Windfall Lake Trail Bridges - Juneau Alaska

Award Notice Posted

Solicitation number
12010918R0009
Agency
Awarded
to Oregon Woods, Inc.
Set-aside
Total Small Business

Opportunity facts

Contract number
12010918C0032 Federal contract award
NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Not on record
Place of performance
Juneau Ranger District Windfall Lake Juneau, Alaska 99801, United States

Notice details come from SAM.gov. Updated .

Notice text

13 versions

Update #13 · Latest ·

Awarded Vendors: Oregon Woods, Inc.. Contract Award Dollar Amount: Base Only - $390,220; Base + Option $709,520. Contract Award Date: 2018-09-26.

Update #12 ·

9/20/2018 - additional questions and answers posted.

Update #11 ·

UPDATE 9/13/2018: This amendment extends the due date for receipt of proposals to 10:00 a.m., September 24, 2018. Changes to the RFP are detailed in the attached SF-30.
For offerors who have already submitted a proposal, the schedule has been replaced in its entirety and must be resubmitted. Other changes include an updated period of performance, allowable closure dates of the trail, and additional clauses for inclusion of options. If these changes affect any portion of your originally submitted proposal, you may submit additioinal pages to supplement the original proposal, submit replacement pages to the original or replace your proposal in its entirety. If you choose to submit replacement pages, you must provide sufficent detail regarding which pages in the original proposal are to be replaced.
*********************************************
UPDATE 8/7/18: This update posts an alternate POC for questions and submission of proposals. Questions, proposals, bid guarantee and any other correspondence should be mailed/emailed to both the primary and secondary point of contact. The mailing address in Juneau is the same for both individuals.
*********************************************
This update posts amendment 1.
*********************************************
This update posts the RFP. A pre-proposal conference will be held on Friday July 20, 2018 at 10:00 a.m. Alaska Time. Call in number is:
888-844-9904. When prompted, enter passcode 9933996#
There have been no updates to the draft drawing package since the presoliictation notice was posted.
**********************************************
This requirement is for the removal and replacement of 2 trail bridges on the Windfall Lake Trail at MP 1.119 and MP 2.286. The Windfall Lake Trail is located on the Juneau Ranger District in Juneau Alaska.
The DRAFT drawing package is attached to this notice. The Government does not expect these plans to change between the posting of this notice and issuance of the final RFP.
The estimated value of this requirement is between $250,000 and $500,000..

Update #10 ·

Due date has been changed to Aug 24, 2018.

Update #9 ·

Due date has been changed to Aug 24, 2018

Update #8 ·

UPDATE 8/7/18: This update posts an alternate POC for questions and submission of proposals. Questions, proposals, bid guarantee and any other correspondence should be mailed/emailed to both the primary and secondary point of contact. The mailing address in Juneau is the same for both individuals.
*********************************************
This update posts amendment 1.
*********************************************
This update posts the RFP. A pre-proposal conference will be held on Friday July 20, 2018 at 10:00 a.m. Alaska Time. Call in number is:
888-844-9904. When prompted, enter passcode 9933996#
There have been no updates to the draft drawing package since the presoliictation notice was posted.
**********************************************
This requirement is for the removal and replacement of 2 trail bridges on the Windfall Lake Trail at MP 1.119 and MP 2.286. The Windfall Lake Trail is located on the Juneau Ranger District in Juneau Alaska.
The DRAFT drawing package is attached to this notice. The Government does not expect these plans to change between the posting of this notice and issuance of the final RFP.
The estimated value of this requirement is between $250,000 and $500,000..

Update #7 ·

UPDATE 8/7/18:  This update posts an alternate POC for questions and submission of proposals.  Questions, proposals, bid guarantee and any other correspondence should be mailed/emailed to both the primary and secondary point of contact.  The mailing address in Juneau is the same for both individuals.

*********************************************

This update posts amendment 1.

*********************************************

This update posts the RFP.  A pre-proposal conference will be held on Friday July 20, 2018 at 10:00 a.m. Alaska Time.  Call in number is:

888-844-9904.  When prompted, enter passcode 9933996#

There have been no updates to the draft drawing package since the presoliictation notice was posted.

