096813 tile carpeting.pdf

PDF 13 KB Posted

Attached to
CONSTRUCT USPFO WAREHOUSE
Solicitation number
W91364-09-B-0003
Issued by

About this file

096813 tile carpeting.pdf

View the file

Other files

File Type Posted
ADDENDUM NO 03 USPFO Narrative.pdf PDF
ADDENDUM NO 03 CSMS PH II Narrative.pdf PDF
USPFO_S201W.pdf PDF
E101.pdf PDF
E404.pdf PDF
USPFO_S002W.pdf PDF
262726 wiring devices.pdf PDF
000 USPFO Specs Combined.pdf PDF
220519 meters and gages for plumbing piping.pdf PDF
USPFO_S401W.pdf PDF
013300d attachment submittal register.pdf PDF
095113 acoustical panel ceilings.pdf PDF
224500 emergency plumbing fixtures.pdf PDF
015000 temporary facilities and controls.pdf PDF
072410 polymer-based exterior finish system —
C500.pdf PDF
USPFO_F303W.pdf PDF
USPFO_M401W.pdf PDF
USPFO_FA602W.pdf PDF
OHARNG-USPFO-A-212bW .pdf PDF
079200 joint sealants.pdf PDF
OHARNG-USPFO-A-724W .pdf PDF
I101.pdf PDF
USPFO_P601W.pdf PDF
088500 decorative film for glass.pdf PDF
OHARNG-USPFO-A-816W .pdf PDF
079500 expansion control.pdf PDF
013100 project management and coordination.pdf PDF
OHARNG-USPFO-A-415W .pdf PDF
099113 exterior painting.pdf PDF
USPFO_S212W.pdf PDF
012300 optional bid items.pdf PDF
220548 vibration and seismic controls for plumbing piping and equipment.pdf PDF
220529 hangers and supports for plumbing piping and equipment.pdf PDF
104416 fire extinguishers.pdf PDF
230553 identification for hvac piping and equipment.pdf PDF
263323 central battery equipment.pdf PDF
275116 public address system.pdf PDF
OHARNG-USPFO-G-115W .pdf PDF
OHARNG_USPFO_Q203W.pdf PDF
E502.pdf PDF
018113 sustainable design requirements.pdf PDF
210500 common work results for fire suppression.pdf PDF
OHARNG-USPFO-G-120W .pdf PDF
260543 underground ducts and raceways for electrical systems.pdf PDF
262816 enclosed switches and circuit breakers.pdf PDF
OHARNG-USPFO-A-710W .pdf PDF
E302.pdf PDF
C200.pdf PDF
019113 general commissioning requirements.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F5W61608 USPFO Warehouse Ohio Army National Guard Rev. 0 Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

TILE CARPETING 096813 - 1

SECTION 096813 - TILE CARPETING

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes modular, tufted carpet tile.

1.2 SUBMITTALS

A. Product Data: For each product indicated.

B. Shop Drawings: Show the following:

1. Carpet tile type, color, and dye lot.

2. Pattern of installation.

3. Insets and borders.

4. Edge, transition, and other accessory strips.

5. Transition details to other flooring materials.

C. Samples: For each color and texture required.

1. Carpet Tile: Full-size Sample.

2. Exposed Edge, Transition, and other Accessory Stripping: 12-inch- long

Samples.

D. LEED Submittal:

1. Product Data for Credit EQ 4.3:

a. For carpet tile, documentation indicating compliance with testing and product requirements of Carpet and Rug Institute's "Green Label Plus" program.

b. For installation adhesive, including printed statement of VOC content.

E. Product Schedule: For carpet tile. Use same designations indicated on Drawings.

F. Maintenance data.

1.3 QUALITY ASSURANCE

A. Installer Qualifications: An experienced installer who is certified by the Floor Covering Installation Board or who can demonstrate compliance with its certification program requirements.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

TILE CARPETING 096813 - 2

B. Mockups: Before installing carpet tile, build mockups to verify selections made under sample submittals and to demonstrate aesthetic effects and set quality standards for materials and execution.

