About this opportunity

Jordan Basin Improvement District is requesting bids on the 12600 South Mountain View Corridor Sewer Project in Salt Lake County, Utah, with bids due November 10, 2026. Only contractors prequalified for the Multiple Mountain View Corridor Sewer Projects are eligible to bid — a restrictive eligibility requirement that filters the market to six named prequalified contractors: Newman Construction, Inc. (Riverton, UT); Nix Construction (South Ogden, UT); Red Pine Construction, LLC (American Fork, UT); Silver Spur Construction, LLC (American Fork, UT); Spade Excavating, Inc. (Bluffdale, UT); and Whitaker Construction Co. Inc. (Brigham City, UT).

The scope includes installation of approximately 2,620 linear feet of 30-inch sanitary sewer pipeline, 10 sanitary sewer manholes, two guided bore crossings under Mountain View Corridor (UDOT right-of-way) — one 225 feet long and one 81 feet long, both with 42-inch minimum casing — along with landscaping and roadway restoration. Contractors or subcontractors performing trenchless construction and guided bore work must submit additional qualification and experience information per Specification 31 71 00 Tunnel Excavation and Initial Support. No changes or substitutions to listed subcontractors or suppliers are permitted after bid opening without written owner approval.

Bidders must submit a notarized bid bond, with all surety companies appearing on the U.S. Department of the Treasury's current list (Circular 570, as amended) and authorized to transact business in Utah. Upon award, the selected contractor must commence work within ten days after receiving the Notice to Proceed. Bids are valid and binding for sixty days after bid opening, or such longer period as specified in the Invitation to Bid unless mutually extended. Liquidated damages provisions apply for failure to achieve Substantial Completion within the specified contract timeframe.

Opportunity text

Only those contractors that were prequalified for the Multiple Mountain View Corridor Sewer Projects may bid on this project. The Work includes installation of approximately 2,620 linear feet of 30-inch sanitary sewer pipeline, 10 sanitary sewer manholes, 225-foot-long guided bore, 81-foot-long guided bore, both with a 42-inch minimum casing crossing under Mountain View Corridor (UDOT right-of-way), landscaping and roadway restoration, and associated pertinences to construct the new sewer lines in accordance with the Contract Documents.