Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
The above numbered solicitation to drydock the Dredge Wheeler is hereby amended to incorporate Section J, which was missing from the initial package. Bid Opening date remains unchanged.
USACE, CONTRACTING DIVISION
ATTN: CEMVN-CT, ROOM 172
7400 LEAKE AVE.
NEW ORLEANS LA 70118-3651
W912P8-17-B-0032
07/21/2017
07/19/2017
1 78
SECTION J
LIST OF ATTACHMENTS
Attachment No. Description Line Item No.
J-1 Checklist for Undocking DD-1 J-2 Sketch of Hopper Door’s Pins & Bushings DD-7 J-3 Section Through Hinge Pin DD-7 J-4 Lower Push-Pull Rods DD-7 J-5 Hopper Doors Cross Section DD-7 J-6 Hopper Doors – Flat Bars DD-7 J-7 Cross Section – Athwartships & Longitudinal HH-2 J-8 Layout of Tanks, Voids, and Cofferdams HH-14 J-9 Waterblast Surface Preparation Standard HH-18 J-10 Wheeler Existing Coating System HH-19 J-11 ¾” Hinge Plate Replacement DD-7 J-12 Weld Seam Repair On Collection Pipes MD-3 J-13 Longitudinal Reinforced Plate HH-2 J-14 Welded Clip For Adjustable Weir MD-6 J-15 Welded Bead Bkt. For Adjustable Weir MD-6 J-16 Bettis Actuator Service Instruction MA-1 J-17 Hopper Door Round Bar DD-7 J-18 Dock Trials Checklist TR-2 J-19 Schedule of Government-Furnished Property H-7 J-20 Nautical Miles Chart DD-1 J-21 List Of Motors That Need Heat Lamps F-6 J-22 Bailey Crane, Engine & Hydraulic Tank MA-11 J-23 Accident Prevention Program Administrative Plan H-3 LMN Form 385-43R J-24 Accident Prevention Program Hazard Analysis H-3 LMN Form 385-6-R J-25 Accident Prevention Plan Checklist Administrative H-3 Section, LMN Form 385-7-R J-26 Fuel Oil Transfer – Floating Plant, Form 414-R H-3 J-27 Hazardous Energy Control Program, US Dredge Wheeler H-3 J-28 Safe Clearance Log H-3 J-29 Safe Clearance Request Form H-3 J-30 Emergency Generator Drawings MA-10 J-31 Muffler for Emergency Generator MA-10 J-32 Sperry EE-3 J-33 #7 Center Tank Conversion to Slops MA-16
Attachment J-1
Attachment J-2
A ttachm ent J-3 ent J-4 ent J-5 ttach m en t J-8
Attachment J-9 m en t J-1 m en m en
J-14 Welded Clip For Bottom Adj Weir
J-15 Welded Bead Bkt For Adjustable Weir
J-16 (BETTIS ACTUATOR Service Instruction)
J-17 Hopper Door Round Bar
Attachment J-18
Attachment J-19
LIST OF GOVERNMENT FURNISHED PARTS
Item Part # Description Qty
DD-3 Seachest Strainer Assembly 2 ea.
DD-3 Rubber Expansion Joint 2 ea.
DD-3 18 inch Gate Valve 2 ea.
DD-7 4013-904-403/404 Push-Pull rod 6 sets DD-7 4013-907-204 Hopper door hinge pin 56 ea.
DD-7.7 4013-907-207 Bearing pot bushing 10 ea.
DD-7.8 4013-907-207 Bearing pot bushing 40 ea.
DD-7.9 4013-907-213 Hopper door pad eye bushing 14 ea.
DD-7.9 4013-904-402 Shaft 14 ea.
DD-7.10 4013-907-406 Bushing (Push/Pull rod with eye) 14 ea.
DD-7.10 4013-904-407 Shaft 14 ea.
DD-7.11 4013-907-405 Bushing (Push/Pull rod with fork) 28 ea.
DD-7.13 920504-3, 101/211 Replacement gasket assembly 14 sets
(14 ea. for center seal, 56 ea. for peripheral) DD-7.13, 2995 BF Goodrich, Elastolock 2995 sealant as needed DD-7.18 4013-901-401 Main Stem 7 ea.
MP-1.4 21965 Tailshaft 1 ea.
MP-1.4 PR6630 One Piece Seal 1 ea.
MP-1.5 22323RH Right Hand Propeller Blades (set of 4) 1 set MP-1.5 D22189-RH Right Hand Propeller Hub 1 ea.
