination.

3. Submittals

4. Coordination Drawings.

5. Requests for Information (RFIs).

6. NPS/DSC SharePoint Project Website.

7. Project meetings.

8. Environmental Coordination.

9. Permits

B. Related Requirements:

1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.

1.2 DEFINITIONS

A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm

CHRI - 217021 01 31 00 - 2

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Permit requirements.

7. Pre-installation conferences.

8. Project closeout activities.

9. Commissioning activities.

1.4 DIVISION 01 (PRE-CONSTRUCTION) SUBMITTALS

A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference unless specified otherwise below. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. A list of Subcontractors for this project.

3. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

4. Satisfactory evidence of liability insurance coverage and workman’s compensation for the

Contactor and all subcontractors.

5. Construction Schedule (per Specification 013216).

6. A comprehensive breakdown of the Schedule of Values (per Specification 013216).

7. Traffic Management Plan (per Specification 013323 Part 2.2.I and Specification 015000);

shall be submitted a minimum of 30 calendar days prior to scheduled date of Notice To Proceed.

8. Accident Prevention Plan (per Specification 013523).

9. Tropical Storm Response Plan (per Specification 013523).

10. Historic Preservation Treatment Plan (per Specification 013591).

11. Quality Control Plan (per Specification 014000).

12. Noise Management Plan (per Specification 015719.12); shall be submitted a minimum of

30 calendar days prior to scheduled date of Notice To Proceed.

CHRI - 217021 01 31 00 - 3

13. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP) (per Specification 015723).

14. Waste Management Plan (per Specification 017419).

15. Turbidity and Sediment/Water Quality Monitoring Plan (in accordance with project permit

Water Quality Certificate, WQC-19-006 (L&W), with specific stipulations as specified in Specification 013100 Part 1.9.B.2; and per Specification 442250); shall be submitted a minimum of 30 calendar days prior to scheduled date of Notice To Proceed.

16. Vibration Monitoring Plan (per Specification 022213); shall be submitted a minimum of 30 calendar days prior to scheduled date of Notice To Proceed.

17. List of Required Contractor-Provided Construction Permits (refer to Specification 013100 Part 1.9.C). Include the following information for each permit:

a. Name of Permit.

b. The Agency(ies) with Jurisdiction issuing the permit.

c. Information required from the Government, if any, in order for the Contractor to complete the permit application.

d. Schedule for Contractor acquisition of the permit.

B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held or as otherwise specified above. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date or as otherwise specified above, the conference will be cancelled and/or Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.

1. CO will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

8. Contractor's signature.

9. Requested date for response.

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

CHRI - 217021 01 31 00 - 4

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:

1. Enter the general information at the top of the form.

2. Under the “Action” section at the bottom of the form, select “Question” then select “CMR” in the drop-down of the “Send to” box.

3. Enter the details of the question and attach related documents.

4. Select “Submit Form” at the bottom of the page.

D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond.

CO will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Contracting Officer's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

1.6 PROJECT WEB SITE

A. Use the NPS/DSC SharePoint Project website for communication throughout the contract period.

The NPS/DSC SharePoint Project website will be used for the following functions:

1. Project directory.

2. Project correspondence.

3. Meeting agendas and minutes.

4. Contract modifications forms and logs.

5. RFI form and processing.

6. Task and issue management.

7. Photo documentation.

8. Baseline schedule, schedule updates and calendar management.

9. Submittal form and processing.

10. Payment coordination documentation.

11. Drawing and specification document hosting, viewing, and updating.

12. Online document collaboration.

13. Reminder and tracking functions.

14. Archiving functions.

15. Notification of submittal and RFI statuses and current responsible party.

CHRI - 217021 01 31 00 - 5

16. Permits and addendums

B. Some documents however are not suitable to be shared using the NPS/DSC SharePoint Project website. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using the NPS/DSC SharePoint Project website and shall be coordinated with the SharePoint Project team as appropriate.

C. Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Department of Interior (DOI). Once the user is registered on the DOI website, they will be given access to the NPS/DSC SharePoint Project website. For login procedures and other SharePoint information, refer to the Workflows website at http://www.nps.gov/dscw/precon_spproj.htm.

D. All users will be required to have the following software packages:

1. Internet Explorer version 7 or later.

2. Adobe Acrobat Professional (Pro) version 9 or later

1.7 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:

1. Roles & Responsibilities/ Lines of Authority.

2. Park rules and regulations.

3. Jobsite Safety.

4. Resolution of comments on required Division 01 documents.

5. Coordination of Subcontractors.

6. Labor law application.

7. Modifications.

8. Schedule of Values

9. Payments to Contractor.

10. Payroll reports.

11. Contract time.

12. Liquidated damages.

13. Contractor Performance Evaluation.

14. Display of Hotline posters.

15. Notice to proceed.

16. Correspondence procedures.

17. NPS/DSC SharePoint Project website.

18. Acceptance/rejection of work.

19. Progress meetings.

20. Submittal procedures.

21. NPS Final Accessibility Inspection.

22. Environmental requirements.

23. Permit requirements.

24. As-constructed drawings/operation and maintenance (O&M) manuals.

25. Saturday, Sunday, holiday and night work.

26. Reference materials.

27. Value engineering.

http://www.nps.gov/dscw/precon_spproj.htm

CHRI - 217021 01 31 00 - 6

B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:

a. Approval of minutes of previous meetings.

b. Submittal status.

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications.

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, Accessibility, etc.)

g. Inspections of work in progress and projected (Special inspections,

h. Construction Schedule update (provide updated CPM).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

k. Permit requirements.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Sustainable design…

This is the start of the file's text. The full file is on GovTribe.