1. Approved mockups may become part of the completed Work if undamaged at time of Substantial Completion.

1.4 DELIVERY, STORAGE, AND HANDLING

A. Comply with CRI 104, Section 5, "Storage and Handling."

1.5 PROJECT CONDITIONS

A. Comply with CRI 104, Section 7.2, "Site Conditions; Temperature and Humidity" and Section 7.12, "Ventilation."

B. Environmental Limitations: Do not install carpet tiles until wet work in spaces is complete and dry, and ambient temperature and humidity conditions are maintained at the levels indicated for Project when occupied for its intended use.

C. Do not install carpet tiles over concrete slabs until slabs have cured and are sufficiently dry to bond with adhesive and concrete slabs have pH range recommended by carpet tile manufacturer.

D. Where demountable partitions or other items are indicated for installation on top of carpet tiles, install carpet tiles before installing these items.

1.6 WARRANTY

A. Special Warranty for Carpet Tiles: Manufacturer's standard form in which manufacturer agrees to repair or replace components of carpet tile installation that fail in materials or workmanship within specified warranty period. Failures include, but are not limited to, more than 10 percent loss of face fiber, edge raveling, snags, runs, loss of tuft bind strength, dimensional stability, excess static discharge, and delamination.

1. Warranty Period: 10 years from date of Substantial Completion.

1.7 EXTRA MATERIALS

A. Furnish extra materials described below, before installation begins, that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

TILE CARPETING 096813 - 3

1. Carpet Tile: Full-size units equal to 5 percent of amount installed for each type indicated, but not less than 10 sq. yd..

PART 2 - PRODUCTS

2.1 CARPET TILE

A. Products: Subject to compliance with requirements, provide one of the following:

1. Lee’s Carpet

a. Color: #348 Nautica.

b. Pattern: Connexion Modular #GT023.

c. Source: Kevin O’Brien 314-276-3012

2. Lee’s Carpet

a. Color: #508 Mineral.

b. Pattern: StepUp Modular #DD763.

c. Source: Kevin O’Brien 314-276-3012

B. Fiber Content: 100% Antron Legacy nylon 6.6 with DuraTech Soil Protection by Invista

C. Fiber Type: 100% Antron Legacy nylon 6.6 with DuraTech soil Protection by Invista

D. Pile Characteristic: Cut-and-loop pile.

E. Yarn Twist: NA

F. Yarn Count: NA

G. Density: 8,082 oz./cu. yd.

H. Pile Thickness: .098” average for finished carpet tile per ASTM D 6859.

I. Stitches: 12 stitches per inch

J. Gage: 1/12” gauge in ends per inch

K. Total Weight: 22 oz./sq. yd. for finished carpet tile.

L. Primary Backing/Backcoating: Encycle-100% PVC-Free Thermoplastic composite

M. Secondary Backing: Manufacturer's standard material

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

TILE CARPETING 096813 - 4

N. Backing System: Non PVC thermo plastic - Encycle

O. Size: 24 by 24 inches.

P. Applied Soil-Resistance Treatment: Dura-Tech.

Q. Antimicrobial Treatment: NA

2.2 INSTALLATION ACCESSORIES

A. Trowelable Leveling and Patching Compounds: Latex-modified, hydraulic-cement-based formulation provided or recommended by carpet tile manufacturer.

B. Adhesives: Water-resistant, mildew-resistant, nonstaining, pressure-sensitive type to suit products and subfloor conditions indicated, that complies with flammability requirements for installed carpet tile and is recommended by carpet tile manufacturer for releasable installation.

1. VOC Limits: Provide adhesives with VOC content not more than 50 g/L when calculated according to 40 CFR 59, Subpart D (EPA method 24).

PART 3 - EXECUTION

3.1 INSTALLATION

A. General: Comply with CRI 104, Section 14, "Carpet Modules," and with carpet tile manufacturer's written installation instructions.

B. Installation Method: As recommended in writing by carpet tile manufacturer.

C. Extend carpet tile into toe spaces, door reveals, closets, open-bottomed obstructions, removable flanges, alcoves, and similar openings.

D. Install pattern parallel to walls and borders.

END OF SECTION 096813