MP-1.6 22323LH Left Hand Propeller Blades (set of 4) 1 set MP-2.2 PR17262-1 Split Seal 1 ea.
MD-1.2.1 4886-901-105 Nose ring - 18” sluice valve 10 ea.
MD-1.2.1 4886-901-108 Backing ring – 18” sluice valve 10 ea.
MD-1.2.1 4886-901-109 Rubber ring – 18” sluice valve 20 ea.
MD-1.2.2 4889-901-105 Nose ring - 24” sluice valve 4 ea.
MD-1.2.2 4889-901-108 Backing ring – 24” sluice valve 4 ea.
MD-1.2.2 4889-901-109 Rubber ring – 24” sluice valve 8 ea.
MD-1.2.3 4890-901-105 Nose ring - 26” sluice valve 4 ea.
MD-1.2.3 4890-901-108 Backing ring – 26” sluice valve 4 ea.
MD-1.2.3 4890-901-109 Rubber ring – 26” sluice valve 12 ea.
MD-1.2.4 4892-901-105 Nose ring - 30” sluice valve 6 ea.
MD-1.2.4 4892-901-108 Backing ring – 30” sluice valve 6 ea.
MD-1.2.4 4892-901-109 Rubber ring – 30” sluice valve 18 ea.
MD-1.2.5 4893-901-105 Nose ring - 32” sluice valve 4 ea.
MD-1.2.5 4893-901-108 Backing ring – 32” sluice valve 4 ea.
MD-1.2.5 4893-901-109 Rubber ring – 32” sluice valve 8 ea.
MD-1.2.6 4898-901-105 Nose ring - 43” sluice valve 2 ea.
MD-1.2.6 4898-901-108 Backing ring – 43” sluice valve 2 ea.
MD-1.2.6 4898-901-109 Rubber ring – 43” sluice valve 6 ea.
Attachment J-19
MD-1.5 4898-901-101 43 inch Valve Body 1 ea.
MD-1.5 4898-901-131 Hydraulic Cylinder 1 ea.
MD-2.1 Jet Pump with Motor 2 ea.
MD-6 4046-002-003 Adjustible Weir Seal 4 ea.
MD-6 4418-002-020 Hydrulic Cylinder 2 ea.
MA-1 Valve 12 inches butterfly valve 4 ea.
MA-1 Valve 10 inches butterfly valve 8 ea.
MA-4 Valve & Actuator 16 inches Butterfly Valve with Bettis Actuator 2 ea.
MA-10 Caterpillar C7.1 Emergency Generator Assembly 1 ea.
MA-10 MSA11-4C1 Muffler for Generator 1 ea.
MA-17 Directional Control Valve Assembly 3 ea.
MA-19 DXT-1009-S-2P-2C Heat Exchanger Assembly 1 ea.
J-20 NAUTICAL MILAGE CHART
J-22 Bailey Crane, Engine & Hydraulic Tank
Attachment J-23
Attachment J-23
Attachment J-24
Attachment J-25
Attachment J-26
Attachment J-27
Attachment J-27
Attachment J-28
Attachment J-29
Attachment J-30
Attachment J-31
CHAMBERED SPARK ARRESTING SILENCERS MSA11
MAXIM SILENCERS, INC.
Size A B C N O P Est Wt.
1 ½” 9 20 1 ½ 3 ½ 7 ½ 17 20
2” 9 20 2 4 7 ½ 17 21
2 ½” 10 24 2 ½ 4 ½ 8 21 28
3 12 26 3 5 9 23 41
3 ½” 14 30 3 ½ 5 ½ 10 27 55
4” 14 36 4 6 11 32 64
5” 16 43 5 7 12 39 88
6” 18 49 6 7 ½ 13 45 110
8” 22 59 8 9 ½ 15 55 178
10” 26 64 10 11 ½ 17 60 280
12” 30 77 12 13 19 73 416
14” 36 83 14 15 ½ 23 78 558
16” 40 90 16 16 ½ 25 85 793
18” 45 96 18 18 27 ½ 91 950
20” 50 109 20 20 ½ 30 104 1392
22” 54 119 22 22 ½ 32 114 1806
24” 60 125 24 24 35 123 2187
26” 64 140 26 25 ½ 37 135 2586
28” 68 155 28 26 ½ 39 150 2984
30” 72 166 30 28 41 161 3445
Note: Dimensions are in inches, weights are in pounds
Rev. 09.14.09
Residential Chamber Type Spark Arresting: Expected Attenuation is 20 to 25 dBA Usa a model MSA11 in residential and light industrial areas for spark arresting capability where background noise is relatively high and constant and the need for higher degrees of silencing is minimal.
