W912DS-12-R-0002.pdf
PDF 389 KB Posted
- Solicitation number
- W912DS-12-R-0002
About this file
Soliciation W912DS-12-R-0002
View the file
Other files
| File | Type | Posted |
|---|---|---|
| St John's Interim Hospital Dv Lay.pdf | ||
| W912DS-12-R-0002 0008.pdf | ||
| W912DS-12-R-0002 0007.pdf | ||
| W912DS-12-R-0002 0006.pdf | ||
| W912DS-12-R-0002 0005.pdf | ||
| W912DS-12-R-0002 0004.pdf | ||
| W912DS-12-R-0002 0003.pdf | ||
| Site Visit - Sign-in Sheet - dtd 2011-10-25.pdf | ||
| W912DS-12-R-0002 0002.pdf | ||
| E505 ELECTRICAL DETAILS.pdf | ||
| 1980DR_E502.pdf | ||
| 1980DR_ES101.pdf | ||
| 1980DR_GI_CVR.pdf | ||
| 26 20 00.pdf | ||
| 63095_Site_Add01.pdf | ||
| 22 00 70.pdf | ||
| W912DS-12-R-0002 0001.pdf | ||
| 00902.pdf | ||
| 10 14 01.pdf | ||
| 33 40 00.pdf | ||
| 00901.pdf | ||
| 33 70 02.00 10.pdf | ||
| 63095_Site_Final_Specs.pdf | ||
| 63095_Site_Final_Dwgs.pdf |
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project: Construction of the Site Design Package for the St. John’s Temporary Hospital Facility located in Joplin Missouri.
This Procurement is 100% Small Business Set Aside Restricted to Small Business located in New ton and Jasper Counties under the Stafford Act.
NAICS 238910, Size Standard $14,000,000.00
Contract Specialist: Nicholas Emanuel (917) 790-8069
NICHOLAS P EMANUEL 917-790-8069
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
11-Oct-2011
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______ calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________00800
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________6 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________10 Nov 2011 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 1843
NEW YORK NY 10278-0090
W912DS
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
212 264-3013FAX:TEL: 212 264-0238 TEL: FAX:
W912DS-12-R-0002 102
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912DS-12-R-0002
Section 00010 - Solicitation Contract Form
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Lump Sum Base
FFP
All Site Work for St. John's Temporary Hispital Facility in Accordance With the Scope of Work, Plans and Specifications.
FOB: Destination
NET AMT
NOTES
Offerors are reminded that they must propose on the issued plans and specifications. Any deviations, conditions, or attachments made by the offeror himself thereto may render the proposal non-responsive and may be caused for its rejection.
TOTAL
TOTAL CLIN 0001 $__________________
Section 00100 - Bidding Schedule/Instructions to Bidders
CLAUSES INCORPORATED BY REFERENCE
52.204-6 Data Universal Numbering System (DUNS) Number APR 2008 52.211-6 Brand Name or Equal AUG 1999 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2004 52.222-24 Preaward On-Site Equal Opportunity Compliance Evaluation FEB 1999
CLAUSES INCORPORATED BY FULL TEXT
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.
(End of provision)
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from Chief, Contracting Division, 26 Federal Plaza, Room 1843, New York, New York 10278.
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
002211
A. OVERVIEW
1. This is a “Best Value - Lowest Price Technically Acceptable” solicitation, in accordance with FAR 15.101-2, for the construction of the site work for the St. John’s Temporary Hospital Facility in Joplin, MO. This Emergency Response Contract falls under the Robert T. Stafford Disaster Relief and Emergency Assistance Act (42 U.S.C. 5150). Contract will be set aside for Small Business that have a geographical address inside the Jasper or Newton Counties of the state of Missouri.
2. Who May Submit – Any Certified Small Business inside of Jasper or Newton Counties in the state of Missouri
B. PROPOSAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS
1. Requirements and Submissions
Proposals should be submitted initially on the most favorable terms from a price and technical standpoint. Two (2) separate volumes shall be submitted as Volume I - Technical Proposal, and Volume II - Price Proposal. Do not assume that Offerors will be contacted or afforded an opportunity to clarify, discuss or revise their proposals.
