GI003_AMD_furniture.pdf
PDF 339 KB Posted
- Attached to
- SC-00008-20 Renovate Building 3-1947
- Solicitation number
- W912PM22B0013
About this file
This solicitation seeks proposals for a firm-fixed-price contract to renovate a two-story, 21,401 square foot administrative building at Fort Bragg, North Carolina. The scope of work includes renovating and repurposing the existing building into adequate workspace and installing classified telecommunications cabling throughout. The project budget is between $5-10 million. The North American Industry Classification System code is 236220 and the size standard is $39.5 million. This is a 100% small business set-aside issued by the U.S. Army Corps of Engineers, Wilmington District. The solicitation will be distributed electronically and proposals are due by the date specified in the System for Award Management. Offerors must be registered in SAM to be eligible for award. Interested parties should contact the Contract Specialist or Contracting Officer for additional information.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A. CONTRACTOR SHALL COMPLY WITH CURRENT NORTH CAROLINA DEPARTMENT OF
ENVIRONMENTAL QUALITY (DEQ) EROSION AND SEDIMENT CONTROL PLANNING AND
DESIGN MANUAL AND FORT BRAGG WATER MANAGEMENT BRANCH (WMB) STANDARDS FOR
EROSION CONTROL WORK, IF APPLICABLE.
B. ALL NCDOT STANDARDS REFERENCES WILL BE THE LATEST EDITION. CONTRACTOR MAY
REFER TO HTTPS://CONNECT.NCDOT.GOV, IF APPLICABLE.
C. CONTRACTOR SHALL COMPLY WITH CURRENT UFC, NC BUILDING CODE, ABA, NFPA, FORT
BRAGG DESIGN GUIDELINES AND OTHER APPLICABLE REQUIREMENTS AS INDICATED ON
THESE CONTRACT DOCUMENTS.
7. DEMOLITION AND CONSTRUCTION
A. ALL CONSTRUCTION AFFECTING TRAFFIC SHALL COMPLY WITH THE FORT BRAGG TRAFFIC
CONTROL IDG, MUTCD, AND NCDOT STANDARD DRAWINGS AND SPECIFICATIONS - LATEST
EDITION. AN ALTERNATE EMERGENCY TRAFFIC CONTROL DETOUR MAY BE REQUIRED.
8. TRAFFIC CONTROL
A. UNLESS SPECIFICALLY NOTED TO BE REMOVED, ALL EXISTING BUILDING COMPONENTS
AND OTHER SITE ITEMS SHALL REMAIN INTACT AND BE PROTECTED AGAINST DAMAGE
DURING THE CONSTRUCTION PERIOD.
B. THE CONTRACTOR SHALL EXERCISE CAUTION DURING DEMOLITION OPERATIONS. THE
CONTRACTOR SHALL REPAIR AND RESTORE ALL EXISTING MATERIAL TO REMAIN THAT IS
DAMAGED. MATERIAL REPAIRS SHALL MATCH EXISTING ADJACENT FINISHED SURFACES
DAMAGES REQUIRING REPLACEMENT WILL BE COORDINATED WITH THE GOVERNMENT,
PRIOR TO REPLACEMENT, AT NO COST TO THE GOVERNMENT.
C. BASED ON AN 2013 INSPECTION REPORT PROVIDED BY THE GOVERNMENT, ASBESTOS WAS
DISCOVERED IN MASTIC UNDER FLOOR TILES BENEATH CARPET WITHIN CORRIDORS AND
OTHER SPACES IN THE BUILDING. ASBESTOS CONTAINING MATERIALS SHALL BE ABATED AND
IF THE CONTRACTOR SUSPECTS OTHER HAZARDOUS MATERIALS ARE PRESENT HE SHALL
NOTIFY THE CONTRACTOR OFFICER'S REPRESENTATIVE IMMEDIATELY.
D. ALL EXISTING FURNITURE INSIDE BUILDING 3-1947 SHALL BECOME PROPERTY OF THE
CONTRACTOR. CONTRACTOR MUST REMOVE ALL FURNITURE FROM GOVERNMENT
PROPERTY.
