(SEE ITEM 13)
1 713
W912PL19R0011
AMEND 0001
Remove and Replace SF1442 Remove and Replace Section 00 21 16 - Instructions to Proposers Remove and Replace Section 00 22 16 - Supplementary Instructions to Proposers Remove and Replace Section 00 22 00 - Supplementary Instructions Add Environmental Assessment - Geo Tech Report
IFT SITE PREP AJO & CASA GRANDE AOR W912PL19R0011
TOHONO O'ODHAM NATION, ARIZONA
PROJECT TABLE OF CONTENTS
DIVISION 00 –
00 01 05 Certification Page 00 10 00 CLIN Schedule 00 21 16 Instructions to Proposers 00 22 00 Supplementary Instructions 00 22 16 Supplementary Instructions to Proposers
00 45 00 REPRESENTATIONS AND CERTIFICATIONS
00 70 00 CONDITIONS OF THE CONTRACT
00 73 00 SUPPLEMENTARY CONDITIONS
00 73 46 WAGE RATES
DIVISION 01 - GENERAL REQUIREMENTS
01 10 00 STATEMENT OF WORK
01 27 00 Measurement and Payment
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 37 00 SECURITY AND OPERATIONAL REQUIREMENT
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.10 10 QUALITY CONTROL SYSTEM (QCS)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 20.00 10 ENVIRONMENTAL PROTECTION (PROVIDED IN NEXT SUBMITTAL)
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL
01 62 35 RECYCLED / RECOVERED MATERIALS
01 78 00 CLOSEOUT SUBMITTALS
DIVISION 03 – CONCRETE
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 00.00 10 CONCRETE ACCESSORIES
03 20 00.00 10 CONCRETE REINFORCING
03 30 00.00 10 CAST-IN-PLACE CONCRETE
03 39 00.00 10 CONCRETE CURING
03 40 00.00 10 PLANT-PRECAST CONCRETE PRODUCTS
DIVISION 31 – EARTHWORK
31 00 00 EARTHWORK
31 05 19 GEOTEXTILE
31 11 00 CLEARING AND GRUBBING
31 32 11 SOIL SURFACE EROSION CONTROL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 23 GRADED-CRUSHED AGGREGATE BASE COURSE
32 11 34 PORTLAND CEMENT-STABILIZED SURFACE COURSE
32 15 00 AGGREGATE SURFACE COURSE
32 15 00.00 29 SURFACE BLADING
32 92 19 SEEDING
DIVISION 33 – UTILITIES
33 40 00 STORM DRAINAGE UTILITIES
Environmental Assessment Geo Tech Report
-- End of Project Table of Contents --
IFT SITE PREP AJO & CASA GRANDE AOR
TOHONO O’ODHAM NATION SECTION 00 21 165 W912PL19R0011
Amendment 0001
00 21 16 - 1
Section 00 21 16 - Instructions to Proposers
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code
Reporting
JUL 2016
52.204-18 Commercial and Government Entity Code Maintenance
JUL 2016
52.204-22 Alternative Line Item Proposal JAN 2017 52.211-1 Availability of Specifications Listed in the GSA
Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29
AUG 1998
52.211-2 Availability of Specifications, Standards, and Data Item Descriptions Listed in the Acquisition Streamlining and Standardization Information System (ASSIST)
APR 2014
52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.215-20 Requirements for Certified Cost or Pricing Data or
Information Other Than Certified Cost or Pricing Data
OCT 2010
52.215-22 Limitations on Pass-Through Charges-- Identification of Subcontract Effort
OCT 2009
52.217-3 Evaluation Of Options APR 1984 52.219-14 Limitations on Subcontracting. Jan 2017 52.222-5 Construction Wage Rate Requirements--Secondary
Site of the Work
MAY 2014
52.225-12 Notice of Buy American Requirement - Construction Materials Under Trade Agreements
MAY 2014
52.228-1 Bid Guarantee SEP 1996 52.228-2 Additional Bond Security OCT 1997 52.232-38 Submission of Electronic Funds Transfer
Information with Offer
JUL 2013
52.236-28 Preparation of Proposals--Construction OCT 1997 252.204-7008 Compliance With Safeguarding Covered Defense
Information Controls
OCT 2016
252.236-7008 Contract Prices-Bidding Schedules DEC 1991
CLAUSES INCORPORATED BY FULL TEXT
52.0000-4010 INQUIRIES
00 21 16 - 2
52.211-3 AVAILABILITY OF SPECIFICATIONS NOT LISTED IN THE GSA INDEX OF FEDERAL
SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS (JUN 1988) Error! Bookmark not defined.
52.211-4 AVAILABILITY FOR EXAMINATION OF SPECIFICATIONS NOT LISTED IN THE GSA INDEX
OF FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS (JUN 1988)
..................................................................................................................................... Error! Bookmark not defined.
52.216-1 TYPE OF CONTRACT (APR 1984)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
52.233-2 SERVICE OF PROTEST (SEP 2006)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)
52.0000-4010 INQUIRIES
1. Any prospective offeror desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders/offerors before submission of their bids/offers. Oral explanations or instructions given before award of a contract are not binding. Any information given to a prospective offeror concerning a solicitation will be furnished promptly to all other prospective offerors as an amendment to the solicitation, if that information is necessary in submitting offers or if lack of it would be prejudicial to other prospective bidders/offerors.
2. All inquiries relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet at www.projnet.org/projnet.
A. To submit and review bid inquiry items, bidders will need to be a current registered user, or self register into the ProjNet system.
To access the Bid Inquiry system, go to the ProjNet web page and fill in:
- Managing Agency - USACE
- Email address
- Key Access (this is the Bidder Inquiry Key - see below for key)
- Click on “Sign In”
- You will be prompted for the answer to your secret question on the next screen
00 21 16 - 3
If this is your first time accessing ProjNet, you will be directed to a screen titled “User account not found. Please create one using the form below”. Fill in the requested information (name, company, city, phone #, etc)
B. From this page, you may view all bidder inquiries or add an inquiry. Please Note:
Offerors shall only submit one question per inquiry. All inquiries containing multiple questions may be rejected.
C. Offerors will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by the technical team.
D. The Solicitation Number is: W912PL19R0011.
The Bidder Inquiry Key is: RF3DWB-E89X7C
3. The Bidder Inquiry System will be unavailable for new inquiries 5 business days prior to bid/proposal submission in order to ensure adequate time allotted to form an appropriate response and amend the solicitation if necessary.
4. Offerors are requested to review the specifications in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
5. The ProjNet call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
6. Responses on the Bidder Inquiry System do not revise, change, amend or supersede the provisions of the solicitation. Changes to the solicitation must be by written amendment thereto. Any Bidder Inquiry System response that can be interpreted to be in conflict with the solicitation or amendment, shall be subordinate to the conflicting provision, term, and/or note, wherever it appears in the solicitation, until revised or altered by a written amendment to the solicitation.
Additionally, offerors may not anticipate a change to the solicitation until the change, revision, correction, or alteration of the solicitation is actually made, in writing and published as an amendment to the solicitation
00 21 16 - 4
(End of provision)
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Priced contract resulting from this solicitation.
(End of provision)
FAR 52.217-3 EVALUATION EXCLUSIVE OF OPTIONS (APR 1984) The Government will evaluate offers for award purposes by including only the price for the basic requirement;
i.e.,options will not be included in the evaluation for award purposes.
52.219-14 Limitations on Subcontracting.
As prescribed in 19.508(e) or 19.811-3 (e), insert the following clause:
Limitations on Subcontracting (Jan 2017)
(a) This clause does not apply to the unrestricted portion of a partial set-aside.
(b) Applicability. This clause applies only to-
(1) Contracts that have been set aside or reserved for small business concerns or 8(a) participants;
(2) Part or parts of a multiple-award contract that have been set aside for small business concerns or 8(a) participants; and
(3) Orders set aside for small business or 8(a) participants under multiple-award contracts as described in 8.405-5 and 16.505(b)(2)(i)(F).
(c) By submission of an offer and execution of a contract, the Offeror/Contractor agrees that in performance of the contract in the case of a contract for-
(1) Services (except construction). At least 50 percent of the cost of contract performance incurred for personnel shall be expended for employees of the concern.
(2) Supplies (other than procurement from a nonmanufacturer of such supplies). The concern shall perform work for at least 50 percent of the cost of manufacturing the supplies, not including the cost of materials.
