Technical Exhibit 2– Grounds Maintenance Services At ERDC
TECHNICAL EXHIBIT 2 (REVISED)
GRASS CUTTING REQUIREMENTS.
TE - 2
REVISED ACRES:
Level I – 101 acres Level II – 47 acres plus Big Black Test Site – 17 acres; new totals 64 acres - Bi-Weekly Level III – 85 acres – Monthly Level IV – 10 acres - Yearly
Maintenance Level Cutting Period Uniform Height
Cutting frequency
I March 1 – July
2 inches Weekly
I August 1 – October 31
2 ½ inches Bi-Weekly
II March 1 – July
2 inches Bi-Weekly
II August 1 – October 31
2 ½ inches Monthly
II
Big Black Test Site
March 1 – October 31
3 inches Bi-Weekly
III March 1 – October 31
3 inches Monthly
IV March 1 – October 31
4 inches 1st cut in May 2nd cut in October