Do not submit any material not required by this solicitation (such as company or system brochures). It is assumed that the Offerors will meet all technical portions (construction criteria) of the RFP. The fact that the technical specifications and the drawings are not evaluated factors during solicitation does not relieve the Offerors from meeting all technical, or other, requirements of the RFP.
The information provided in the submissions will be used by the Source Selection Board to evaluate each proposal. Offerors are advised that conciseness and relevance of the proposal is important and unrelated information will not be evaluated. Proposals that provide only superficial coverage of the information required may not receive additional consideration and may be excluded from the competitive range. Additionally, should the proposal include any standard company terms and conditions that conflict with the terms and conditions of the solicitation, the proposal may be determined to be "unacceptable" and thus ineligible for award.
2. Where to Submit – Offerors shall submit their proposal packages to the Corps of Engineers (USACE) at the address shown in Block 7 of Standard Form 1442. If proposals are hand-delivered, you must be aware of enhanced security requirements in effect in the Federal Building and allow for extra time to clear security. You must have a valid picture ID in order to enter the building. No additional time will be allowed due to security requirements. E-MAILED OR
FAXED PROPOSALS ARE NOT AUTHORIZED AND WILL NOT BE ACCEPTED.
3. Submission Deadline – The USACE must receive proposals not later than the time and date specified in Block 13 of Standard Form 1442.
4. Incurring Costs – The Government is not liable for any costs incurred by the Offerors submitting an offer in response to this solicitation.
5. Format Requirements
All text must be legible and easily read. The page size of the Offeror’s proposal shall not exceed 8-1/2 by 11 inches. Diagrams, charts and tables shall conform to the paper size. All text shall be typed single-spaced. Margins (1-inch) shall be clean and clear. If fold-out charts are unavoidable, and are to be utilized, all sheets shall be reproduced on 11 inch by 17 inch, and folded to 8-1/2 by 11 inch size with the title clearly visible at the bottom right corner. Offerors shall limit Volume 1, Technical Proposal, to a maximum of 45 pages including drawings. Pages in excess of 45 pages will not be evaluated.
Submit one (1) original plus seven (7) copies. All proposals shall contain the volume number and the name, address and telephone number of the Prime and Key Subcontractors, Joint Venture, or other entity identified on the cover. The original proposal must be clearly marked as “ORIGINAL” and the original signatures must be in blue ink. Copies of the proposals must also be clearly marked as “COPY x of y (i.e. COPY 1 of 7)”. Proposal clarity and material organization in each volume are mandatory. No material shall be incorporated by reference.
Each volume will be submitted separately bound. The proposal shall address and contain the information listed below
The Proposal shall be organized by factors. They shall be described in separate sections, appropriately tabbed in a report form. All pages of each factor shall be sequentially numbered.
Elaborate or lengthy presentations are not necessary or desirable.
C. FACTORS FOR EVALUATION
1. VOLUME 1 – TECHNICAL PROPOSAL (FACTOR 1, 2 and 3) Factor Location Description Relative Importance FACTOR 1 Vol. 1 TAB A Past Relevant Experience of Offeror’s
Team Factors 1, 2, 3 and 4 are of equal importance
FACTOR 2 Vol. 1 TAB B Past Performance of Offeror’s Team Factors 1, 2, 3 and 4 are of equal importance
FACTOR 3 Vol. 1 TAB C Qualification’s of the Offeror’s Team Factors 1, 2, 3 and 4 are of equal importance
FACTOR 4 Vol. 1 TAB D Technical Approach of the Offeror’s Team
Factors 1, 2, 3 and 4 are of equal importance
a. Vol. 1 TAB A – FACTOR 1 – CONTRACTOR PAST RELEVANT EXPERIENCE
The Offeror shall demonstrate relevant past experience through the submission of not less than two (2) examples of relevant projects not less than 75% complete or physically completed within the last seven (7) years similar in scope, complexity & magnitude to the proposed project. The definition of relevant is provided below:
1. Relevant scope is defined as construction experience of similar type projects which include the construction of heavy site/civil projects with ancillary buildings (experience in construction of buildings not necessary).
2. Relevant complexity is defined as the management and coordination of multi-disciplined construction teams to complete projects that include at least two of the following types of work: underground utilities, site electrical, paving, and grading/earthwork.