(3) General construction. The concern will perform at least 15 percent of the cost of the contract, not including the cost of materials, with its own employees.
00 21 16 - 5
(4) Construction by special trade contractors. The concern will perform at least 25 percent of the cost of the contract, not including the cost of materials, with its own employees.
(End of clause)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE
EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
25.0 – 30.0% 6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
00 21 16 - 6
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Tohono O'dham Nation, which is located southwest of Tucson, AZ, Pima County, AZ
52.228-1 Bid Guarantee. As prescribed in 28.101-2 , insert a provision or clause substantially as follows:
Bid Guarantee (Sept 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g.,bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds-
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
00 21 16 - 7
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Clause)
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
U.S. Army Corps of Engineers, 915 Wilisre Bldg, Suie 930 Attn: CESPL-CTE Sandra Oquita Los Angeles, CA 90017
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of provision)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for--
May 29 and May 30. The start time will be at 8:00 am. The POC is Karl Ahlen and PH # is 213 280 8580
(c) Participants will meet at--
00 21 16 - 8
Everyone will meet at the San Miguel Gate which is at the end of IR 19. The directions are to drive to Seles AZ 86 go south on IR 19 until there is a 90 degree left turn. Go onto the gravel road and stop by the gate at the border. 31O33’18.39” N and 111o46”12.25”W
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://farsite.hill.af.mil/
52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)
Portions of this solicitation are altered as follows:
NA
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any NA (48 CFR Chapter NA) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
IFT SITE PREP AJO & CASA GRANDE AOR W912PL-19-R-0011
Amendment 0001
SECTION 00 22 00 - 1
SECTION 00 22 00 - SUPPLEMENTARY INSTRUCTIONS
I. REQUIREMENT FOR SEPARATE PRICE AND TECHNICAL PROPOSAL
II. GENERAL INSTRUCTIONS
III. SPECIFIC INSTRUCTIONS FOR THE PRICE PROPOSAL, VOLUME 1
IV. SPECIFIC INSTRUCTIONS FOR THE TECHNICAL PROPOSAL, VOLUME 2
V. TECHNICAL PROPOSAL SUBMISSION REQUIREMENTS
VI. PROPOSAL EXPENSE AND PRE-AWARD COSTS
VII. ATTACHMENTS
Amendment 0001
SECTION 00 22 00 - 2
I. REQUIREMENT FOR SEPARATE PRICE AND TECHNICAL PROPOSAL
A. EACH OFFEROR MUST SUBMIT BOTH A PRICE PROPOSAL AND A
TECHNICAL PROPOSAL. THE PRICE PROPOSAL AND THE TECHNICAL
PROPOSAL MUST BE SUBMITTED AS SEPARATE (I.E., PHYSICALLY
DISTINCT) VOLUMES. BOTH THE PRICE PROPOSAL AND THE TECHNICAL
PROPOSAL MUST BE RECEIVED BY THE CLOSING DATE AND TIME SET FOR
RECEIPT OF PROPOSALS.
B. THE PRICE PROPOSAL (VOLUME 1) MUST INCLUDE THE SIGNED
ACKNOWLEDGEMENT SHEET(STANDARD FORM SF-1442, BLOCK #19),
INCLUDING ACKNOWLEDGEMENT OF ALL AMENDMENTS; THE
COMPLETED PRICING SCHEDULE; THE OFFEROR’S OFFICIAL ONLINE ORCA
REPRESENTATIONS AND CERTIFICATIONS; BID BOND, AND ANY OTHER
REQUIREMENTS DESCRIBED IN PARAGRAPH 3 BELOW.
C. THE TECHNICAL PROPOSAL (VOLUME 2) CONSISTS OF ALL INFORMATION
AND MATERIAL SUBMITTED OR PROVIDED FOR EVALUATION IN RESPONSE
TO THE TECHNICAL (NON-COST) EVALUATION FACTORS SPECIFIED IN
BOTH THIS SECTION AND SECTION 00 22 16: SUPPLEMENTARY
INSTRUCTIONS TO PROPOSERS. THE PURPOSE OF THE TECHNICAL
EVALUATION IS TO ASSESS THE QUALITY OF EACH OFFER (I.E., THE
QUALITY OF THE PROPOSED PRODUCT OR SERVICE), TO DETERMINE THE
CAPABILITY OF EACH OFFEROR, AND TO DETERMINE THE ABILITY OF
EACH OFFEROR TO PERFORM THE PERSPECTIVE CONTRACT
SUCCESSFULLY.
D. OFFERORS SUBMITTING PROPOSALS FOR THIS PROJECT SHOULD LIMIT
SUBMISSION TO DATA ESSENTIAL FOR EVALUATION OF PROPOSALS SO
THAT A MINIMUM OF TIME AND MONIES WILL HAVE BEEN EXPENDED IN
PREPARING THE INFORMATION REQUIRED HEREIN. HOWEVER, IN ORDER
TO BE EFFECTIVELY AND EQUITABLY EVALUATED, THE PROPOSALS MUST
INCLUDE INFORMATION SUFFICIENTLY DETAILED TO CLEARLY DESCRIBE
THE OFFEROR’S RESPONSES TO THE SOLICITATION FACTORS WHICH MAY
OR MAY NOT REQUIRE SUCH DETAILS ON EXPERIENCE, TECHNICAL
APPROACH AND MANAGEMENT CAPABILITIES TO SUCCESSFULLY
COMPLETE THE PROJECT. PROPOSALS SHOULD FOLLOW THE ORDER
SEQUENCE SET FORTH IN THE RFP. INFORMATION PROVIDED OUT OF
SEQUENCE WILL NOT BE EVALUATED AND MAY RESULT IN THE
OFFEROR’S DISQUALIFICATION FROM AWARD.
Amendment 0001
SECTION 00 22 00 - 3
II. GENERAL INSTRUCTIONS
A. WRITTEN PROPOSAL MATERIALS SHALL BE SUBMITTED IN STANDARD
THREE RING LOOSE-LEAF BINDERS AND ON A CD-ROM USING A
SEARCHABLE “.PDF” FORMAT. PROPOSALS SHALL BE TABBED AND
LABELED IN A MANNER TO AFFORD EASY IDENTIFICATION FROM A TABLE
OF CONTENTS. FONT SIZE SHALL NOT BE LESS THAN 10 POINT. EACH
PAGE SHALL BE IDENTIFIED WITH THE APPROPRIATE PAGE NUMBER
CENTERED AT THE BOTTOM OF THE PAGE. SHEET SIZE OF THE PROPOSAL
CONTENTS SHALL BE 8-1/2 INCHES X 11 INCHES. THE PROPOSED
PRELIMINARY CONSTRUCTION SCHEDULE SHEET SIZE MAY BE 11 INCHES
X 17 INCHES AND WILL COUNT AS ONE PAGE. OFFERORS THAT DO NOT
MEET THESE REQUIREMENTS MAY BE SUBJECT TO REJECTION.
B. PROPOSAL REVISIONS SHALL BE SUBMITTED AS PAGE REPLACEMENTS
WITH REVISED TEXT READILY IDENTIFIABLE, E.G., BOLD FACE PRINT OR
UNDERLINING. THE SOURCE OF THE REVISION, E.G., ERROR, OMISSION, OR
CLARIFICATION, OR AMENDMENT SHALL ALSO BE ANNOTATED FOR EACH
REVISION. PROPOSAL REPLACEMENT PAGES SHALL BE NUMBERED,
SHALL BE CLEARLY MARKED “REVISED” SHALL SHOW THE DATE OF THE
REVISION, SHALL BE SUBMITTED IN APPROPRIATE NUMBER OF COPIES
E.G., IF TWO (2) COPIES OF THE ORIGINAL PAGE WERE REQUIRED, THEN
TWO (2) COPIES OF THE REVISED PAGE WILL ALSO BE REQUIRED, AND
SHALL BE A DIFFERENT COLOR THAN THE ORIGINAL PAGE THEY ARE TO
REPLACE.
C. PLEASE ENSURE THAT THE OUTSIDE OF EACH SEPARATE VOLUME IS
CLEARLY MARKED TO INDICATE ITS CONTENTS AND THE IDENTITY OF
THE OFFEROR. ADDITIONALLY, THE ORIGINAL COST/PRICE PROPOSAL
AND ORIGINAL TECHNICAL PROPOSAL SHOULD BE CLEARLY INDICATED
ON THE OUTSIDE COVER.
