018100 - GENERAL COMMISSIONING REQUIREMENTS.DOC

DOC document 34 KB Posted

Attached to
Construction Indefinite Delivery-Indefinite Quantity (IDIQ) Multiple Award Task Order Contracts (MATOC) Federal contract opportunity
Solicitation number
W91364-12-R-0005
Issued by
Department of the Army Ohio Army National Guard

About this file

GENERAL COMMISSIONING

View the file

Other files for this federal contract opportunity

Other files attached to Construction Indefinite Delivery-Indefinite Quantity (IDIQ) Multiple Award Task Order Contracts (MATOC), newest first.
File Type Posted
proposal questions and answers MATOC.pdf PDF
site visit information.pdf PDF
329200 - TURF AND GRASSES.DOC DOC document
334100 - STORM UTILITY DRAINAGE PIPING.DOC DOC document
312000 - EARTH MOVING.DOC DOC document
315000 - EXCAVATION SUPPORT AND PROTECTION.DOC DOC document
12-R-0005-0001.pdf PDF
A201.pdf PDF
P-102.PDF PDF
E-102.pdf PDF
013200 - CONSTRUCTION PROGRESS DOCUMENTATION.DOC DOC document
S-104.PDF PDF
A303.pdf PDF
015000 - TEMPORARY FACILITIES AND CONTROLS.DOC DOC document
221119 SF - DOMESTIC WATER PIPING SPECIALTIES.DOC DOC document
E-109.pdf PDF
E-107.pdf PDF
cr_recyclables_tracking_report_form_9feb2011.xlsx XLSX spreadsheet
265100 - INTERIOR LIGHTING.DOC DOC document
237339 SF - INDOOR DIRECT-FIRED HEATING AND VENTILATING UNITS.DOC DOC document
012500 - SUBSTITUTION PROCEDURES.DOC DOC document
104416 - FIRE EXTINGUISHERS.DOC DOC document
016000 - PRODUCT REQUIREMENTS.DOC DOC document
101400 - SIGNAGE.DOC DOC document
013100 - PROJECT MANAGEMENT AND COORDINATION.DOC DOC document
133419 - METAL BUILDING SYSTEMS.DOC DOC document
220529 SF - HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT.DOC DOC document
224500 SF - EMERGENCY PLUMBING FIXTURES.DOC DOC document
078413 - PENETRATION FIRESTOPPING.DOC DOC document
260519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES.DOC DOC document
072100 - THERMAL INSULATION.DOC DOC document
089119 - FIXED LOUVERS.doc DOC document
232123 SF - HYDRONIC PUMPS.doc DOC document
042200 - CONCRETE UNIT MASONRY.DOC DOC document
083613 - SECTIONAL DOORS.DOC DOC document
ED-100.pdf PDF
085113 - ALUMINUM WINDOWS.DOC DOC document
230500_FL - COMMON WORK RESULTS FOR HVAC.DOC DOC document
233713 SF - DIFFUSERS REGISTERS AND GRILLES.DOC DOC document
230516 SF - EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING.DOC DOC document
230553 SF - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT.DOC DOC document
017839 - PROJECT RECORD DOCUMENTS.DOC DOC document
230523 SF - GENERAL-DUTY VALVES FOR HVAC PIPING.DOC DOC document
C-103.pdf PDF
C-010.PDF PDF
E-106.pdf PDF
051200 STRUCTURAL STEEL FRAMING.DOC DOC document
220548 SF - VIBRATION AND SEISMIC CONTROLS FOR PLUMBING PIPING AND EQUIPMENT.DOC DOC document
M-104.PDF PDF
230713 SF - DUCT INSULATION.DOC DOC document
Show all 50

Construction Indefinite Delivery-Indefinite Quantity (IDIQ) Multiple Award Task Order Contracts (MATOC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNIT TRAINING EQUIPMENT SITE ADD/ALT

Copyright 2010 by The American Institute of Architects (AIA)

Exclusively published and distributed by Architectural Computer Services, Inc. (ARCOM) for the AIA

SECTION 018100 - GENERAL COMMISSIONING REQUIREMENTS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.

