Attachment 02-BAR Intake Crane Pre-Bid Telecon_20200623.pptx

PPTX presentation 40 MB Posted

Attached to
Solicitation W912P520R0001 - Barkley Dam Intake Gantry Crane Replacement
Solicitation number
W912P520R0001
Issued by

About this file

This document provides details on a forthcoming federal contract solicitation for the removal and replacement of a 165-ton gantry crane at Barkley Dam in Grand Rivers, Kentucky. The Nashville District U.S. Army Corps of Engineers intends to issue a request for proposal for a firm fixed price construction contract. The contractor will be responsible for designing, manufacturing, assembling, testing and installing a new 165-ton multi-hoist gantry crane. Additional work includes removing the existing crane and below-the-hook lifting devices. Electrical work involves installing new 480V feeders. The anticipated NAICS code is 333923 for overhead traveling crane manufacturing with a size standard of 500 employees. The solicitation will be full and open competition with a period of performance of 420 calendar days from notice to proceed. The anticipated release date for the solicitation is June 2, 2020, with site visits scheduled thereafter. The contract value is estimated to be over $10 million. Offerors must register in the System for Award Management database.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Bid Telecon July 06, 2020

Barkley Intake Gantry Crane Replacement

.59

Agenda Roll Call

Introduction

On-Site Visit

Scope of Project

Execution/Construction

Due to the COVID-19 pandemic, access to Barkley Power Plant is restricted. This project briefing was developed to ensure that each prospective bidder receives the same project description. Information in the brief is only for the purpose of facilitating a discussion with prospected bidders. Only the project plans and specification should be used in preparation of bids.

Roll call

ATTENDANCECOMPANY
Collier Electrical Service, Inc.
WEMCO Incorporated
Konecranes
CJ Mahan Construction Co.
J.F. Brennan Company, Inc.
BCI Construction USA, Inc.
Uni-Systems Engineering, Inc.

Contracting Introduction Solicitation posted June 25, 2020.

Contractors should have sent in list of employees (max 2) to visit site by July 1, 2020.

Site Visit – Tuesday July 7, 2020 @ 9:00 a.m. CST

Questions Due Date:

Thursday July 9, 2020 @ 12:00 a.m. Central Time

Bid Opening Due Date – Friday July 27, 2020 @ 1:00 p.m. Central Time

Email questions to Ray Kendrick, Contract Specialist, at Ray.Kendrick@usace.army.mil.

Contracting Officers Representative (COR) Information John Reed, Senior Project Engineer and COR

Ongoing Projects Specification Sections Contract Options Liquidated Damages Schedule Submittals

EM385-1-1

Quality Control

ON-SITE SITE VISIT

Contractors will park in the highlighted area when arriving.

Tues. July 7, 2020

Will not go into the Power House except to use the restroom with an escort, will go as a group either at the beginning of tour or after, will take 1 or 2 in at a time.

Will be required to wear hard hat and safety boots around crane.

ON-SITE SITE VISIT (Continued) May take pictures of the crane and access points to the crane but not of other items.

All questions shall be submitted to Ray Kendrick, Contract Specialist, for official responses, at Ray.Kendrick@usace.army.mil.

Project Scope Firm-Fixed Price Construction Contract, Best Value Trade Off type of acquisition

Removal and Replacement of 165-Ton Intake Gantry Crane Performance base specifications Design-Build Fabrication of 165 Ton Gantry Crane Fabrication of below the hook lifting devices

Options 1: Crane Deconstruction 2: Crane Rail Replacement 3: Debris Container 4: Spillway Maintenance Platform

Unit 1 Generator rewind was conducted in 2011.

Complex, but standard for hydropower industry New to Barkley, not innovative to industry Limited pool of contractors for routine work that occurs routinely.