D. “CONFIDENTIAL” PROJECTS CANNOT BE SUBMITTED TO DEMONSTRATE
CAPABILITY UNLESS ALL OF THE INFORMATION REQUIRED FOR
EVALUATION PURPOSES AS SPECIFIED HEREIN CAN NONETHELESS BE
PROVIDED TO THE GOVERNMENT AS PART OF THE OFFEROR’S TECHNICAL
PROPOSAL. OFFERORS THAT INCLUDE IN THEIR PROPOSALS
INFORMATION THAT THEY DO NOT WANT TO DISCLOSE TO THE PUBLIC
FOR ANY PURPOSE, OR USED BY THE GOVERNMENT EXCEPT FOR
EVALUATION PURPOSES, MUST BE CLEARLY MARKED IN ACCORDANCE
WITH THE INSTRUCTIONS AT FAR 52.215-1, “INSTRUCTIONS TO OFFEROR-
COMPETITIVE ACQUISITION,” PARAGRAPH (3), “RESTRICTIONS ON
DISCLOSURE AND USE OF DATA.”
E. DRAWINGS, SKETCHES AND SCHEDULES SUBMITTED AS PART OF
Amendment 0001
SECTION 00 22 00 - 4
OFFEROR’S VOLUME 2, TECHNICAL PROPOSAL, SHALL ONLY BE USED FOR
THE PURPOSE OF EVALUATING THE PROPOSAL. SUCH DOCUMENTS SHALL
NOT BE THE BASIS FOR ALTERING THE REQUIREMENTS, TERMS AND
CONDITIONS OF THE SOLICITATION. THE PROJECT DURATION AS STATED
IN SECTION 00 73 00 SUPPLEMENTARY CONDITIONS PARAGRAPH 52.211-10
“COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR 1984)
IS AS SET FORTH THEREIN.
III. SPECIFIC INSTRUCTIONS FOR THE PRICE PROPOSAL, VOLUME 1
A. NUMBER OF SETS OF THE PRICE PROPOSAL
SUBMIT THE PRICE PROPOSAL AS FOLLOWS: ONE ORIGINAL
B. FORMAT AND CONTENTS OF THE PRICE PROPOSAL/LIST OF TABS
THE ORIGINAL AND ALL COPIES OF THE PRICE PROPOSAL SHALL BE
APPROPRIATELY LABELED AS SUCH, SHALL BE ORGANIZED AS
INDICATED BELOW, AND SHALL BE COMPRISED OF THE FOLLOWING:
PROPOSAL COVER SHEET. THE PROPOSAL COVER SHEET IS REQUIRED
BY FAR 52.215-1(C) (2). THIS PROVISION, ENTITLED “INSTRUCTIONS TO
OFFERORS—COMPETITIVE ACQUISITION,” HAS BEEN INCLUDED IN FULL
TEXT IN SECTION 00 21 00 INSTRUCTIONS. PROVIDE THE FOLLOWING
INFORMATION IN THE PROPOSAL COVER SHEET:
• SOLICITATION NUMBER.
• NAME, ADDRESS, TELEPHONE AND FACSIMILE NUMBERS OF THE
OFFEROR (AND EMAIL ADDRESS IF AVAILABLE).
• DUNS, CAGE, AND TAX IDENTIFICATION NUMBERS OF THE OFFEROR.
• STATEMENT SPECIFYING THE EXTENT OF AGREEMENT WITH ALL
TERMS, CONDITIONS, AND PROVISIONS INCLUDED IN THE
SOLICITATION AND THE OFFEROR’S AGREEMENT TO FURNISH ANY OR
ALL ITEMS UPON WHICH PRICES ARE OFFERED; AT THE PRICE SET
OPPOSITE EACH ITEM AS REFLECTED ON THE PROPOSAL SCHEDULE.
• NAMES, TITLES, TELEPHONE AND FACSIMILE NUMBERS (AND EMAIL
ADDRESSES IF AVAILABLE) OF PERSONS AUTHORIZED TO NEGOTIATE
ON THE OFFEROR’S BEHALF WITH THE GOVERNMENT IN CONNECTION
WITH THIS SOLICITATION.
• ACKNOWLEDGMENT THAT THE OFFEROR’S SYSTEM FOR AWARD
MANAGEMENT REGISTRATION IS CURRENT PER FAR CLAUSE 52.204-7,
SYSTEM FOR AWARD MANAGEMENT AND DFARS 252.204-7004,
ALTERNATE A, SYSTEM FOR AWARD MANAGEMENT.
Amendment 0001
SECTION 00 22 00 - 5
TAB CONTENTS OF THE PRICE PROPOSAL
#1 TAB 1 SHALL CONTAIN THE COMPLETED SF 1442, ENTITLED
“SOLICITATION, OFFER AND AWARD” FRONT AND BACK; CERTIFICATE
OF CORPORATE PRINCIPAL, COMPLETED AS APPLICABLE, INCLUDING
CORPORATE SEAL, IF ANY.
#2 SECTION 00 10 00, CONTRACT LINE ITEM NUMBER SCHEDULE. THE
COMPLETED CONTRACT LINE ITEM NUMBER SCHEDULE WITH THE
OFFEROR’S PROPOSED CONTRACT LINE ITEM PRICES INSERTED IN THE
APPROPRIATE SPACES. PRICES MUST BE PROPOSED FOR ALL
CONTRACT LINE ITEMS AND PRICES SUB-LINE ITEMS. UNIT PRICES ARE
TO BE EXTENDED TO THE ACTUAL “DOLLAR AND CENTS” AMOUNTS
(I.E., TO TWO DECIMAL PLACES). DO NOT ROUND OFF TO THE NEAREST
DOLLAR. CHECK YOUR PRICING SUBMISSIONS VERY CAREFULLY FOR
MATHEMATICAL AND CLERICAL ERRORS PRIOR TO SUBMISSION.
#3 OFFICIAL ONLINE SAM (SYSTEM OF AWARD MANAGEMENT)
REPRESENTATIONS & CERTIFICATIONS
#4 A BID GUARANTEE, STANDARD FORM 24, “BID BOND.”
#5 TEAMING AGREEMENT OR IRREVOCABLE SUBCONTRACTOR OFFERS (IF
APPLICABLE)
IV. SPECIFIC INSTRUCTIONS FOR THE TECHNICAL PROPOSAL, VOLUME 2
A. THE TECHNICAL PROPOSAL SHALL NOT INCLUDE ANY COST
INFORMATION AND SHALL NOT EXCEED 35 PAGES.
VOLUME 2, TECHNICAL PROPOSAL, SHALL NOT EXCEED 35 PAGES,
EXCLUDING THE PROPOSAL COVER SHEET, TABLE OF CONTENTS, TAB
DIVIDERS. ALSO THE PAST PERFORMANCE QUESTIONNAIRES (PPQ),
PERFORMANCE EVALUATIONS FROM PAST PERFORMANCE INFORMATION
RETRIEVAL SYSTEM (PPIRS), INCLUDING CONTRACTOR PERFORMANCE
ASSESSMENT REPORTING SYSTEM (CPARS) WILL NOT COUNT AGAINST
THE PAGE LIMITATION. THE GOVERNMENT WILL NOT BE OBLIGATED TO
EVALUATE ANY INFORMATION BEYOND THE 35 PAGE LIMITATION NOTED
ABOVE. THE OFFEROR SHALL NOT SUBMIT VERBATIM SECTIONS OF THIS
SOLICITATION AS PART OF THEIR PROPOSAL. OFFERORS THAT DO NOT
MEET THESE REQUIREMENTS MAY BE SUBJECT TO REJECTION.
B. NUMBER OF SETS OF THE TECHNICAL PROPOSAL
SUBMIT THE ORIGINAL AND FOUR (4) ADDITIONAL SETS OF THE WRITTEN
TECHNICAL PROPOSAL (I.E., THE ORIGINAL AND FOUR (4) THREE (3)) COPIES
Amendment 0001
SECTION 00 22 00 - 6
OF ALL OF THE INFORMATION REQUIRED BELOW, WITH EACH SET
SEPARATELY PACKAGED). AN ELECTRONIC COPY OF VOLUME 2 SHALL BE
SUBMITTED ON A CD-ROM USING A SEARCHABLE “.PDF” FORMAT.