6. STANDARDS
9. EXISTING UTILITY INTERRUPTIONS
A. EXISTING UTILITIES MAY BE INTERRUPTED FOR A MAXIMUM OF 12 HOURS AT A TIME.
CONTRACTOR IS REQUIRED TO CONTACT THE COR AND OBTAIN APPROVAL PRIOR TO
ANTICIPATED INTERRUPTION. SEE SPECIFICATIONS FOR PER-APPROVAL REQUIREMENTS.
B. ALL UTILITY INTERRUPTIONS AND DURATIONS SHALL BE INDICATED ON THE
CONTRACTOR'S SCHEDULE AND COORDINATED WITH THE COR.
C. FIRE ALARM INTERRUPTIONS SHALL BE SCHEDULED IN WRITING WITH THE COR A MINIMUM OF
14 DAYS IN ADVANCE.
10. EXTERIOR UTILITY WORK
A. ANY EXTERIOR ELECTRICAL WORK PERFORMED BY THE CONTRACTOR SHALL BE COORDINATED
WITH SANDHILLS UTILITY SERVICE (SUS). CONTACT MR. DAVID KEITH AT (910) 496-2220.
B. ANY EXTERIOR WATER OR SANITARY SEWER WORK PERFORMED BY THE CONTRACTOR SHALL
BE COORDINATED WITH AMERICAN STATES UTILITY SERVICES (ASUS). CONTACT ALLEN
FORRESTER AT (910) 495-1311.
C. ANY EXTERIOR GAS WORK PERFORMED BY THE CONTRACTOR SHALL BE COORDINATED WITH
PEIDMONT NATURAL GAS (PNG). CONTACT CLAYTON PARKER AT (910) 247-7992.
11. SECURITY PROCEDURES FOR ACCESS
A. CONTRACTOR SHALL FOLLOW JSOC SECURITY REQUIREMENTS AT ALL TIMES.
REFER TO SPECIFICATION SECTION 01 00 60 FOR ADDITIONAL INFORMATION.
B. CONTRACTOR SHALL FOLLOW JSOC SECURITY POLICIES ON SITE AT ALL TIMES.
IN GENERAL, THE CONTRACTOR WILL BE GIVEN FULL ACCESS TO THE PROJECT SITE AS
SHOWN ON THE PLANS, HOWEVER, PERIODS MAY BE ENCOUNTERED WHEN NO CONTRACTOR OR
SUBCONTRACTOR PERSONNEL WILL BE ALLOWED ON THE CONSTRUCTION SITE. WORK
STOPPAGES DUE TO THOSE EVENTS WILL BE HELD TO AN ABSOLUTE MINIMUM, AND THE
CONTRACTOR WILL BE GIVEN AS MUCH ADVANCED NOTICE AS POSSIBLE. NOTICE OF THE WORK
STOPPAGE AND RESUMPTION WILL BE RELAYED THROUGH THE COR WHO WILL COMMUNICATE
THIS INFORMATION TO CONTRACTOR. SUCH WORK STOPPAGE WILL NOT BE THE BASIS FOR A
CLAIM AGAINST THE GOVERNMENT. THE GOVERNMENT HAS THE RIGHT TO INSTRUCT THE
CONTRACTOR TO EVACUATE THE SITE WITHOUT PRIOR NOTIFICATION AT ANY TIME AND MAY
REFUSE ENTRY OF ANY OR ALL CONTRACTOR PERSONNEL.
C. THE CONTRACTOR'S PERSONNEL MUST WEAR IDENTIFICATION IN ACCORDANCE WITH
JSOC SECURITY POLICIES AT ALL TIMES.
D. ACCESS TO THE PROJECT AREA IS LIMITED TO NORMAL WORK HOURS (0730 TO 1600)
UNLESS SPECIFICALLY APPROVED BY THE COR FOR SPECIFIED PERIODS OF TIME OUTSIDE THE
NORMAL WORK HOURS. EXCLUDES FEDERAL HOLIDAYS.
E. IT IS A CRIME UNDER 18 USC 795 TO PHOTOGRAPH DEFENSE INSTALLATIONS WITHOUT
FIRST OBTAINING THE PERMISSION OF THE COMMANDING OFFICER OF THE MILITARY
INSTALLATION. IT IS ALSO A CRIME UNDER 18 USC 797 TO REPRODUCE, PUBLISH SELL OR GIVE
AWAY ANY PHOTOGRAPH, PICTURE OR GRAPHIC REPRESENTATION OF A DEFENSE INSTALLATION
WITHOUT FIRST OBTAINING THE PERMISSION OF THE COMMANDING OFFICER OF THE MILITARY
INSTALLATION AND JSOC.