Barkley Project

Lock Dam Power plant

Barkley Plant 4 Kaplan Unit Plant (32-43 MW) 12 Intake Gates slots 12 Intake Bulkhead / Trash rack slot 12 Spillways

Barkley Plant Service bay 59 ton intake gate 50 ton spillway bulkhead

Site Orientation Contractor access to intake and intake service bay Large field area available with site restoration gates

Service Bay Field Lay down

Alternate area

Transformer installation

Existing Crane 110 Ton Gantry Crane Single 75 ton intake hoist Tandem 110 ton spillway hoist 10 Ton Jib Old Standards engineered up to 137.5 Ton (125%)

75 ton main lifting beam Intake Gates Bulkheads Trash racks Emergency closure

110 ton spillway lifting beam Spillway bulkheads Designed to set under flow Emergency closure

10 ton Jib Clamshell for trash General maintenance Lifts over railroad

New Crane 165 Ton performance base specifications, Design-Build.

Scope New Gantry Crane, trolley, New from the rails up Enclosed Trolley New lifting beams and below the hook devices (BTH) Intake beam (attached) Spillway (BTH) Debris container Spillway work platform Rail Replacement Option

Major Changes Consolidate to a single main hoist unit Trolley layout Cantilever hoist

New Crane (Rating) 165 Ton New Crane

177,000 lbs. Hydraulic loading of a spillway emergency close +100,000 lbs. Spillway bulkhead 277,000 lbs. = 138.5 Tons + 24,000 lbs. Estimated new spillway lifting beam 301,000 lbs. = 150.5 Tons

10 Ton underhung auxiliary 25 Ton Clamshell 2 Ton maintenance hoist on trolley

New Crane (main hoist) 165 Ton Intake Gate Intake Bulkhead Spillway Lifting beam / Bulkhead Trash rack lifting beam / rack Spillway work platform Debris container Electric gate latches for intake gate/bulkhead Electric linear pin drives for connection to other beams

New Crane (Clamshell) Dual purpose 2 line clamshell bucket (25 ton hoisting line and constant torque closing line) General purpose hook

New Crane (Auxiliary) 10 Ton Hoist Agreement with Railroad for permanent clearance Loads over powerhouse and centerline rail Lift length to service intake floor and service bay

New Crane (Rail Option) ASME B30 and CMAA Compliant Work needed:

Remove grout Replace unusable embedded rail anchors and base plates Some have been checked and appear to be reusable Replace rails Spalling repair Re-grout

Execution / Construction New crane erected in intake service bay area Old crane moved to vicinity of spillway gate 1 and kept in service as long as possible.

Outage Definition: The Crane cannot operate the gates for the intended function including interferences or electrical service.

Outages coordinate with COR Generator max of 2 units during September, October, and November Generator max of 1 unit during outside of September, October, and November NO UNITS during June, July, and August Spillway max of 3 during June, July, August, September, and October No Crane Service: 48 hours maximum for the entire dam / powerhouse with expectation of 24 hours shifts to return crane to service

Execution / De-Construction Existing crane removal estimating permanent closure of Spillway slot 1 Any obstruction in navigation chamber greater than 4 hours = lock closure

Possible mobile crane locations

Possible work barge

Barkley Lock WILL NOT be closed when KY Lock is closed

Execution / Construction Any lifts or obstructions over the railroad must be coordinated with Paducah and Louisville Railroad (P&L) Flag man required, rented from P&L http://www.palrr.biz/contact.htm

Thank you.

image6.jpg image7.jpg image8.JPG image9.jpg image10.png image11.jpeg image12.png image13.jpg image14.jpg image15.JPG image16.png image17.png image18.jpg image19.JPG image20.jpg image21.jpg image22.jpg image23.jpg image24.jpg image25.jpg image26.png image27.png image28.png image29.png image30.png image31.png image32.png image33.png image34.jpg image35.png image36.png image37.png image38.emf image39.emf image40.png image41.png image42.jpeg image43.jpg image1.png image2.png image3.png image4.png image5.png