C. FORMAT AND CONTENTS OF THE TECHNICAL PROPOSAL/LIST OF TABS
THE ORIGINAL AND ALL COPIES OF THE TECHNICAL PROPOSAL SHALL
BE APPROPRIATELY LABELED AS SUCH, SHALL BE ORGANIZED AS
INDICATED BELOW, AND SHALL BE COMPRISED OF THE FOLLOWING:
THE PROPOSAL COVER SHEET AS REQUIRED BY FAR 52.215-1(C)(I)(V). THIS
PROVISION, TITLED “INSTRUCTIONS TO OFFERORS-COMPETITIVE
ACQUISITION,” IS PROVIDED IN FULL TEXT IN SECTION 00 21 00
INSTRUCTIONS.
THE ORIGINAL AND ALL COPIES OF THE TECHNICAL PROPOSAL SHALL BE
APPROPRIATELY LABELED AS SUCH, SHALL BE ORGANIZED AS INDICATED
BELOW, AND SHALL BE COMPRISED OF THE FOLLOWING:
TAB CONTENTS OF THE TECHNICAL PROPOSAL
TAB #1 FACTOR 1: ENVIRONMENTAL COMPLIANCE
TAB #2 FACTOR 2: TECHNICAL APPROACH
TAB #3 FACTOR 3: PAST EXPERIENCE
TAB #4 FACTOR 4: KEY PERSONNEL
TAB #5 FACTOR 5: PAST PERFORMANCE
TAB #6 FACTOR 6: SCHEDULE
V. TECHNICAL PROPOSAL SUBMISSION REQUIREMENTS
SEE ATTACHED FORMS AT THE END OF THIS SECTION AND SECTION 00 22 16
FOR PROPOSAL SUBMISSION REQUIREMENTS, LIST OF EVALUATION FACTORS,
FOR MORE DETAILS.
Amendment 0001
SECTION 00 22 00 - 7
VI. PROPOSAL EXPENSE AND PRE-AWARD COSTS
THIS REQUEST FOR PROPOSAL DOES NOT COMMIT THE GOVERNMENT TO
PAY ANY COSTS INCURRED IN THE PREPARATION AND SUBMISSION OF
THE INITIAL AND ANY SUBSEQUENT PROPOSALS OR FOR ANY COSTS
INCURRED PRIOR TO EXECUTION OF A FORMAL CONTRACT.
VII. ATTACHMENTS
ATTACHMENT # 1: PROJECT EXPERIENCE FORM (TAB 3)
ATTACHMENT # 2: COVER LETTER AND PAST PERFORMANCE QUESTIONNAIRE
(PPQ) (TAB 5)
ATTACHMENT # 3: PERFORMANCE ASSESSMENT REPORT (PAR) (TAB 5)
ATTACHMENT # 4: PERSONNEL RESUME FORM (TAB 4)
Amendment 0001
SECTION 00 22 00 - 8
ATTACHMENT # 1
PROJECT EXPERIENCE FORM
(TAB 3)
OFFEROR’S NAME:
PROVIDE A COMPLETED FORM FOR EACH PROJECT FOR
WHICH EXPERIENCE IS BEING CLAIMED. EXPERIENCE
PROVIDED FOR (CHECK MORE THAN ONE BOX IF
APPLICABLE):
[ ] OFFEROR:
[ ] KEY CONSTRUCTION SUBCONTRACTOR:
WAS PROJECT A FIRM-FIXED-PRICE CONTRACT (Y/N)?
IF NO, WHAT TYPE WAS IT?
PROJECT NAME:
PROJECT LOCATION:
OWNER/CLIENT:
FOR THIS PROJECT FOR WHICH EXPERIENCE IS BEING CLAIMED, FIRM(S)
WORKED AS THE [ ] PRIME CONTRACTOR; OR [ ] SUBCONTRACTOR. IF
EXPERIENCE IS PROVIDED FOR MORE THAN ONE FIRM, CHECK MORE THAN ONE
BOX AS APPROPRIATE FOR EACH FIRM LISTED.
Amendment 0001
SECTION 00 22 00 - 9
BRIEF DESCRIPTION OF PROJECT (INCLUDE, AS APPLICABLE, HOW PROJECT
IS SIMILAR IN SCOPE AND MAGNITUDE TO THE WORK REQUIRED IN THIS
RFP)
CONSTRUCTION CONTRACT AMOUNT OR DESIGN FEE (FOR DESIGNER):
ORIGINAL CONTRACT COMPLETION DATE: ________________________
FINAL CONTRACT COMPLETION DATE: ________________________
ACTUAL COMPLETION DATE: ________________________
PERCENT OF COMPLETION (IF PROJECT IS CURRENTLY UNDER CONSTRUCTION)
EXPLANATION OF ANY LATE FINISH:
WAS THE PROJECT TERMINATED EARLY OR WERE CURE/SHOW CAUSE LETTERS
RECEIVED? ___YES ___NO
EXPLAIN EARLY TERMINATION (DEFAULT/CONVENIENCE) OR CURE/SHOW
CAUSE LETTERS
SAFETY RECORD: ____INJURIES WITH LOST WORKDAYS*, ____INJURIES WITHOUT
LOST WORKDAYS*
(*USE THE NUMBER REPORTED ON OSHA FORM NO. 200 OR EQUIVALENT)
LIST AND EXPLAIN ANY CUSTOMER CONCERNS OR DISSATISFACTION. EXPLAIN
HOW YOU RESPONDED.
SMALL BUSINESS SUBCONTRACTING (COMPLETE FOR OFFEROR (PRIME
CONTRACTOR) ONLY):
Amendment 0001
SECTION 00 22 00 - 10
LARGE BUSINESS OFFERORS ONLY: WHAT WERE T\HE VARIOUS SMALL
BUSINESS PERCENTAGE GOALS IN THE
ORIGINAL CONTRACT, IF APPLICABLE (SEE FAR 52.219-9)? SDB: _______ WOB:
SMALL BUSINESS: _______ VETERAN-OWNED: _______ HUBZONE: _______
WHAT WAS THE ACTUAL PERCENT ACHIEVED AT CONTRACT COMPLETION? SDB:
_______ WOB: _______
SMALL BUSINESS: _______ VETERAN-OWNED: _______ HUBZONE: _______
EXPLANATION—IF GOALS WERE NOT MET:
Amendment 0001
SECTION 00 22 00 - 11
ATTACHMENT #2
NAVFAC / USACE PAST PERFORMANCE QUESTIONNAIRE (PPQ)
OWNER/CLIENT PAST PERFORMANCE SURVEY
(TAB 5)
Amendment 0001
SECTION 00 22 00 - 12
SAMPLE COVER LETTER
DATE
SUBJECT: NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE
NAME AND
ADDRESS OF
REFERENCE
LADIES AND GENTLEMEN:
THE U.S. ARMY CORPS OF ENGINEERS, LOS ANGELES DISTRICT, IS
CONDUCTING A REVIEW OF OUR PAST PERFORMANCE HISTORY AS PART OF
AN UPCOMING SOURCE SELECTION ACQUISITION.
PLEASE COMPLETE THE ATTACHED NAVFAC/USACE PAST PERFORMANCE
QUESTIONNAIRE TO AID THE GOVERNMENT IN ITS EVALUATION OF OUR PAST
PERFORMANCE AND E-MAIL IT DIRECTLY TO THE U.S. ARMY CORPS OF
ENGINEERS A THE BELOW E-MAIL ADDRESS
CHRISTINA.CHAVEZ@USACE.ARMY.MIL..
THE GOVERNMENT IS REQUESTING RECEIPT OF THIS INFORMATION BY 2:00
P.M. ON 27 JUNE 2019.
YOU ARE ADVISED THAT IT IS GOVERNMENT POLICY THAT THE IDENTITY OF
SOURCES PROVIDING PAST PERFORMANCE INFORMATION WILL NOT BE
RELEASED OUTSIDE THE GOVERNMENT.
WE APPRECIATE YOUR EFFORTS TO HELP THE GOVERNMENT FAIRLY
EVALUATE OUR RECORD OF PAST PERFORMANCE. SHOULD YOU HAVE ANY
QUESTIONS RELATED TO THIS MATTER, PLEASE CONTACT MS. CHAVEZ AT
TELEPHONE (213) 452-3246.