Example: In residential neightborhoods having high traffic or light industry with relatively constant background noise. Residents in these areas are typically accustomed to the noise or make some efforts to shield themselves from the ever present background noise. Use of an MSA11 can keep engine exhaust noise within existing noise levels.
O V
E R
V
IE
W
• Internal combustion engine exhausts
• Marine service
• Refinaries / Hazardous environments
• Offshore drilling / Production platforms
TY
P
IC
A
L A
P P
LI
C
A
TI
O N
S
• Advanced acoustical design
• Heavy duty, all welded construction and long service life
• Easily installed in any position
• High heat silicone black finish
• Sizes 11⁄2” to 31⁄2” have MNPT connections
• Two chambers
• Efficient spark arresting
• Drain connectionsFE
A
TU
R E
S
• Explosion relief cover
• Flexible connectors
• Companion flanges
• Cleanout openings
• Side inlet
• Horizontal or vertical support arrangements
• Special paint
• Stainless steel construction: 304, 316 & 321
• Complete range of exhaust accessories
• Spark arresting efficiency certification
O P
TI
O
N A
L A
C C
E
SS
O R
IE
SS
A tta ch m en t J
-3
Date: July 26, 2017
To: U.S. Army Corps of Engineers
Attn: Mr. Bob Brockway
Email: william.r.brockway@usace.army.mil
Cust. Ref: Autopilot Hardware/Install
NGSM Ref: Q2017-3-73 UID: 163888
Subject: Dredge Wheeler
Dear Mr. Brockway, Northrop Grumman Systems Corporation, Sperry Marine is pleased to offer this proposal for the above referenced vessel.
This is a budgetary price proposal for installation and a firm fixed price for hardware.
This quotation is valid for 60 days, unless otherwise withdrawn in writing.
Location of Services: Local - Within 25 miles of Sperry Marine Office. If outside of this area, the customer will be responsible for freight and additional travel costs associated with the installation.
Payment terms: NET 30
Acceptance of this proposal is limited to the Northrop Grumman Systems Corporation, Sperry
Marine standard commercial terms and conditions. Sperry Marine reserves the right to reject any other terms imposed by the purchaser which are not in accordance with FAR Part 12 and FAR
Parts 52.212-4 and 52.212-5. Sperry Marine takes exception to the 52.222-41 Service Contract
Act. In addition, Sperry Marine reserves the right to increase the cost of the original quotation in consideration of the acceptance of different or additional terms and conditions imposed by the purchaser. Delays associated with Terms and Conditions discussion may adversely affect delivery schedule.
Northrop Grumman Systems Corporation
Sperry Marine
1865 Industrial Blvd
Harvey, LA 70058-2313 USA
Office Phone: 504 328 9171 Office Fax: 504 328 9855
Northrop Grumman Systems Corporation, Sperry Marine
Dredge Wheeler Autopilot Hardware & Install
The information contained herein is submitted upon the understanding that it is privileged or confidential within the meaning of the Freedom of Information Act, 5 USC, Sec. 552(b)(4).