F. DESIGNATE THE INSTALLATION AS A RESTRICTED AREA. RESTRICTED AREA POSTING RESTRICTS
PERSONS GAINING ACCESS TO MILITARY INSTALLATION FROM CONDUCTING IMAGERY
SURVEILLANCE, PHOTOGRAPHY AND VIDEO RECORDING WITHOUT THE INSTALLATION
COMMANDERS AND JSOC CONSENT.
G. THE INTRODUCTION OF WEAPONS, AMMUNITION, EXPLOSIVES OR OTHER PROHIBITED ITEMS AND
PHOTOGRAPHY OF THE FACILITIES IS PROHIBITED WITHOUT SPECIFIC AUTHORIZATION FROM THE
JSOC COMMANDER.
2. CONSTRUCTION PHASING & PROJECT SCHEDULES
A. THE CONTRACTOR SHALL ENSURE THAT HIS ACTIVITIES SHALL NOT INTERFERE WITH THE
OPERATIONS CONDUCTED AT SURROUNDING BUILDINGS AND WORK AREAS.
B. CONTRACTOR SHALL NOT BLOCK ACCESS TO EXISTING BUILDINGS, ROADS AND/OR FACILITIES.
C. CONTRACTOR SHALL PROVIDE A PROJECT SCHEDULE TO THE COR PRIOR TO CONSTRUCTION
AND MOBILIZATION. CONTRACTOR SHALL PROVIDE WEEKLY UPDATES ON THE PROJECT
SCHEDULE FOR FULL DURATION OF PROJECT. THE WEEKLY UPDATES SHALL BE PROVIDED
SHOWING THE SCHEDULE FOR THE UPCOMING 2 WEEKS INCLUDE UPDATES REGARDING THE
PHASING OF CONSTRUCTION.
D. ADJACENT AREAS WILL BE OCCUPIED BY GOVERNMENT PERSONNEL THROUGHOUT THE
CONSTRUCTION PERIOD. CONTRACTOR SHALL NOT ALLOW CONSTRUCTION ACTIVITIES TO
DISRUPT ON-GOING GOVERNMENT OPERATIONS DURING DEMOLITION AND CONSTRUCTION.
3. CONTRACTOR STAGING AREA
A. SEE EROSION AND SEDIMENT CONTROL SHEET CG101.
A. THE LAMONT ROAD BORROW PIT IS ANTICIPATED TO BE CLOSED DURING THE ENTIRE
CONSTRUCTION PHASE OF THIS PROJECT FOR OBTAINING FILL MATERIAL. NO DISPOSAL
ALLOWED.
B. FORT BRAGG LANDFILL IS CLOSED AND CAN NO LONGER ACCEPT/DISPOSE OF BORROW.
A. CONTRACTOR SHALL INSTALL TEMPORARY FENCING WITHIN THE GENERAL PROJECT SITE,
COORDINATE LOCATION WITH JSOC AND COR. THE TYPE, MATERIAL, HEIGHT, AND LOCATION
OF THE FENCE SHALL BE IN ACCORDANCE WITH SPECIFICATIONS AND APPROVED BY THE
GOVERNMENT PRIOR TO INSTALLATION.
B. ALL WORK ACTIVITIES AND STORAGE SHALL BE CONFINED WITHIN THE ESTABLISHED
PROJECT LIMITS UNLESS SPECIFICALLY AUTHORIZED BY THE COR FOR SPECIFIED PERIODS
OF TIME.
C. THE CONTRACTOR MUST HAVE AT LEAST ONE EMPLOYEE ONSITE TO RECEIVE AND DIRECT
PLACEMENT OF DELIVERED MATERIALS AND SUPPLIES.
1. CONSTRUCTION METHODS AND PROCEDURES & CONTRACTOR ACCESS
A. THE CONTRACTOR SHALL PROVIDE SANITARY FACILITIES FOR HIS WORKERS DURING THE
ENTIRE CONSTRUCTION PHASE. COORDINATE LOCATION WITH COR. SANITARY FACILITIES
SHOULD BE PROVIDED IN ACCORDANCE WITH THE USACE SAFETY AND HEALTH REQUIREMENTS
MANUAL EM 385-1-1.