SINCERELY,
CONTRACTOR
ATTACHMENT
SECTION 00 22 00 - 13
NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (FORM PPQ-0)
CONTRACT INFORMATION (CONTRACTOR TO COMPLETE BLOCKS 1-4)
1. CONTRACTOR INFORMATION
FIRM NAME: CAGE CODE:
ADDRESS: DUNS NUMBER:
PHONE NUMBER:
EMAIL ADDRESS:
POINT OF CONTACT: CONTACT PHONE NUMBER:
2. WORK PERFORMED AS: PRIME CONTRACTOR SUB CONTRACTOR JOINT
VENTURE OTHER (EXPLAIN)
PERCENT OF PROJECT WORK PERFORMED:
IF SUBCONTRACTOR, WHO WAS THE PRIME (NAME/PHONE #):
3. CONTRACT INFORMATION
CONTRACT NUMBER:
DELIVERY/TASK ORDER NUMBER (IF APPLICABLE):
CONTRACT TYPE: FIRM FIXED PRICE COST REIMBURSEMENT OTHER (PLEASE SPECIFY):
CONTRACT TITLE:
CONTRACT LOCATION:
AWARD DATE (MM/DD/YY):
CONTRACT COMPLETION DATE (MM/DD/YY):
ACTUAL COMPLETION DATE (MM/DD/YY):
EXPLAIN DIFFERENCES:
ORIGINAL CONTRACT PRICE (AWARD AMOUNT):
FINAL CONTRACT PRICE (TO INCLUDE ALL MODIFICATIONS, IF APPLICABLE):
EXPLAIN DIFFERENCES:
4. PROJECT DESCRIPTION:
COMPLEXITY OF WORK HIGH MED ROUTINE
HOW IS THIS PROJECT RELEVANT TO PROJECT OF SUBMISSION? (PLEASE PROVIDE DETAILS SUCH AS
SIMILAR EQUIPMENT, REQUIREMENTS, CONDITIONS, ETC.)
CLIENT INFORMATION (CLIENT TO COMPLETE BLOCKS 5-8)
5. CLIENT INFORMATION
NAME:
TITLE:
PHONE NUMBER:
EMAIL ADDRESS:
6. DESCRIBE THE CLIENT’S ROLE IN THE PROJECT:
7. DATE QUESTIONNAIRE WAS COMPLETED (MM/DD/YY):
8. CLIENT’S SIGNATURE:
NOTE: NAVFAC/USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNAIRE AND SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATIONS. CLIENTS ARE HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER, QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE. PLEASE CONTACT THE OFFEROR FOR USACE POC INFORMATION. THE GOVERNMENT
RESERVES THE RIGHT TO VERIFY ANY AND ALL INFORMATION ON THIS FORM.
SECTION 00 22 00 - 14
ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT
YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE
RATING DEFINITION NOTE
(E) EXCEPTIONAL PERFORMANCE MEETS CONTRACTUAL
REQUIREMENTS AND EXCEEDS MANY TO
THE GOVERNMENT/OWNER’S BENEFIT.
THE CONTRACTUAL PERFORMANCE OF
THE ELEMENT OR SUB-ELEMENT BEING
ASSESSED WAS ACCOMPLISHED WITH
FEW MINOR PROBLEMS FOR WHICH
CORRECTIVE ACTIONS TAKEN BY THE
CONTRACTOR WAS HIGHLY EFFECTIVE.
AN EXCEPTIONAL RATING IS
APPROPRIATE WHEN THE
CONTRACTOR SUCCESSFULLY
PERFORMED MULTIPLE
SIGNIFICANT EVENTS THAT WERE
OF BENEFIT TO THE
GOVERNMENT/OWNER. A
SINGULAR BENEFIT, HOWEVER,
COULD BE OF SUCH MAGNITUDE
THAT IT ALONE CONSTITUTES AN
EXCEPTIONAL RATING. ALSO,
THERE SHOULD HAVE BEEN NO
SIGNIFICANT WEAKNESSES
IDENTIFIED.
(VG) VERY GOOD PERFORMANCE MEETS CONTRACTUAL
REQUIREMENTS AND EXCEEDS SOME TO
THE GOVERNMENT’S/OWNER’S BENEFIT.
THE CONTRACTUAL PERFORMANCE OF
THE ELEMENT OR SUB-ELEMENT BEING
ASSESSED WAS ACCOMPLISHED WITH
SOME MINOR PROBLEMS FOR WHICH
CORRECTIVE ACTIONS TAKEN BY THE
CONTRACTOR WERE EFFECTIVE.
A VERY GOOD RATING IS
APPROPRIATE WHEN THE
CONTRACTOR SUCCESSFULLY
PERFORMED A SIGNIFICANT EVENT
THAT WAS A BENEFIT TO THE
GOVERNMENT/OWNER. THERE
SHOULD HAVE BEEN NO
SIGNIFICANT WEAKNESSES
IDENTIFIED.
(S)
SATISFACTORY
PERFORMANCE MEETS MINIMUM
CONTRACTUAL REQUIREMENTS. THE
CONTRACTUAL PERFORMANCE OF THE
ELEMENT OR SUB-ELEMENT CONTAINS
SOME MINOR PROBLEMS FOR WHICH
CORRECTIVE ACTIONS TAKEN BY THE
CONTRACTOR APPEAR OR WERE
SATISFACTORY.
A SATISFACTORY RATING IS
APPROPRIATE WHEN THERE WERE
ONLY MINOR PROBLEMS, OR
MAJOR PROBLEMS THAT THE
CONTRACTOR RECOVERED FROM
WITHOUT IMPACT TO THE
CONTRACT. THERE SHOULD HAVE
BEEN NO SIGNIFICANT
WEAKNESSES IDENTIFIED. PER DOD
POLICY, A FUNDAMENTAL
PRINCIPLE OF ASSIGNING RATINGS
IS THAT CONTRACTORS WILL NOT
BE ASSESSED A RATING LOWER
THAN SATISFACTORY SOLELY FOR
NOT PERFORMING BEYOND THE
REQUIREMENTS OF THE
CONTRACT.
(M) MARGINAL PERFORMANCE DOES NOT MEET SOME
CONTRACTUAL REQUIREMENTS. THE
CONTRACTUAL PERFORMANCE OF THE
ELEMENT OR SUB-ELEMENT BEING
ASSESSED REFLECTS A SERIOUS
PROBLEM FOR WHICH THE CONTRACTOR
HAS NOT YET IDENTIFIED CORRECTIVE
ACTIONS. THE CONTRACTOR'S
PROPOSED ACTIONS APPEAR ONLY
MARGINALLY EFFECTIVE OR WERE NOT
FULLY IMPLEMENTED.
A MARGINAL IS APPROPRIATE
WHEN A SIGNIFICANT EVENT
OCCURRED THAT THE
CONTRACTOR HAD TROUBLE
OVERCOMING WHICH IMPACTED
THE GOVERNMENT/OWNER.
SECTION 00 22 00 - 15
(U)
UNSATISFACTORY
PERFORMANCE DOES NOT MEET MOST
CONTRACTUAL REQUIREMENTS AND
RECOVERY IS NOT LIKELY IN A TIMELY
MANNER. THE CONTRACTUAL
PERFORMANCE OF THE ELEMENT OR
SUB-ELEMENT CONTAINS SERIOUS
PROBLEM(S) FOR WHICH THE
CONTRACTOR'S CORRECTIVE ACTIONS
APPEAR OR WERE INEFFECTIVE.
AN UNSATISFACTORY RATING IS
APPROPRIATE WHEN MULTIPLE
SIGNIFICANT EVENTS OCCURRED
THAT THE CONTRACTOR HAD
TROUBLE OVERCOMING AND
WHICH IMPACTED THE
GOVERNMENT/OWNER. A
SINGULAR PROBLEM, HOWEVER,
COULD BE OF SUCH SERIOUS
MAGNITUDE THAT IT ALONE
CONSTITUTES AN
UNSATISFACTORY RATING.
(N) NOT
APPLICABLE
NO INFORMATION OR DID NOT APPLY TO
YOUR CONTRACT
RATING WILL BE NEITHER
POSITIVE NOR NEGATIVE.
SECTION 00 22 00 - 16
TO BE COMPLETED BY CLIENT
PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS
YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.