Please note the following:
Purchase orders must be addressed to:
Northrop Grumman Systems Corporation
Sperry Marine
1865 Industrial Blvd
Harvey, LA 70058-2313
Cage Code 6MKG6
Duns Number 022200740
Scope of Supply:
A Steering Control System
A.01 1 NAVIPILOT/4KP/1/BASIC Navipilot 4000+ Control and Display Unit/SCU/Basic dongle
A.02 3 074851-0000-000 Steering Control Unit
A.03 2 074780-0000-000 NAVINET 4000 CAN Bus Connection Board
A.04 4 020041-0000-000 AC Bang-Bang Solenoid Valve Control Board with Relays
A.05 1 074835-0000-000 Steering Mode Selector Switch with 5 Positions
A.06 1 074835-0000-000 System Switch with 5 Positions
A.07 2 074477-0000-000 Control Lamp Module, 4 Indicator Lamps/Dimmer
A.08 2 074473-0000-000 Control lamp Module, 8 Indicator Lamps/Dimmer
A.09 2 022659-0000-000 Cap "No. 1 Power Available"
A.10 2 022660-0000-000 Cap "No. 2 Power Available"
A.11 2 029007-0000-000 Cap "Pump 1 ON"
A.12 2 029009-0000-000 Cap "Pump 2 ON"
A.13 2 029759-0000-000 Cap "NFU"
A.14 2 026525-0000-000 Cap "Hand"
A.15 2 030687-0000-000 Cap "Auto"
A.16 2 026709-0000-000 Cap "Port"
A.17 2 026490-0000-000 Cap "Neutral"
A.18 2 026711-0000-000 Cap "Stbd"
A.19 4 040777-0000-000 Blind cap
A.20 1 074817-0000-000 Follow-up Handwheel, +/- 45°, 6 Potentiometers + EL SHAFT
A.21 2 074741-0000-000 Follow-up Handwheel, +/- 45°, 3 Potentiometers + EL SHAFT
A.22 2 074780-0000-000 Navinet 4000 CAN Bus Connection Board
A.23 3 074709-0000-000 FU Device Interface
A.24 2 047873-0000-000 Isolation Amplifier
A.25 3 074836-0000-000 Jog-Override Dual Non-Follow-up Switch
A.26 4 060290-0000-000 Power Connection Unit 115 VAC/ 24 VDC, 10A
A.27 2 074848-0000-000 Steering Failure Alarm Sensor
A.28 2 020757-0000-000 Indicator Lamp "Steering Failure"
A.29 1 820-0935 Center Console Plate
A.30 2 820-0934 Wing Station Panel
A.31 3 820-0936 Helm Adapter Plate - CLB TO CPLATH
A.32 1 820-1007 Top Adapter Plate for UGP
A.33 2 820-0898UM SFA Alarm Adapter Plate
A.34 4 042700-0000-000 Power supply
A.35 2 055592-0000-000 Bearing Rail
A.36 2 055593-0000-000 Bearing Rail
A.37 1 055332-0000-000 Bearing Rail
A.38 2 055471-0000-000 Bearing Rail
A.39 1 055608-0000-000 Bearing Rail
A.40 6 055335-0000-000 Bearing Rail
A.41 2 040631-0000-000 Alarm Buzzer
A.42 2 025952-0000-000 Mute Push-Button
A.43 2 022808-0000-000 Cap "Mute"
A.44 1 1882438-802 Special SSW Box
A.45 4 074788-0000-000 RRB - 3 Pots, 2 Sets of Limit Switches +/-45
A.46 2 074722-0000-000 RRB - 2 Pots, 1 Set of Limit Switches +/-45
A.47 6 020508-0000-000 Lever Linkage
A.48 2 060327-0000-000 RAI, +/- 45, 144mm, Bracket Mount
A.49 6 060338-0000-000 RAI , +/- 45, 144mm, Console Mount
A.50 1 060368-0000-000 ROT, +/-30, 144mm, Console Mount
A.51 2 074849-0000-000 Rudder Angle Calibrator
A.52 3 820-1003 ROI, +/- 45, 144mm Fab new dial plate.
A.53 7 074919-0000-000 24VDC Dimmer
A.54 1 074883-0000-000 Bulkhead Repeater w/Dimmer
A.55 1 074859-0000-000 Terminal Box for Repeater
A.56 7 820-1010 Dimmer Label
A.57 3 MS24525-27 Sync Switches
A.58 3 820-1009 Sync Switch Labels
A.59 1 !SLS900 Can Bus Cable
B Additional
B.01 2 056800 Manuals on CD-ROM
B.02 1 !SLS900 Application effort, drawings etc.
B.03 50 !SLS900 Assembly Hours
B.04 1 !SLS900 Misc.labels, lugs, hardware
B.05 1 !SLS900 ABS Review and Approval
Notes:
1. Dual rudder, 2 pump per rudder, max. rudder angle ±45°, Bang-Bang controlled by 115V AC solenoids and dump valves, 115V AC control power from pump starters.
2. Heading signal to be provided by existing NAVIGAT X MK1.
3. Steering Alarm Panel existing system
4. Existing -802 Steering Selector Box to be replaced onboard as this is a special unit.
Scope of Work:
C Provisioning of Service
C.01 Lockout/Tagout of existing power sources.
C.02 Remove existing autopilot system.
C.03 Labeling of cables.
C.04 Install Power Connection Unit
C.05 Install Navipilot 4000 System components.
C.06 Connect and configure new steering repeater.