B. THE WORK FOR THIS PROJECT CONSISTS OF FURNISHING ALL LABOR, EQUIPMENT,
TRANSPORTATION, AND MATERIALS NECESSARY TO PERFORM ALL WORK IN STRICT
ACCORDANCE WITH THE PROJECT SPECIFICATIONS, APPLICABLE DIRECTORATE OF PUBLIC
WORKS (DPW) DRAWINGS, UNIFIED FACILITIES CRITERIA (UFC), JOINT SPECIAL OPERATIONS
(JSOC) STANDARDS, FORT BRAGG INSTALLATION DESIGN GUIDELINES (IDG) AND OTHER
CONTRACT DOCUMENTS. THE SCOPE OF WORK OF THIS CONTRACT IS REFERENCED IN
PROJECT SPECIFICATIONS SECTION 01 00 05.
C. THE CONTRACTOR SHALL REFER TO THE PROJECT SPECIFICATIONS IN ALL SITUATIONS. THE
CONTRACTOR SHALL BRING CONFLICTS BETWEEN PROJECT SPECIFICATIONS AND PLANS TO
THE ATTENTION OF THE CONTRACTING OFFICER REPRESENTATIVE (COR) FOR RESOLUTION. ALL
MATERIALS AND WORKMANSHIP SHALL CONFORM TO THE PROJECT SPECIFICATIONS.
D. ALL DIMENSIONS AND CONDITIONS TIED TO OR OTHERWISE RELATED TO EXISTING
CONSTRUCTION ARE SUBJECT TO FIELD VERIFICATION BY THE CONTRACTOR. VERIFICATION
SHALL BE MADE PRIOR TO ORDERING, FABRICATING, OR CONSTRUCTING ANY RELATED
STRUCTURAL COMPONENTS. WHERE DISCREPANCIES OCCUR, THE CONTRACTOR SHALL ADVISE
THE COR IMMEDIATELY AND PROVIDE THE COR WITH THE CORRECT DIMENSIONS AND
CONDITIONS.
E. THE CONTRACTOR SHALL ADEQUATELY PROTECT ALL EXISTING SITE FEATURES AND FACILITIES
DURING DEMOLITION AND CONSTRUCTION.
F. PRIOR TO ANY DEMOLITION OR NEW WORK COMMENCING THE ELECTRICAL CONTRACTOR
SHALL ARRANGE A MEETING WITH THE COR AND JSOC REPRESENTATIVE TO DISCUSS ALL
ELECTRICAL OUTAGE PROCEDURES FOR SHUTDOWN OF ANY ELECTRICAL PANELS. THE
ELECTRICAL CONTRACTOR MUST NOTIFY THE COR, IN WRITING, AT LEAST 7 DAYS PRIOR TO
ANY ELECTRICAL SHUTDOWN DURING DEMOLITION OR NEW CONSTRUCTION.
G. THIS PROJECT IS WITHIN A CATEGORY 3 SITE. THE PROJECT IS WITHIN ACTIVE IRP SITE FTBR-063
WITH KNOWN GROUNDWATER CONTAMINATION EXCEEDING THE NCDEQ GROUNDWATER
QUALITY STANDARDS (2L). GROUNDWATER DEPTHS AT THIS SITE ARE APPROXIMATELY 8-44
FEET BELOW GROUND SURFACE. EXCAVATING OR BORING ACTIVITIES HAVE THE POTENTIAL TO
ENCOUNTER CONTAMINATED GROUNDWATER. IF CONTAMINATED GROUNDWATER OR SOIL IS
ENCOUNTERED DURING CONSTRUCTION, NOTIFY THE COR IMMEDIATELY AND IT MUST BE
HANDLED IN ACCORDANCE WITH ALL APPLICABLE RULES AND REGULATIONS.
4. LAMONT ROAD BORROW PIT
5. EROSION AND SEDIMENT CONTROL
GENERAL NOTES:
12. PERMITS
D. PERMITS, AS LISTED ABOVE, ARE NOT INTENDED TO BE A COMPLETE LIST. CONTRACTORS ARE TO ADD
ADDITIONAL PERMITS, AS THEY BECOME KNOWN. PERMIT SUBMITTALS ARE TO BE SUBMITTED TO THE
GOVERNMENT FOR REVIEW AND APPROVAL. AVOID OMISSIONS.