1. QUALITY:
A) QUALITY OF TECHNICAL DATA/REPORT PREPARATION
EFFORTS
E VG S M U N
B) ABILITY TO MEET QUALITY STANDARDS SPECIFIED FOR
TECHNICAL PERFORMANCE E VG S M U N
C) TIMELINESS/EFFECTIVENESS OF CONTRACT PROBLEM
RESOLUTION WITHOUT EXTENSIVE CUSTOMER GUIDANCE
E VG S M U N
D) ADEQUACY/EFFECTIVENESS OF QUALITY CONTROL PROGRAM
AND ADHERENCE TO CONTRACT QUALITY ASSURANCE
REQUIREMENTS (WITHOUT ADVERSE EFFECT ON PERFORMANCE)
E VG S M U N
2. SCHEDULE/TIMELINESS OF PERFORMANCE:
A) COMPLIANCE WITH CONTRACT DELIVERY/COMPLETION
SCHEDULES INCLUDING ANY SIGNIFICANT INTERMEDIATE
MILESTONES. (IF LIQUIDATED DAMAGES WERE ASSESSED OR THE
SCHEDULE WAS NOT MET, PLEASE ADDRESS BELOW)
E VG S M U N
B) RATE THE CONTRACTOR’S USE OF AVAILABLE RESOURCES TO
ACCOMPLISH TASKS IDENTIFIED IN THE CONTRACT
E VG S M U N
3. CUSTOMER SATISFACTION:
A) TO WHAT EXTENT WERE THE END USERS SATISFIED WITH THE
PROJECT?
E VG S M U N
B) CONTRACTOR WAS REASONABLE AND COOPERATIVE IN
DEALING WITH YOUR STAFF (INCLUDING THE ABILITY TO
SUCCESSFULLY RESOLVE DISAGREEMENTS/DISPUTES;
RESPONSIVENESS TO ADMINISTRATIVE REPORTS, BUSINESSLIKE
AND COMMUNICATION)
E VG S M U N
C) TO WHAT EXTENT WAS THE CONTRACTOR COOPERATIVE,
BUSINESSLIKE, AND CONCERNED WITH THE INTERESTS OF THE
CUSTOMER?
E VG S M U N
D) OVERALL CUSTOMER SATISFACTION E VG S M U N
4. MANAGEMENT/ PERSONNEL/LABOR
A) EFFECTIVENESS OF ON-SITE MANAGEMENT, INCLUDING
MANAGEMENT OF SUBCONTRACTORS, SUPPLIERS, MATERIALS,
AND/OR LABOR FORCE?
E VG S M U N
B) ABILITY TO HIRE, APPLY, AND RETAIN A QUALIFIED
WORKFORCE TO THIS EFFORT
E VG S M U N
C) GOVERNMENT PROPERTY CONTROL E VG S M U N
D) KNOWLEDGE/EXPERTISE DEMONSTRATED BY CONTRACTOR
PERSONNEL
E VG S M U N
E) UTILIZATION OF SMALL BUSINESS CONCERNS E VG S M U N
F) ABILITY TO SIMULTANEOUSLY MANAGE MULTIPLE PROJECTS
WITH MULTIPLE DISCIPLINES
E VG S M U N
SECTION 00 22 00 - 17
G) ABILITY TO ASSIMILATE AND INCORPORATE CHANGES IN
REQUIREMENTS AND/OR PRIORITY, INCLUDING PLANNING,
EXECUTION AND RESPONSE TO GOVERNMENT CHANGES
E VG S M U N
H) EFFECTIVENESS OF OVERALL MANAGEMENT (INCLUDING
ABILITY TO EFFECTIVELY LEAD, MANAGE AND CONTROL THE
PROGRAM)
E VG S M U N
5. COST/FINANCIAL MANAGEMENT
A) ABILITY TO MEET THE TERMS AND CONDITIONS WITHIN THE
CONTRACTUALLY AGREED PRICE(S)?
E VG S M U N
B) CONTRACTOR PROPOSED INNOVATIVE ALTERNATIVE
METHODS/PROCESSES THAT REDUCED COST, IMPROVED
MAINTAINABILITY OR OTHER FACTORS THAT BENEFITED THE
CLIENT
E VG S M U N
C) IF THIS IS/WAS A GOVERNMENT COST TYPE CONTRACT,
PLEASE RATE THE CONTRACTOR’S TIMELINESS AND ACCURACY
IN SUBMITTING MONTHLY INVOICES WITH APPROPRIATE BACK-
UP DOCUMENTATION, MONTHLY STATUS REPORTS/BUDGET
VARIANCE REPORTS, COMPLIANCE WITH ESTABLISHED BUDGETS
AND AVOIDANCE OF SIGNIFICANT AND/OR UNEXPLAINED
VARIANCES (UNDER RUNS OR OVERRUNS)
E VG S M U N
D) IS THE CONTRACTOR’S ACCOUNTING SYSTEM ADEQUATE FOR
MANAGEMENT AND TRACKING OF COSTS? IF NO, PLEASE
EXPLAIN IN REMARKS SECTION.
YES NO
E) IF THIS IS/WAS A GOVERNMENT CONTRACT, HAS/WAS THIS
CONTRACT BEEN PARTIALLY OR COMPLETELY TERMINATED FOR
DEFAULT OR CONVENIENCE OR ARE THERE ANY PENDING
TERMINATIONS? INDICATE IF SHOW CAUSE OR CURE NOTICES
WERE ISSUED, OR ANY DEFAULT ACTION IN COMMENT SECTION
BELOW.
YES NO
F) HAVE THERE BEEN ANY INDICATIONS THAT THE CONTRACTOR
HAS HAD ANY FINANCIAL PROBLEMS? IF YES, PLEASE EXPLAIN
BELOW.
YES NO
6. SAFETY/SECURITY
A) TO WHAT EXTENT WAS THE CONTRACTOR ABLE TO MAINTAIN
AN ENVIRONMENT OF SAFETY, ADHERE TO ITS APPROVED
SAFETY PLAN, AND RESPOND TO SAFETY ISSUES? (INCLUDES:
FOLLOWING THE USERS RULES, REGULATIONS, AND
REQUIREMENTS REGARDING HOUSEKEEPING, SAFETY,
CORRECTION OF NOTED DEFICIENCIES, ETC.)
E VG S M U N
B) CONTRACTOR COMPLIED WITH ALL SECURITY REQUIREMENTS
FOR THE PROJECT AND PERSONNEL SECURITY REQUIREMENTS.
E VG S M U N
7. GENERAL
A) ABILITY TO SUCCESSFULLY RESPOND TO EMERGENCY AND/OR
SURGE SITUATIONS (INCLUDING NOTIFYING COR, PM OR
CONTRACTING OFFICER IN A TIMELY MANNER REGARDING
URGENT CONTRACTUAL ISSUES).
E VG S M U N
B) COMPLIANCE WITH CONTRACTUAL TERMS/PROVISIONS
(EXPLAIN IF SPECIFIC ISSUES)
E VG S M U N
C) WOULD YOU HIRE OR WORK WITH THIS FIRM AGAIN? (IF NO,
PLEASE EXPLAIN BELOW)
YES NO
SECTION 00 22 00 - 18
D) IN SUMMARY, PROVIDE AN OVERALL RATING FOR THE WORK
PERFORMED BY THIS CONTRACTOR.
E VG S M U N
PLEASE PROVIDE RESPONSES TO THE QUESTIONS ABOVE (IF APPLICABLE) AND/OR
ADDITIONAL REMARKS. FURTHERMORE, PLEASE PROVIDE A BRIEF NARRATIVE
ADDRESSING SPECIFIC STRENGTHS, WEAKNESSES, DEFICIENCIES, OR OTHER
COMMENTS WHICH MAY ASSIST OUR OFFICE IN EVALUATING PERFORMANCE
RISK (PLEASE ATTACH ADDITIONAL PAGES IF NECESSARY):
SECTION 00 22 00 - 19
ATTACHMENT # 3:
PERFORMANCE ASSESSMENT REPORT (PAR)
(TAB 5)
PERFORMANCE ASSESSMENT REPORT
(TO BE COMPLETED BY OFFEROR)
1. CONTRACTOR (FIRM BEING
EVALUATED): NAME: ADDRESS:
2. CONTRACT NUMBER: TASK ORDER (TO)
NUMBER IF APPLICABLE:
3. SOLICITATION TYPE: NEGOTIATED OR SEALED
BID
4. CONTRACT/TO TYPE: FIXED-
PRICE COST, REIMBURSEMENT,
HYBRID (EXPLAIN)
5. ROUTINE DIFFICULT (LOW TO HIGH)
COMPLEXITY OF WORK 1 2 3 4 5
6. CONTRACT/TO DOLLAR VALUE:
7. CONTRACT/TO STATUS: ACTIVE
COMPLETE COMPLETION DATE (W/
EXTENSIONS):
8. DESCRIPTION, LOCATION & RELEVANCY OF WORK:
9. PROBLEMS ENCOUNTERED AND HOW RESOLVED:
10. NAME, ADDRESS, TELEPHONE NUMBER AND E-MAIL OF THE PROCURING
CONTRACTING OFFICER AND/OR THE CONTRACTING OFFICER’S REPRESENTATIVE (COR)
(AND OTHER REFERENCES, E.G., ADMINISTRATIVE CONTRACTING OFFICER, IF
APPLICABLE):
11. CHECK ONE OF THE FOLLOWING BLOCKS:
A WRITTEN PERFORMANCE EVALUATION WAS RECEIVED FOR THIS PROJECT AND IS
ATTACHED.
