W912DS21B0010 Amend 0004.pdf
PDF 398 KB Posted
- Attached to
- SOLICITATION: Raritan River, New Jersey, Maintenance Dredging Federal Navigation Project
- Solicitation number
- W912DS21B0010
About this file
This document provides an amendment to a solicitation for maintenance dredging of the Raritan River in New Jersey. The amendment includes responses to contractor questions for informational purposes only and does not revise the original solicitation.
The amendment answers questions on dredging areas requiring different disposal methods concurrently, the potential for debris encountered, responsibility for dredging under bridge structures, restrictions on spud use, and oversight of an independent dredging inspector. The maintenance dredging project involves removing approximately 500,000 cubic yards of shoaled material from two dredging areas to a depth of -25 feet MLLW plus two feet of overdepth allowance. 435,000 cubic yards will be dredged from Area A and placed at an HARS site while 65,000 cubic yards from Area B will be upland placed at contractor furnished sites. The work shall utilize a mechanical dredge with closed clamshell bucket and be completed between September and December 2021, maintaining production rates of 10,000 cubic yards per day for Area A and 2,000 cubic yards per day for Area B.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to provide the Government's responses to contractors' Requests for Information (RFI). This is for
INFORMATIONAL PURPOSES ONLY.
NOTE: Bidders must acknow ledge receipt of this amendment by the date specif ied in the solicitation (or as amended) by one of the follow ing methods: In the space provided on the SF1442, by separate letter, or by signing Block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE LATE BID, LATE
MODIFICATIONS OF BIDS, OR LATE WITHDRAWAL OF BIDS (FAR 14.304).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 03-Jun-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS21B0010
X 9B. DATED (SEE ITEM 11)
07-May-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
02-Jun-2021
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 16-300
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DS21B0010
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 01 00 00 - GENERAL REQUIREMENTS
The following have been added by full text:
AMENDMENT 0004
(Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the Offerors “for information only ”and do not revise the solicitation, plans or specifications.).
Q1. Please confirm that dredge areas requiring upland disposal and areas that require HARS disposal are allowed to be dredged concurrently.
A1. The contractor may perform the work in whichever manner (consecutively or simultaneously) as they see fit.
Q2. Considering the potential for significant debris to be encountered in Items 3, 4 & 5, please add separate line items for debris disposal corresponding to each item.
A2. This channel was dredged as recently as 2014. There is no anticipation of significant debris accumulation in the shoals to be dredged. As debris is encountered during the dredging cycle, it shall be fully noted in the Contractors QC reporting (size, weight, delay, etc.). Any possible request for equitable adjustment must be submitted in writing under the appropriate clause (differing site condition, changes, VEQ, etc.).
Q3. The contract drawings detail shoal material in the area where the rail road bridge swing span support pier is located. Please confirm that the contractor will not be responsible for dredging material located under the swing span support pier.
A3. The contractor shall exercise the utmost caution when dredging in the vicinity of any bridge to prevent the collapse, undermining or damage to the structure. Material located underneath or within close proximity to the bridge structure will not be required to be removed.
Q4. Please confirm there are no restricted areas within the dredge prism where the contractor will not be allowed to utilize spuds.
A4. A search of the regulatory files within New York District, United States Army Corps of Engineers was conducted, and results can be found in Specifications Section 01 30 00 Administrative Requirements. The Contractor shall take all necessary precautions to prevent damage to these structures. The Contractor is required to coordinate with the
W912DS21B0010
owners, if such action is necessary, to mark the structures or move the cables in order to avoid interference with dredging operations.
Q5. The NJ DEP permit specifies an independent dredging inspector to oversee the work. Is the independent dredging inspector the responsibility of the contractor or the USACE?
A5. The Contractor is responsible for having NYD certified dredged material inspectors (DMIs) monitor the transport of all dredged materials to the HARS. More information can be found in the specification Section 35 20 23.10 18. The NJDEP WQC permit requirement for an Independent Dredge Inspector is a separate requirement from the DMI.
This requirement will be fulfilled (virtually or in-person) by USACE as part of our daily Quality Assurance Inspection.
This amendment does not change any other parts of the solicitation.
(End of Summary of Changes)