Prebid_slides_-_ACA_crew_quarters.ppt

PPT presentation 573 KB Posted

Attached to
Construct ACA Alert Crew Quarters Federal contract opportunity
Solicitation number
W91364-16-R-0001
Issued by
Department of the Army Ohio Army National Guard

About this file

Pre-Bid Slides

View the file

Other files for this federal contract opportunity

Other files attached to Construct ACA Alert Crew Quarters, newest first.
File Type Posted
W91364-16-C-0001_ACA_Crew_Fac.pdf PDF
W91364-16-R-0001_AMENDMENT_06_ACA_Crew.doc DOC document
Sec_26_0513_MEDIUM-VOLTAGE_CABLES.pdf PDF
Sec_26_0913_POWER_MONITORING.pdf PDF
Sec_26_1200_MEDIUM-VOLTAGE_TRANSFORMERS.pdf PDF
Sec_26_4100_LIGHTNING_PROTECTION.pdf PDF
Sec_27_0538_L-V_CABLE_TRAY.pdf PDF
Sec_22_1313_SANITARY_SEWERS.pdf PDF
Sec_22_1113_WATER_DISTRIBUTION_PIPING.pdf PDF
M1-1.pdf PDF
M5-3.pdf PDF
237400ADD1.pdf PDF
OANG_Addendum_No_1_write_up.pdf PDF
M1-2.pdf PDF
Question_3.docx DOCX document
ES-1-Updated.pdf PDF
Section_26_3100_PV_Array.pdf PDF
W91364-16-R-0001_AMENDMENT_02_ACA_Crew.doc DOC document
Pre-bid_attendance_list.pdf PDF
Attachment_A_AF_3065_Breakout_Divisions.xls XLS spreadsheet
Attachment_B_ENVIRONMENTAL_Forms.pdf PDF
ACA_soil_report.pdf PDF
Vol_1_B3_Submission_12-01-2015.pdf PDF
Construct_ACA_Crew_Building_Type_B3_Documents_2015_12_01.pdf PDF
ACA_crew_facility_construction_and_work_areas.pdf PDF
5_D._Energy_Econ_Analysis.pdf PDF
W91364-16-R-0001_ACA_Crew_Fac.pdf PDF
Vol_2_B3_Submission_12_01_2015.pdf PDF
4_EPACT_Energy_Score_Sheet.pdf PDF
3_LEED_Checklist_AirCrew_TypeB3__30_Dec_2015.pdf PDF
1_ACA_Crew_B-3_Narrative_30_Dec_2015.pdf PDF
Show all 31

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Prebid Meeting & Site Survey

WYTD079032: Construct ACA Alert Crew Quarters

Performance period: 270 days

Project is funded

Construction Phasing

Phase 1 – Install temporary construction & security fencing
Phase 2 – Remove portion of existing south fence as required.
Phase 3 – Construct Alert Crew Facility
Phase 4 – Reinstall existing fence to the south of the new facility.
Phase 5 – Remove temporary fencing and demobilize.

Scope of Work

Base Bid – 6500 sf facility and all supporting demolition, site work and utilities for a complete and usable facility.
Project to be certified to LEED Silver
6 Optional Bid Items including roof mounted PV array and solar water heating
Clean-up will be as needed to prevent debris on the parking apron – No Foreign Object Debris (FOD) damage

Site Plan

Site Access, Staging and Security

Single Source Items

Building automation system – Johnson Controls
Fire alarm transceivers – Monaco for reporting fire alarm signals to the base central monitoring station at building 102.
Building Mass Notification Systems – Main Control Panel, Local operating consoles and transceivers – ATI. Strobes, speakers, and other items may be from another manufacturer. The completed system must communicate with the central station at bldg. 118.
Intrusion Detection System – Advantor
Cores for locksets – Schlage Primus 6-pin interchangeable cores with sidebit milling.

Speicial Features of Work

Fire suppression system – wet pipe sprinkler system
HVAC: Lochnivar boilers with an AAON RTU and VAVs
“Easy Button” – Overhead hangar door control – see drawing E3-1. Wiring to connect to 2” UG conduit west of 601.
Room A-107 – SCIF – acoustical and physical security features.
Klaxon – alert system with ready lights, etc

Miscellaneous

Stored materials – won’t be paid for unless properly stored, and supplier invoices provided. Only large ticket items, etc…
Laydown areas will be the grass and landscaped areas to the west of building 127 or as approved by the contracting officer
Contractor parking will be in the base centralized parking lots.
FAA requirements for cranes