A WRITTEN PERFORMANCE EVALUATION WAS NOT RECEIVED FOR THIS PROJECT. A
PAST PERFORMANCE QUESTIONNAIRE (PPQ) HAS BEEN SENT TO THE REFERENCE(S)
LISTED IN BLOCK 10, WITH A LETTER REQUESTING THAT THE COMPLETED
QUESTIONNAIRE BE RETURNED DIRECTLY TO THE U.S. ARMY CORPS OF ENGINEERS BY
SECTION 00 22 00 - 20
SECTION 00 22 00 ATTACHMENT 4
PHASE 1 – VOLUME 1 - TAB 4
RESUME FORM
RESUME FORM - KEY PERSONNEL AND QUALIFICATIONS
(COMPLETE ONE FORM FOR EACH KEY PERSON)
1. NAME AND TITLE:
2. ROLE IN THIS
CONTRACT:
3. NAME OF FIRM WITH WHICH ASSOCIATED
(CITY AND STATE):
4. YEARS EXPERIENCE AS
ROLE IN BLOCK 2:
TOTAL:________________
WITH CURRENT
FIRM:_____________
5. CURRENT PROFESSIONAL REGISTRATION (STATE AND DISCIPLINE), IF
APPLICABLE:
6. EDUCATION (DEGREE AND SPECIALIZATION), IF APPLICABLE:
7. OTHER PROFESSIONAL QUALIFICATIONS (PUBLICATIONS,
ORGANIZATIONS, TRAINING, AWARDS, ETC.):
8. SUMMARY OF RELEVANT EXPERIENCE:
A.
(1) TITLE AND LOCATION (CITY
AND STATE):
(2) DATES
STARTED/COMPLETED:
(3) PROJECT DESCRIPTION (BRIEF SCOPE, SIZE, COST, ETC.) AND
SPECIFIC ROLE:
B.
SECTION 00 22 00 - 21
C.
D.
SECTION 00 22 16 - 1
SECTION 00 22 16 - SUPPLEMENTARY INSTRUCTIONS TO PROPOSERS
I. ELIGIBILITY FOR CONTRACT AWARD
II. SOURCE SELECTION USING BEST VALUE TRADE OFF PROCESS
III. PROPOSAL SUBMITTAL
IV. INITIAL EVALUATION OF TECHNICAL PROPOSAL (VOLUME II)
V. EVALUATION OF PRICE PROPOSAL (VOLUME I)
VI. INTENT TO AWARD WITHOUT DISCUSSIONS
VII. DISCUSSION PROCESS
VIII. FINAL PROPOSAL REVISIONS
IX. DEBRIEFINGS
SECTION 00 22 16 - 2
I. ELIGIBILITY FOR CONTRACT AWARD
IN ACCORDANCE WITH THE FAR, NO CONTRACT SHALL BE ENTERED INTO
UNLESS THE CONTRACTING OFFICER ENSURES THAT ALL REQUIREMENTS OF
LAW, EXECUTIVE ORDERS, REGULATIONS, AND ALL OTHER APPLICABLE
PROCEDURES, INCLUDING CLEARANCES AND APPROVALS, HAVE BEEN MET.
THIS INCLUDES THE FAR REQUIREMENT THAT NO AWARD SHALL BE MADE
UNLESS THE CONTRACTING OFFICER MAKES AN AFFIRMATIVE DETERMINATION
OF RESPONSIBILITY. TO BE DETERMINED RESPONSIBLE, A PROSPECTIVE
CONTRACTOR MUST MEET THE GENERAL STANDARDS IN PART FAR 9 AND ANY
SPECIAL STANDARDS SET FORTH IN THE SOLICITATION.
II. SOURCE SELECTION USING BEST VALUE TRADE OFF PROCESS
THE GOVERNMENT WILL SELECT THE OFFER THAT REPRESENTS THE BEST
VALUE TO THE GOVERNMENT BY USING THE TRADE-OFF PROCESS DESCRIBED
IN FAR PART 15. THIS PROCESS PERMITS TRADE-OFFS BETWEEN PRICE AND
TECHNICAL FACTORS AND ALLOWS THE GOVERNMENT TO ACCEPT OTHER THAN
THE LOWEST PRICED OFFER.
THE AWARD DECISION WILL BE BASED ON A COMPARATIVE ASSESSMENT OF
PROPOSALS AGAINST ALL SOURCE SELECTION CRITERIA IN THE SOLICITATION.
PROPOSALS SHALL NOT USE BROAD STATEMENTS SUCH AS: “OFFEROR
UNDERSTANDS”, OR “WILL COMPLY WITH THE SPECIFICATIONS”, OR
STATEMENTS PARAPHRASING THE SPECIFICATIONS, AND GENERAL OR OVERLY
BROAD STATEMENTS SUCH AS “STANDARD PROCEDURES WILL BE EMPLOYED”
OR “WELL KNOWN TECHNIQUES WILL BE USED”. PROPOSALS WITH THESE TYPES
OF STATEMENTS WILL BE RATED NON-ACCEPTABLE. LIST OF EVALUATION
FACTORS (VOLUME II) AND SPECIFIC TECHNICAL EVALUATION CRITERIA
ALL TECHNICAL EVALUATION FACTORS, WHEN COMBINED, ARE SIGNIFICANTLY
MORE IMPORTANT THAN COST OR PRICE.
ENVIRONMENTAL COMPLIANCE WILL BE THE MOST IMPORTANT FACTOR
FOLLOWED BY TECHNICAL APPROACH. THE FACTORS ARE LISTED IN ORDER OF
IMPORTANCE WITH FACTOR 1 BEING THE MOST IMPORTANT AND FACTOR 6
BEING THE LEAST IMPORTANT.
THE GOVERNMENT IS CONCERNED WITH OBTAINING THE MOST
ADVANTAGEOUS BALANCE BETWEEN TECHNICAL MERIT/QUALITY AND
COST/PRICE TO THE GOVERNMENT. THE DEGREE OF IMPORTANCE OF PRICE
SECTION 00 22 16 - 3
COULD BECOME GREATER DEPENDING UPON THE EQUALITY OF THE TECHNICAL
PROPOSALS. IF COMPETING TECHNICAL PROPOSALS ARE DETERMINED TO BE
ESSENTIALLY EQUAL, PRICE COULD BECOME THE CONTROLLING FACTOR. THE
GOVERNMENT MAY AWARD A CONTRACT ON THE BASIS OF INITIAL OFFERS
RECEIVED WITHOUT DISCUSSIONS; THEREFORE, THE OFFEROR’S PROPOSAL
SHOULD CONTAIN THE BEST TERMS FROM A TECHNICAL AND PRICE
STANDPOINT.
THE EVALUATION PROCESS ESSENTIALLY CONSISTS OF THREE PARTS:
PROPOSAL COMPLIANCE REVIEW AND RESPONSIBILITY DETERMINATION,
TECHNICAL/QUALITY EVALUATION, AND PRICE EVALUATION.
A. PROPOSAL COMPLIANCE REVIEW: THIS IS AN INITIAL REVIEW TO ENSURE
THAT ALL REQUIRED FORMS AND CERTIFICATIONS ARE COMPLETED AND THAT
BOTH A TECHNICAL AND PRICE PROPOSAL WERE RECEIVED.
