B08 ANSWERS2.pdf

PDF 139 KB Posted

Attached to
DECONCINNI HVAC Replacement and Install Federal contract opportunity
Solicitation number
W91RUS24R0007
Issued by
Department of the Army Materiel Command Army Contracting Command Aberdeen Proving Ground

About this file

This document contains a solicitation for HVAC replacement and installation services at the DeConcini Hill site. The solicitation is being issued by the Department of the Army Materiel Command Army Contracting Command Aberdeen Proving Ground. The worksite is located within a secured 60'x60' fenced compound that contains tower infrastructure and has an interior work area of approximately 1,800 square feet. The existing HVAC units do not contain heat strips. The solicitation seeks replacement HVAC units that provide cooling only without additional heat strips. No other details are provided on requirements, pricing, or response deadlines.

View the file

Other files for this federal contract opportunity

Other files attached to DECONCINNI HVAC Replacement and Install, newest first.
File Type Posted
B08 R-56 Grounding for Additional QA1.pdf PDF
B08 ADDITIONAL QA1.pdf PDF
B08 ADDITIONAL QA.pdf PDF
B08 Marvair_ComPac 01.18_rev.20.pdf PDF
B08 W91RUS24R0007-03 - Conformed Copy.pdf PDF
B08 CLARIFICATIONS.pdf PDF
B08 W91RUS24R0007-03 - Amend 03.pdf PDF
B08 POP INFORMATION.pdf PDF
B08 W91RUS24R0007-02 - Amend 02.pdf PDF
B08 DC-HVAC_ANSWERS-1_240119.pdf PDF
B08 DC_Hill_HVAC_StripMap.pdf PDF
B08 W91RUS24R0007-01 - Amend 01.pdf PDF
B08 DC_Hill_RadioVault.pdf PDF
B08 CommStat3_PDS.pdf PDF
B08 W91RUS24R0007 - RFQ.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A: The greatest restriction to workspace at the jobsite is a 60'X60' chain-link fence securing the repeater/tower compound. The double gate to compound is between 12 and 15 feet wide. The repeater site infrastructure (tower, repeater vault, generator, and fuel tank) is built in one half of the fenced area. The distance from the HVAC units to the fence is 28 to 30 feet. Once inside the gate, There is a work area of about 1800 Square feet on the side with the HVAC units.

2) And also, for the existing units is there 15 KW heat strips installed? If not, are you looking for heat strips installed, or do you want this to just be a straight cooling system?

A: There are no heat strips on the existing units. I don’t think it will be necessary for the new units to have any. Please design the system to provide cooling only.