INSTALLATION:
· AIR QUALITY (GENERATORS) - DPW-ECB AIR QUALITY PROGRAM MANAGER
· ARMY RADIATION PERMIT (ARP) - INSTALLATION RADIATION SAFETY OFFICER - VICTOR D. WOOTEN, 910-9088-4138
· BOILERS & GENERATORS PERMIT - DPW-ECB AIR QUALITY - MIKE FISHER, REM
· BORROW PIT PERMIT - DPW - ENVIRONMENTAL BRANCH (SUBMIT 14 CALENDAR DAYS PRIOR TO WORK) -
BORROW PIT HAS BEEN CLOSED BY DPW UNTIL FURTHER NOTICE.
· CONSTRUCTION AND DEMOLITION (C&D) WASTE PERMIT - FOR FORT BRAGG LAMONT ROAD
CONSTRUCTION AND DEMOLITION LANDFILL FACILITY - DPW - ENVIRONMENTAL BRANCH. LANDFILL HAS
REACHED ITS CAPACITY TO ACCEPT CONSTRUCTION AND DEMOLITION WASTE AND WILL NO LONGER
ACCEPT CONSTRUCTION AND DEMOLITION WASTE (TO INCLUDE FRIABLE ASBESTOS CONTAINING
MATERIALS). SEE DPW'S SOLID WASTE AND RECYCLING REQUIREMENTS, DATED 6 OCT 2016, OR
CONTACT DAN MESSIER AT DANIEL.J.MESSIER@MAIL.MIL OR 910-396-6873.
· DIGGING/EXCAVATION PERMIT (FB FORM 1605-E) - DPW - FACILITIES ENGINEER (SUBMIT 15 CALENDAR
DAYS PRIOR TO WORK)
· ENVIRONMENTAL PERMITS (POSSIBLE 180 DAY PROCESS). SEE SPEC SECTION 01 57 19.
·· REGULATORY PERMITS
·· CLEAN AIR ACT (CAA) [FEDERAL, STATE AND LOCAL] - DPW - INSTALLATION ENVIRONMENTAL OFFICE
(AIR PROGRAM MANAGER)
·· GENERAL USE PERMITTED EQUIPMENT (SEE FAR 52.236-7.)
·· STREAM CROSSING PERMIT (SEE CLEAN WATER ACT SECTION 404 AND SECTION 401 (WATER QUALITY)).
·· TITLE V AIR PERMITS (BASED ON TYPE OF MATERIAL DUST, BOILERS AND DOMESTIC WATER HEATERS) -
DPW - ENVIRONMENTAL BRANCH, ENVIRONMENTAL COMPLIANCE BRANCH (ECB)
·· TRANSPORTER AND DISPOSAL FACILITIES PERMITS
·· EXCAVATION
· IRRIGATION PERMIT - DPW WATER QUALITY PROGRAM MANAGER, 910-907-3214.
· STORAGE TANKS AND WATER QUALITY PROGRAM, FORT BRAGG-DPW-ECB, 910-907-3214.
· LANDFILL DISPOSAL PERMIT - DPW-ENVIRONMENTAL SUSTAINMENT DIVISION (ESD), 910-396-3372.
· PHOTOGRAPHY - INSTALLATION PERMIT - DIRECTOR OPERATIONS DIRECTORATE DCS G3/5/7 - POC IS
MR. DREDDRICK BROWN, DSN 225-8469 OR COM (703) 695-8469.
· TRAFFIC CONTROL PERMIT - DPW TRANSPORTATION ENGINEER, RAY GOFF, 910-907-1759
· UTILITY CONNECTION
· UTILITY OUTAGE REQUESTS - FT BRAGG DPW
COUNTY
· WATER WELL
FEDERAL
· NOTICE OF PROPOSED CONSTRUCTION OR ALTERATION - FAA FORM 7460-1
NC STATE:
· ASBESTOS REMOVAL FOR DEMOLITION/RENOVATION - NCPH, RALEIGH (10 WORKING DAYS PRIOR TO
REMOVAL)
· AIR QUALITY
· DEMOLITION
· EROSION & SEDIMENT CONTROL (E&SC) CERTIFICATE OF APPROVAL/PERMIT - DEQ (FORMALLY
NCDENR) DEPT OF WATER QUALITY (DWQ), UNDER GENERAL PERMIT NO. NCG010000 FOR
"CONSTRUCTION ACTIVITIES THAT ARE ALSO SUBJECT TO THE NORTH CAROLINA SEDIMENTATION
POLLUTION CONTROL ACT OF 1973."