B. TECHNICAL/QUALITY EVALUATION: THE SSEB WILL EVALUATE AND
RATE THOSE PROPOSALS PASSING THE FIRST REVIEW, ABOVE. PROPOSALS WILL
BE EVALUATED AGAINST THE RFP REQUIREMENTS. FACTORS WILL BE RATED
ON AN “UNACCEPTABLE, MARGINAL, ACCEPTABLE, GOOD AND OUTSTANDING
BASIS”.
C. PRICE EVALUATION: THE SSEB WILL EVALUATE PRICE PROPOSALS
INDEPENDENT OF THE TECHNICAL/QUALITY EVALUATION. THE SSEB WILL NOT
HAVE ACCESS TO PRICE INFORMATION UNTIL COMPLETION OF THE
TECHNICAL/QUALITY EVALUATION. THE PROPOSED PRICE WILL BE ANALYZED
FOR REASONABLENESS. IT MAY ALSO BE ANALYZED TO DETERMINE WHETHER
IT IS REALISTIC FOR THE WORK TO BE PERFORMED; REFLECTS A CLEAR
UNDERSTANDING OF THE REQUIREMENTS; AND IS CONSISTENT WITH THE
OFFEROR’S TECHNICAL PROPOSALS. ALL OFFERS WITH SEPARATELY PRICE LINE
ITEMS AND/OR SUB LINE ITEMS WILL BE ANALYZED FOR UNBALANCED PRICING.
FACTOR 1: ENVIRONMENTAL COMPLIANCE
THIS FACTOR WILL BE THE MOST IMPORTANT FACTOR. THIS PROJECT WILL BE
CONSTRUCTED ON THE TOHONO O’ODHAM NATION, REFERRED TO AS THE
NATION IN THE REST OF THIS SECTION, AND IN AREAS THAT HAVE CULTURALLY
AND ENVIRONMENTALLY IMPORTANT TO THE NATION. THE ENVIRONMENTAL
COMPLIANCE PLAN WILL NEED TO COVER THE FOLLOWING ELEMENTS;
(1) COMPLIANCE WITH THE BEST PRACTICES IN THE ENVIRONMENTAL
ASSESSMENT.
(2) TRAINING THE PERSONNEL TO WORK WITH THE MONITORS
SECTION 00 22 16 - 4
(3) ENFORCEMENT OF TRAINING RECEIVED (CONSEQUENCE OF NON-
COMPLIANCE)
(4) MANAGEMENT PROCESS TO SUPPORT EMPLOYEES IN COMPLYING
WITH THE ENVIRONMENTAL PROCESS
(5) TAKING TRAINING WITH NATION, HOW TO ACCOMPLISH IT
(6) COMPILING WITH THE RESTORATION PLAN BEST PRACTICE’S
(7) AVOIDANCE OF IMPACTS
(8) HOW TO THE RELOCATION OF (3) SAGUARO
(9) RISK AVOIDANCE STRATEGY TO AVOID
SUPERIOR RATINGS WILL BE GIVEN TO OFFERORS THAT GIVE EXAMPLES OF
HOW THEY WOULD COMPLY WITH ALL ENVIRONMENTAL REQUIREMENTS AND
HOW THEIR COMPLIANCE STRATEGY WILL REDUCE RISK TO THE CONTRACTOR
AND THE GOVERNMENT. SUPERIOR RATINGS WILL ALSO BE GIVEN TO OFFERORS
ON HOW COMPREHENSIVE AND DETAILED THEIR RESPONSE TO THE FACTOR IS,
WHILE STILL ADHERING TO THE PAGE LIMIT FOR THE TECHNICAL PROPOSAL.
FACTOR 2: TECHNICAL APPROACH
PROVIDE A CONCISE MANAGEMENT PLAN FOR THE PROJECT THAT DESCRIBES
HOW YOUR LABOR, RESOURCES, SUBCONTRACTORS AND MATERIAL SUPPLIERS
WILL BE COORDINATED AND USED TO ENSURE SUCCESSFUL COMPLETION OF
THE PROJECT. PLEASE ENSURE THAT YOUR RESPONSE TO THIS FACTOR BY
ADDRESSES THE FOLLOWING ELEMENTS;
(1) HOW WILL THE PROJECT BE STAFFED, PLEASE EXPLAIN HOW YOU WILL
BILLET THE CONSTRUCTION CREWS, AND TRANSPORT THEM TO THE
PROJECT AND BACK.
(2) WILL NEED TO EXPLAIN HOW THE PROJECT WILL BE IMPLEMENTED. THE
ELEMENTS THAT WOULD NEED TO BE COVERED WOULD BE PHASING
WITH THE AJO CAG 0434, 0436, 0438, 0440 AND 0442 SITES BEING STARTED
FIRST.
(3) HOW WILL OFFEROR COMPLY WITH THE STAGING REQUIREMENTS OF THE
ENVIRONMENTAL ASSESSMENT THAT ONLY TWO STAGING AREAS ARE
IDENTIFIED
(4) HOW WILL THE LOGISTICS OF THE CONSTRUCTION BE HANDLED.
INCLUDED IN THIS RESPONSE WOULD BE A PLAN ON HOW THE
CONTRACTOR WILL INTEND TO STAY WITHIN THE AUTHORIZED RIGHT OF
WAYS.
(5) PROVIDE A DETAILED EXPLANATION ON HOW QUALITY CONTROL PLAN
WILL BE IMPLEMENTED.
(6) PROVIDE A DESCRIPTION OF HOW CONSTRUCTION CREWS, EQUIPMENT
WILL BE TRANSPORTED OUT TO THE SITE. THIS PLAN WILL ALSO HAVE TO
INCLUDE DESCRIPTION ON HOW THE HAUL ROUTES WILL NOT BE
SECTION 00 22 16 - 5
DAMAGED AND AREAS WITHIN BUILT UP AREAS WILL BE KEPT CLEAN.
(7) DESCRIBE HOW EACH CLIN WILL BE MANAGED IN THE BASE CONTRACT
SUPERIOR RATINGS WILL BE GIVEN TO OFFERORS THAT TIE THEIR
TECHNICAL APPROACH WITH HOW THEY COMPLY WITH ENVIRONMENTAL
REQUIREMENTS FOR THE PROJECT. SUPERIOR RATING WILL ALSO BE GIVEN
RESPONSES THAT INDICATE A METHOD TO REDUCE IMPACTS ON TRAFFIC
AND INHABITANT AREAS AND HOW THEY WILL RESPECT THE LOCAL
INHABITANTS CONCERNS ABOUT THE ENVIRONMENT AND CULTURE.
FACTOR 3 PAST EXPERIENCE
THE OFFEROR WILL SUBMIT 3 PROJECTS THAT WORTH AT LEAST $5 MILLION
DOLLARS. THE PROJECTS WILL HAVE TO BEEN CONSTRUCTED IN RURAL AREAS
WHERE THERE WAS SIGNIFICANT LOGISTICAL CHALLENGES. THE PROJECTS
WILL HAVE INVOLVED ROAD WORK AND SITE DEVELOPMENT IN RURAL AREAS.
THE CONTRACTS ALSO NEED TO SUBMIT ONE PROJECT WORTH AT LEAST $2
MILLION THAT WAS COMPLETED ON A NATIVE AMERICAN RESERVATION OR
NATIVE ALASKAN OR HAWAIIN VILLAGE
SUPERIOR RATINGS WILL BE GIVEN TO PROJECTS SUBMITTED THAT MORE
CLOSELY RESEMBLE THE SCOPE AND COST OF THE CURRENT SOLICITATION.
SUPERIOR RATINGS WILL ALSO BE GIVEN TO OFFERORS THAT HAVE MORE THAN
ONE PROJECT THAT HAS BEEN CONSTRUCTED ON A NATIVE AMERICAN
RESERVATION OR NATIVE ALASKAN OR HAWAIIAN COMMUNITY.
FACTOR 4: KEY PERSONNEL RESUMES
KEY PERSONNEL: PROVIDE RESUMES FOR THE FOLLOWING:
KEY PERSONNEL: PROVIDE RESUMES FOR THE FOLLOWING:
(1) HEALTH LIFE SAFETY OFFICER
(2) QUALITY CONTROL MANAGER
(3) SUPERINTENDENT
SECTION 00 22 16 - 6
(4) PROJECT MANAGER
(5) ENVIRONMENTAL COMPLIANCE COORDINATOR
RESUMES SUBMITTED FOR THIS TECHNICAL PROPOSAL…