018100 - GENERAL COMMISSIONING REQUIREMENTS.DOC
DOC document 34 KB Posted
- Attached to
- Construction Indefinite Delivery-Indefinite Quantity (IDIQ) Multiple Award Task Order Contracts (MATOC) Federal contract opportunity
- Solicitation number
- W91364-12-R-0005
About this file
GENERAL COMMISSIONING
View the file
Other files for this federal contract opportunity
Show all 50
Construction Indefinite Delivery-Indefinite Quantity (IDIQ) Multiple Award Task Order Contracts (MATOC) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNIT TRAINING EQUIPMENT SITE ADD/ALT
Copyright 2010 by The American Institute of Architects (AIA)
Exclusively published and distributed by Architectural Computer Services, Inc. (ARCOM) for the AIA
SECTION 018100 - GENERAL COMMISSIONING REQUIREMENTS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
B. OPR and BoD documentation are included by reference for information only.
1.2 SUMMARY
A. Section includes general requirements that apply to implementation of commissioning without regard to specific systems, assemblies, or components.
B. Related Sections:
1. Division 1 Section 018150 "Commissioning of HVAC" for commissioning process activities for HVAC&R systems, assemblies, equipment, and components.
1.3 DEFINITIONS
A. BoD: Basis of Design. A document that records concepts, calculations, decisions, and product selections used to meet the OPR and to satisfy applicable regulatory requirements, standards, and guidelines. The document includes both narrative descriptions and lists of individual items that support the design process.
B. Commissioning Plan: A document that outlines the organization, schedule, allocation of resources, and documentation requirements of the commissioning process.
C. CA: Commissioning Authority.
D. OPR: Owner's Project Requirements. A document that details the functional requirements of a project and the expectations of how it will be used and operated. These include Project goals, measurable performance criteria, cost considerations, benchmarks, success criteria, and supporting information.
E. Systems, Subsystems, Equipment, and Components: Where these terms are used together or separately, they shall mean "as-built" systems, subsystems, equipment, and components.
1.4 COMMISSIONING TEAM
A. Members Appointed by the Contractor with the Government's approval: Individuals, each having the authority to act on behalf of the entity he or she represents, explicitly organized to implement the commissioning process through coordinated action. The commissioning team shall consist of, but not be limited to, Project superintendent and subcontractors, installers, suppliers, and specialists deemed appropriate by the CA.
B. Members Appointed by Owner:
1. CA: The designated person, company, or entity that plans, schedules, and coordinates the commissioning team to implement the commissioning process. The Government will designate a CA or will engage the CA under a separate contract.
2. Representatives of the facility user and operation and maintenance personnel.
3. Architect and engineering design professionals.
1.5 OWNER'S RESPONSIBILITIES
A. Provide the OPR documentation to the CA and each Contractor for information and use.
B. Assign operation and maintenance personnel and schedule them to participate in commissioning team activities.
C. Provide the BoD documentation, prepared by Architect and approved by Government, to the CA and Contractor for use in developing the commissioning plan, systems manual, and operation and maintenance training plan.
1.6 CONTRACTOR'S RESPONSIBILITIES
A. Contractor shall assign representatives with expertise and authority to act on its behalf and shall schedule them to participate in and perform commissioning process activities including, but not limited to, the following:
1. Evaluate performance deficiencies identified in test reports and, in collaboration with entity responsible for system and equipment installation, recommend corrective action.
2. Cooperate with the CA for resolution of issues recorded in the Issues Log.
3. Attend commissioning team meetings held on an as needed basis.
4. Integrate and coordinate commissioning process activities with construction schedule.
5. Review and accept construction checklists provided by the CA.
6. Complete electronic construction checklists as Work is completed and provide to the Commissioning Authority on an as requested basis.
7. Review and accept commissioning process test procedures provided by the Commissioning Authority.
8. Complete commissioning process test procedures.
1.7 CA'S RESPONSIBILITIES
A. Organize and lead the commissioning team.
B. Provide commissioning plan.
C. Convene commissioning team meetings.
D. Provide Project-specific construction checklists and commissioning process test procedures.
E. Verify the execution of commissioning process activities using random sampling. The sampling rate may vary from 1 to 100 percent. Verification will include, but is not limited to, equipment submittals, construction checklists, training, operating and maintenance data, tests, and test reports to verify compliance with the OPR. When a random sample does not meet the requirement, the CxA will report the failure in the Issues Log.
F. Prepare and maintain the Issues Log.
G. Prepare and maintain completed construction checklist log.
H. Witness systems, assemblies, equipment, and component startup.
I. Compile test data, inspection reports, and certificates; include them in the systems manual and commissioning process report.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 018100
| Project No; 390265 GENERAL COMMISSIONING REQUIREMENTS |
| 018100 - 3 |