C.07 Interface autopilot system to existing ship’s navigation equipment.
Shipyard assistance will be required for the mounting of units (welding) and lift support to transport equipment from dock to vessel.
Northrop Grumman Systems Corporation, Sperry Marine installation takes exception to any and all of the following:
• Provision of 220V power to Power Connection Unit 24V.
• Mounting of supplied adaptor plates.
• Iron, welding, fitting, painting, and carpenter work.
• Delivery of and pulling of any cable and mounting of any peripheral equipment.
• Rental of cranes, workboats, helicopters, divers.
• Delivery and mounting of equipment other than specified in this quote.
• Opening and closing of ceilings, bulkheads, floors, windows, etc.
All labor, material and travel identified in this quotation are solely suggested by Northrop
Grumman Systems Corporation, Sperry Marine based on the scope of supply and scope of work provided.
Northrop Grumman Systems Corporation, Sperry Marine takes exception to all work, except as specifically identified.
If during the course of the work, it is discovered that additional work is needed and/or if there are any delays caused by anyone other than Sperry Marine representative, and the labor time is affected, we will inform the U.S. Corp of Engineers. for a purchase order modification as necessary.
Pricing Summary:
C Scope of Work
C.01
Onboard Labor Daily Rate
Charges
Weekday Rate @ $1,900.00/day/person 8 days /
2 persons
$30,400.00
Weekend Rate @ $2,100.00/day/person 2 days /
2 persons
$8,400.00
Subtotal $38,800.00
C.02 Miscellaneous Hardware $5,000.00
Total Budgetary Price $43,800.00
Shipyard Support
Approximately 40 hrs for mounting
(welding).
Shipyard determined
Sperry Marine looks forward to supporting your needs. Any questions regarding the technical aspect of this quote may be directed to Mr. Joseph Monfrey at any time.
Joseph A. Monfrey Steven A. Garner
Mission Assurance Manager US Contracts Administrator
Northrop Grumman Systems Corp (Sperry Marine) Northrop Grumman Systems Corp (Sperry Marine)
Harvey, LA Harvey, LA
Date: July 26, 2017
To: U.S. Army Corps of Engineers
Attn: Mr. Bob Brockway
Email: william.r.brockway@usace.army.mil
Cust. Ref: Navigat X MK 1 Gyro Hardware/Install
NGSM Ref: Q2017-2-65 UID: 163888-G
Subject: Dredge Wheeler
Dear Mr.Brockway, Northrop Grumman Systems Corporation, Sperry Marine is pleased to offer this proposal for the above referenced vessel.
This is a budgetary price proposal for installation.
This quotation is valid for 60 days, unless otherwise withdrawn in writing.
Location of Services: Local - Within 25 miles of nearest Northrop Grumman Sperry Marine
Office location. If outside of this area, the customer will be responsible for freight and additional travel costs associated with the installation.
Payment terms: NET 30
Acceptance of this proposal is limited to the Northrop Grumman Systems Corporation, Sperry
Marine standard commercial terms and conditions. Sperry Marine reserves the right to reject any other terms imposed by the purchaser which are not in accordance with FAR Part 12 and FAR
Parts 52.212-4 and 52.212-5. Sperry Marine takes exception to the 52.222-41 Service Contract
Act. In addition, Sperry Marine reserves the right to increase the cost of the original quotation in consideration of the acceptance of different or additional terms and conditions imposed by the purchaser. Delays associated with Terms and Conditions discussion may adversely affect delivery schedule.
Northrop Grumman Systems Corporation
Sperry Marine
1865 Industrial Blvd
Harvey, LA 70058-2313 USA
Office Phone: 504 328 9171 Office Fax: 504 328 9855
Dredge Wheeler Gyrocompass Hardware & Install
The information contained herein is submitted upon the understanding that it is privileged or confidential within the meaning of the Freedom of Information Act, 5 USC, Sec. 552(b)(4).