**********************************************


This requirement is for the removal and replacement of 2 trail bridges on the Windfall Lake Trail at MP 1.119 and MP 2.286.  The Windfall Lake Trail is located on the Juneau Ranger District in Juneau Alaska.

The DRAFT drawing package is attached to this notice.  The Government does not expect these plans to change between the posting of this notice and issuance of the final RFP.

The estimated value of this requirement is between $250,000 and $500,000.

Update #6 ·

This update posts amendment 1.
*********************************************
This update posts the RFP. A pre-proposal conference will be held on Friday July 20, 2018 at 10:00 a.m. Alaska Time. Call in number is:
888-844-9904. When prompted, enter passcode 9933996#
There have been no updates to the draft drawing package since the presoliictation notice was posted.
**********************************************
This requirement is for the removal and replacement of 2 trail bridges on the Windfall Lake Trail at MP 1.119 and MP 2.286. The Windfall Lake Trail is located on the Juneau Ranger District in Juneau Alaska.
The DRAFT drawing package is attached to this notice. The Government does not expect these plans to change between the posting of this notice and issuance of the final RFP.
The estimated value of this requirement is between $250,000 and $500,000..

Update #5 ·

This update posts amendment 1.

*********************************************

This update posts the RFP.  A pre-proposal conference will be held on Friday July 20, 2018 at 10:00 a.m. Alaska Time.  Call in number is:

888-844-9904.  When prompted, enter passcode 9933996#

There have been no updates to the draft drawing package since the presoliictation notice was posted.

**********************************************


This requirement is for the removal and replacement of 2 trail bridges on the Windfall Lake Trail at MP 1.119 and MP 2.286.  The Windfall Lake Trail is located on the Juneau Ranger District in Juneau Alaska.

The DRAFT drawing package is attached to this notice.  The Government does not expect these plans to change between the posting of this notice and issuance of the final RFP.

The estimated value of this requirement is between $250,000 and $500,000.

Update #4 ·

This update posts the RFP. A pre-proposal conference will be held on Friday July 20, 2018 at 10:00 a.m. Alaska Time. Call in number is:
888-844-9904. When prompted, enter passcode 9933996#
There have been no updates to the draft drawing package since the presoliictation notice was posted.
**********************************************
This requirement is for the removal and replacement of 2 trail bridges on the Windfall Lake Trail at MP 1.119 and MP 2.286. The Windfall Lake Trail is located on the Juneau Ranger District in Juneau Alaska.
The DRAFT drawing package is attached to this notice. The Government does not expect these plans to change between the posting of this notice and issuance of the final RFP.
The estimated value of this requirement is between $250,000 and $500,000..

Update #3 ·

This update posts the RFP.  A pre-proposal conference will be held on Friday July 20, 2018 at 10:00 a.m. Alaska Time.  Call in number is:

888-844-9904.  When prompted, enter passcode 9933996#

There have been no updates to the draft drawing package since the presoliictation notice was posted.

**********************************************


This requirement is for the removal and replacement of 2 trail bridges on the Windfall Lake Trail at MP 1.119 and MP 2.286.  The Windfall Lake Trail is located on the Juneau Ranger District in Juneau Alaska.

The DRAFT drawing package is attached to this notice.  The Government does not expect these plans to change between the posting of this notice and issuance of the final RFP.

The estimated value of this requirement is between $250,000 and $500,000.

Update #2 ·

This requirement is for the removal and replacement of 2 trail bridges on the Windfall Lake Trail at MP 1.119 and MP 2.286. The Windfall Lake Trail is located on the Juneau Ranger District in Juneau Alaska.
The DRAFT drawing package is attached to this notice. The Government does not expect these plans to change between the posting of this notice and issuance of the final RFP.
The estimated value of this requirement is between $250,000 and $500,000..

Update #1 ·

This requirement is for the removal and replacement of 2 trail bridges on the Windfall Lake Trail at MP 1.119 and MP 2.286.  The Windfall Lake Trail is located on the Juneau Ranger District in Juneau Alaska.

The DRAFT drawing package is attached to this notice.  The Government does not expect these plans to change between the posting of this notice and issuance of the final RFP.

The estimated value of this requirement is between $250,000 and $500,000.