B. OPR and BoD documentation are included by reference for information only.

1.2 SUMMARY

A. Section includes general requirements that apply to implementation of commissioning without regard to specific systems, assemblies, or components.

B. Related Sections:

1. Division 1 Section 018150 "Commissioning of HVAC" for commissioning process activities for HVAC&R systems, assemblies, equipment, and components.

1.3 DEFINITIONS

A. BoD: Basis of Design. A document that records concepts, calculations, decisions, and product selections used to meet the OPR and to satisfy applicable regulatory requirements, standards, and guidelines. The document includes both narrative descriptions and lists of individual items that support the design process.

B. Commissioning Plan: A document that outlines the organization, schedule, allocation of resources, and documentation requirements of the commissioning process.

C. CA: Commissioning Authority.

D. OPR: Owner's Project Requirements. A document that details the functional requirements of a project and the expectations of how it will be used and operated. These include Project goals, measurable performance criteria, cost considerations, benchmarks, success criteria, and supporting information.

E. Systems, Subsystems, Equipment, and Components: Where these terms are used together or separately, they shall mean "as-built" systems, subsystems, equipment, and components.

1.4 COMMISSIONING TEAM

A. Members Appointed by the Contractor with the Government's approval: Individuals, each having the authority to act on behalf of the entity he or she represents, explicitly organized to implement the commissioning process through coordinated action. The commissioning team shall consist of, but not be limited to, Project superintendent and subcontractors, installers, suppliers, and specialists deemed appropriate by the CA.

B. Members Appointed by Owner:

1. CA: The designated person, company, or entity that plans, schedules, and coordinates the commissioning team to implement the commissioning process. The Government will designate a CA or will engage the CA under a separate contract.

2. Representatives of the facility user and operation and maintenance personnel.

3. Architect and engineering design professionals.

1.5 OWNER'S RESPONSIBILITIES

A. Provide the OPR documentation to the CA and each Contractor for information and use.

B. Assign operation and maintenance personnel and schedule them to participate in commissioning team activities.

C. Provide the BoD documentation, prepared by Architect and approved by Government, to the CA and Contractor for use in developing the commissioning plan, systems manual, and operation and maintenance training plan.

1.6 CONTRACTOR'S RESPONSIBILITIES

A. Contractor shall assign representatives with expertise and authority to act on its behalf and shall schedule them to participate in and perform commissioning process activities including, but not limited to, the following:

1. Evaluate performance deficiencies identified in test reports and, in collaboration with entity responsible for system and equipment installation, recommend corrective action.

2. Cooperate with the CA for resolution of issues recorded in the Issues Log.

3. Attend commissioning team meetings held on an as needed basis.

4. Integrate and coordinate commissioning process activities with construction schedule.

5. Review and accept construction checklists provided by the CA.

6. Complete electronic construction checklists as Work is completed and provide to the Commissioning Authority on an as requested basis.

7. Review and accept commissioning process test procedures provided by the Commissioning Authority.

8. Complete commissioning process test procedures.

1.7 CA'S RESPONSIBILITIES

A. Organize and lead the commissioning team.

B. Provide commissioning plan.

C. Convene commissioning team meetings.

D. Provide Project-specific construction checklists and commissioning process test procedures.

E. Verify the execution of commissioning process activities using random sampling. The sampling rate may vary from 1 to 100 percent. Verification will include, but is not limited to, equipment submittals, construction checklists, training, operating and maintenance data, tests, and test reports to verify compliance with the OPR. When a random sample does not meet the requirement, the CxA will report the failure in the Issues Log.

F. Prepare and maintain the Issues Log.

G. Prepare and maintain completed construction checklist log.

H. Witness systems, assemblies, equipment, and component startup.

I. Compile test data, inspection reports, and certificates; include them in the systems manual and commissioning process report.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 018100

Project No; 390265 GENERAL COMMISSIONING REQUIREMENTS
018100 - 3