Please note the following:
Purchase orders must be addressed to:
Northrop Grumman Systems Corporation
Sperry Marine
1865 Industrial Blvd
Harvey, LA 70058-2313
Cage Code 6MKG6
Duns Number 022200740
Scope of Supply:
Government Furnished Material
Pos. Qty. Description
A Gyro Compass System
A.01 1 Navigat X MK 1 Gyro
A.02 1 Gyro Adapter Plate
A.03 1 Bearing Repeater Cover
A.04 1 Bulkhead Bearing Repeater
A.05 1 Repeater Terminal Box
A.06 1 Bearing Repeater
A.07 1 Column Bearing Repeater Stand w/Terminal Box
A.08 1 Azimuth Device
A.09 1 Naviprint Rudder and Course Recorder Printer
A.10 1 Naviprint Terminal Board
A.11 4 Lemkuhl Digital Repeaters
A.12 1 Installation Cable
A.13 1 Repeater Distribution Junction Box
Scope of Work:
B Provisioning of Service
B.01 Lockout/Tagout of existing power sources.
B.02 Remove existing gyrocompass (Gyro #1: Sperry MK37 Mod. 1).
B.03 Labeling of cables.
B.04 Install Navigat X MK 1 gyrocompass systems.
B.05 Perform alignment tests.
B.06 Install repeater distribution junction box .
B.07 Connect and configure bearing repeaters.
B.08 Interface gyrocompass system to existing ship’s navigation equipment.
Shipyard assistance will be required for the mounting of repeaters and pulling of data cable to new repeater.
Northrop Grumman Systems Corporation, Sperry Marine installation takes exception to any and all of the following:
• Provision of ancillary 24V DC power for gyro.
• Mounting of gyro adaptor plates.
• Removal and mounting of gyro repeater column bearing stand.
• Iron, welding, fitting, painting, and carpenter work.
• Delivery of and pulling of any cable and mounting of any peripheral equipment.
• Rental of cranes, workboats, helicopters, divers.
• Delivery and mounting of equipment other than specified in this quote.
• Opening and closing of ceilings, bulkheads, floors, windows, etc.
All labor, material and travel identified in this quotation are solely suggested by Northrop
Grumman Systems Corporation, Sperry Marine based on the scope of supply and scope of work provided.
If during the course of the work, it is discovered that additional work is needed and/or if there are any delays caused by anyone other than Sperry Marine representative, and the labor time is affected, we will inform the U.S. Army Corps of Engineers for a purchase order modification as necessary.
Pricing Summary:
B Scope of Work
B.01 Daily Rate Charge Weekday Rate @
$1,900.00/day/person
3 days /
2 persons
$11,400.00
B.02 Installation Hardware $350.00
B.03 Shipyard Support
- Approximately 8 hrs for mounting and cable run
Shipyard determined
Subtotal $11,750.00
Sperry Marine looks forward to supporting your needs. Any questions regarding the technical aspect of this quote may be directed to Mr. Joseph Monfrey at any time.
Joseph A. Monfrey Steven A. Garner
Mission Assurance Manager US Contracts Administrator
Northrop Grumman Systems Corp (Sperry Marine) Northrop Grumman Systems Corp (Sperry Marine)
Harvey, LA Harvey, LA
| J-Section.pdf |
| SECTION J |
| Binder1 |
| Attachment J-1 (Undocking) |
| Attachment J-2 (Sketch of Hopper Door Pins - Bushings) |
| Attachment J-3 (Section Through Hinge Pin) |
| Attachment J-4 (Lower Push-Pull Rods) |
| Attachment J-5 (Hopper Door Cross Section) |
| Attachment J-6 (HOPPER DOOR - FLAT BARS) |
| Attachment J-7 (Athwartship - Longitudinal Cross Section) |
| attachment J-8 (Layout of Tanks-Voids-Cofferdams) |
| attachment J-9 (Waterblast Surface Preparation Standard) |
| attachment J-10 (Existing Coating) |
| Attachment J-11 (0.75 inch Hinge Plate Replacement) |
| Attachment J-12 (Weld Seam Repair on Collection Pipes) |
| Attachment J-13 (Longitudinal Reinforced Plate) |
| Attachment J-14 (Welded Clip For Bottom Adj Weir) |
