RFI-004.docx

DOCX document 12 KB Posted

Attached to
Replace Roofs at Buildings 36 & 2022
Solicitation number
W912JB-18-R-9004
Issued by

About this file

Request For Information and answer.

View the file

Other files

File Type Posted
W912JB-18-R-9004-0002.pdf PDF
W912JB-18-R-9004-0004.pdf PDF
Second_Site_Visit_Attendence_Sheet_Bldg_36_and_2022.docx DOCX document
2nd_Site_Visit_minutes_Bldg_36_and_2022_roof.docx DOCX document
Revised_Evaluation_Factors-001.docx DOCX document
W912JB-18-R-9004-0003.pdf PDF
Updated_Wage_Determination_(MI105).pdf PDF
W912JB-18-R-9004-001.pdf PDF
RFI-005.docx DOCX document
Amendment_to_instructions_to_offerors_section.docx DOCX document
RFI-003.docx DOCX document
RFI-002.pdf PDF
Bldg_36_and_2022_Drawings.pdf PDF
RFI-001.docx DOCX document
Building_36_and_2022_Site_Visit_Minutes.pdf PDF
36_and_2022_site_visit_sign_in_sheet.docx DOCX document
Building_36_Pics.pdf PDF
Bldg._2022_Pics.pdf PDF
W912JB-18-R-9004.pdf PDF
3._TDVG182579_Repair_Roofs_at_Bldgs._36_and_2022_100__Specs.pdf PDF
3._SOW_TDVG182579.doc DOC document
2._TDVG182579_AF_Form_66_Schedule_of_Material_Submittals.xlsx XLSX spreadsheet
Alpena_Base_Access_requirements.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI-004

W912JB-18-R-9004

Building 36 and 2022 Roof

Q: On review of the specification section 2.2 Underlayment Materials it only shows ice & water shield specs. Is the entire roof to be covered with this? or can we switch to a synthetic underlayment after the first 3' of edge and valley coverage?

A: The SOW Items 2b and 2c addresses this question