· GENERAL STORMWATER DISCHARGE
· GEOTHERMAL (POSSIBLE COUNTY INVOLVEMENT)
· SEPTIC SYSTEM (POSSIBLE COUNTY INVOLVEMENT)
· STORMWATER MANAGEMENT - NCDEQ AND FT BRAGG WATER MANAGEMENT BRANCH
· WATER SYSTEM SERVICE (FIRE PROTECTION AND DOMESTIC WATER SERVICE) - NCDEQ.
ASUS (AMERICAN STATES UTILITY SERVICES) :
· WATER AND SANITARY SEWER
COE SAFETY:
· CONFINED SPACE ENTRY PERMIT - (SEE EM 385-1-1, DATED 30 NOV 2014, SECTION 34 (STARTING ON
PAGE 34-1)
· ENERGIZED WORK PERMIT - MUST BE SUBMITTED TO THE COR IN ADVANCE FOR ACCEPTANCE. (SEE
EM 385-1-1, DATED 30 NOV 14, PARAGRAPH 11.A.02C).
· HOT WORK PERMIT - DEFINED AS HOT RIVETING, WELDING, BURNING, ABRASIVE BLASTING, OR OTHER
FIRE- OR SPARK-PRODUCING OPERATIONS. (SEE EM 385-1-1, DATED 30 NOV 2014, PARA 09.A.04 (PAGE
9-1 & 2) & PAGE Q-29. THE FORT BRAGG FIRE DEPARTMENT REQUIRES NOTICE 14 CALENDAR DAYS
PRIOR TO WORK, FOR:
·· WELDING
·· CUTTING
·· HEATING
A. CONTRACTOR SHALL SECURE ALL PERMITS NECESSARY FOR CONSTRUCTION OF THE PROJECT.
DETERMINE FEE BASIS AS APPROPRIATE AND PAY ALL FILING FEES AT NO ADDITIONAL COST TO THE
GOVERNMENT. CONSTRUCTION SHALL NOT BEGIN ON ANY PHASE WITHOUT APPROPRIATE PERMITS.
B. PERMITS ARE TO BE MAINTAINED IN THE CONTRACTOR'S ONSITE CONSTRUCTION OFFICE, ORGANIZED
IN A 3 RING BINDER, TABBED AND WITH A TABLE OF CONTENTS FOR INSPECTION BY THE GOVERNMENT.
C. THE FOLLOWING PERMITS MAY BE REQUIRED FOR PROJECTS AT FORT BRAGG.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
G
H
J
K
L
M
N
P
S U
B M
I T
T E
D
B
Y
C H
E C
K E
D
B
Y
D R
A W
N
B
Y
D E
S I G
N E
D
B
Y
C O
N T
R A
C T
N
O
S O
L I C
I T
A T
I O
N
N
O
I S
S U
E
D
A T
E
S I Z
E
M A
R K
D E
S C
R I P
T I O
N D
A T
E
SHEET ID
J O
N E
S
F
R A
N K
L I
R
D
S
U I T
E
R A
L E
I G
H
N
C
F
A X
L I C
E N
S E
F
R E
A D
Y
T
O
A
D V
E R
T I S
E
A N
S I
D
CONTROLLED UNCLASSIFIED INFORMATION
CONTROLLED UNCLASSIFIED INFORMATION
F O
B
A
G G
N
O R
H
A R
O L I N
A
R E
N O
V A
B
U I L D
I N
G
J S
O C
Y
S
C
M A
R C
H
US Army Corps of Engineers
F I L
M
E
U S
A
R M
Y
C
O R
P S
E
N G
I N
E E
R S
D
A R
L I N
G T
V E
W I L M
I N
G T
O N
N
O R
H
R
O L I N
A
W I L M
I N
G T
D
I S
T R
I C
T
W P
M B
GI003
G E
N E
R A
L
C
O N
S T
R U
C T
I O
N
N
O T
E S
D
S
A L T
S M
A N
M
M
I L E
Y
M
B
A R
T O
N
R
D
O W
N S
G I D
G N