| Attachment J-15 (Welded Bead Bkt Adj Weir) |
| Attachment J-16 (BETTIS ACTUATOR Service Instruction) |
| Attachment J-17 (Hopper Door Round Bar) |
| Attachment J-18 (Dock Trial) |
| Attachment J-19 (Government Furnished Prop) |
| Attachment J-20 (Nautical Milage Chart) |
| Attachment J-21 (Electrical Motors that need Heater) |
| Attachment J-22 (Bailey Crane, Engine & Tank) |
| J### Bailey Crane, Engine & Tank |
| J###Hydraulic Tank |
| Crane Technical Manual 28 |
| Tank Dets |
| Attachment J-23 (Form 385-43R) |
| Attachment J-24 (Form 385-6-R) |
| Attachment J-25 (Form 385-7-R) |
| Attachment J-26 (Form 414R) |
| Attachment J-27 (Hazardous Control Program) |
| Attachment J-28 (Safe Clearance Log) |
| Attachment J-29 (Safe Clearance Request Form) |
| Attachment J-30 (Emer Generator Drawings) |
| E1877-2016-01 SHEET 1 |
| E1877-2016-01 SHEET 2 |
| E1877-2016-01 SHEET 3 |
| E1877-2016-01 SHEET 4 |
| E1877-2016-01 SHEET 5 |
| E1877-2016-01 SHEET 6 |
| E1877-2016-01 SHEET 7 |
| Attachment J-31 (Muffler for EGen) |
| J#### Muffler MSA11-4C1-4in |
| J#### Muffler MSA11-4C1-4in |
| SilencersMSA11-Specs |
A9R177vk65_17avxj8_9g8
Attachment J-32 (Sperry)
| J-Section.pdf |
| SECTION J |
| Binder1 |
| Attachment J-1 (Undocking) |
| Attachment J-2 (Sketch of Hopper Door Pins - Bushings) |
| Attachment J-3 (Section Through Hinge Pin) |
| Attachment J-4 (Lower Push-Pull Rods) |
| Attachment J-5 (Hopper Door Cross Section) |
| Attachment J-6 (HOPPER DOOR - FLAT BARS) |
| Attachment J-7 (Athwartship - Longitudinal Cross Section) |
| attachment J-8 (Layout of Tanks-Voids-Cofferdams) |
| attachment J-9 (Waterblast Surface Preparation Standard) |
| attachment J-10 (Existing Coating) |
| Attachment J-11 (0.75 inch Hinge Plate Replacement) |
| Attachment J-12 (Weld Seam Repair on Collection Pipes) |
| Attachment J-13 (Longitudinal Reinforced Plate) |
| Attachment J-14 (Welded Clip For Bottom Adj Weir) |
| Attachment J-15 (Welded Bead Bkt Adj Weir) |
| Attachment J-16 (BETTIS ACTUATOR Service Instruction) |
| Attachment J-17 (Hopper Door Round Bar) |
| Attachment J-18 (Dock Trial) |
| Attachment J-19 (Government Furnished Prop) |
| Attachment J-20 (Nautical Milage Chart) |
| Attachment J-21 (Electrical Motors that need Heater) |
| Attachment J-22 (Bailey Crane, Engine & Tank) |
| J### Bailey Crane, Engine & Tank |
| J###Hydraulic Tank |
| Crane Technical Manual 28 |
| Tank Dets |
| Attachment J-23 (Form 385-43R) |
| Attachment J-24 (Form 385-6-R) |
| Attachment J-25 (Form 385-7-R) |
| Attachment J-26 (Form 414R) |
| Attachment J-27 (Hazardous Control Program) |
| Attachment J-28 (Safe Clearance Log) |
| Attachment J-29 (Safe Clearance Request Form) |
| Attachment J-30 (Emer Generator Drawings) |
| E1877-2016-01 SHEET 1 |
| E1877-2016-01 SHEET 2 |
| E1877-2016-01 SHEET 3 |
| E1877-2016-01 SHEET 4 |
| E1877-2016-01 SHEET 5 |
| E1877-2016-01 SHEET 6 |
| E1877-2016-01 SHEET 7 |
| Attachment J-31 (Muffler for EGen) |
| J#### Muffler MSA11-4C1-4in |
| J#### Muffler MSA11-4C1-4in |
| SilencersMSA11-Specs |
A9R177vk65_17avxj8_9g8
Attachment J-32 (Sperry)
| Redacted Attachment J-32 (Sperry).pdf |
| Dredge Wheeler Autopilot Hardware_Install Proposal Rev D for distribution |
| Dredge Wheeler Autopilot Sea Trial Proposal for distribution |
| Dredge Wheeler Gyro Hardware_Install Proposal UID A for distribution |
| Redacted Attachment J-32 (Sperry) Am_0001.pdf |
| Dredge Wheeler Autopilot Hardware_Install Proposal Rev D for distribution |
| Dredge Wheeler Autopilot Sea Trial Proposal for distribution |
| Dredge Wheeler Gyro Hardware_Install Proposal UID A for distribution |
File details come from the government source that posted it. Updated .