3. Relevant magnitude is defined as the performance of site/civil work with the site work portion of a contract value of at least $1,500,000.00.
No more than five (5) total project information sheets shall be submitted. If more than five (5) project information sheets are submitted, only the first five (5) will be considered. Information shall be provided on the form found in Paragraph F, Relevant Project Information Sheet.
Rating Guidelines for Factor 1:
The government will not award to an Offeror that receives an Unacceptable Rating for this factor.
Acceptable: Proposal clearly meeting the minimum requirements of the solicitation.
Unacceptable: Proposal does not clearly meet the minimum requirements of the solicitation.
b. Vol. 1 TAB B – FACTOR 2 – CONTRACTOR PAST PERFORMANCE
Provide performance and evaluation information on the provided Past Performance Customer
Questionnaire for projects submitted under Factor 1. The Past Performance Questionnaire included in the solicitation is provided for the offeror or its team members to submit to this client for each project the offeror includes in its proposal for FACTOR 2. Ensure correct phone numbers and email addresses are provided for the client point of contact. Completed Past Performance Questionnaires should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ which will provide contractor and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for the other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. Also include performance recognition documents received within the last 7 years such as awards, award fee determinations, customer letters of commendation, and any other forms of performance recognition. In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS), including Contractor Performance Assessment Reporting System (CPARS), using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror. While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror. Offeror shall provide an explanation if the performance is less than satisfactory. Offeror shall request Past Performance Customer Questionnaires, found in Section 00 21 00, Paragraph G, Past Performance Customer Questionnaire, to be filled out and returned directly to the USACE at the address shown in Block 8 of Standard Form 1442 If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Nicholas Emanuel via email at Nicholas.P.Emanuel@usace.army.mil prior to proposal closing date. . Questionnaires should be received by the USACE by the proposal submission deadline in order to be considered. The offeror shall provide a copy of the front page of all Past Performance Customer Questionnaires in the technical proposal that were sent to clients as proof that the questionnaires were requested. In the event a Final Revised Proposal is requested, and the Offeror wishes to submit different examples from what was submitted in the original proposal, an attempt shall be made by the Offeror to provide performance and evaluation information on the provided Past Performance Customer Questionnaire for the new projects submitted. Offeror’s shall provide documentation of any terminated contracts with address and phone listings of the owner or owner’s representative.
Rating Guidelines for Factor 2 this factor.
Acceptable: Based on the offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror’s performance record is unknown.
Unacceptable: Based on the offeror’s performance record, the Government has no reasonable expectation that the offeror will be able to successfully perform the required effort
c. Vol. 1 TAB C – FACTOR 3 – QUALIFICATIONS OF THE OFFEROR’S TEAM
The Offeror shall provide the following to show qualifications of the team:
The Offeror shall identify the areas of work they intend to self perform and the areas of work they intend to subcontract along with the names of their significant subcontractors.
Provide an Organization Chart showing Key Personnel for the Offeror's Construction Team. At a minimum, the organizational chart shall identify the Key Personnel, the contractor and significant subcontractor entities, their responsibilities, structure and lines of authority. At a minimum, the following Key personnel shall be identified by name within the chart: Contractor’s (Offeror’s) Project Manager; Construction Quality Control Manager; and Superintendent. A sample organizational chart is provided in Specification Section 00 22 11 Attachment A for information only. The Contractor (Offeror) shall develop its own chart, unique to and specific to their organization and team. Individual resumes in the format found in Specification Section 00 22 11, Paragraph 8.0, Key Personnel Resume Form, shall be provided and that includes the following information:
1) Name.
2) Management title on this project.
3) Number of years with firm and other firms.
4) Number of years in this management title or role.
5) Specialization.
6) Education, apprenticeship, and relevant training.
7) Professional registration.
8) Specific experience and qualifications relevant to this project.
Expected roles and responsibilities of Key Personnel:
Contractor's Project Manager: (Overall Manager of the Project)
1) Performs all project management duties of the project.
2) Serves as the Governments' sole point of contact in all matters relating to work including, but not limited to, contract compliance, progress of work, overall project scheduling, financial matters, and change orders.
3) Attends all job meetings.
4) On-site a minimum of 80% of the time.
5) The Overall Project Manager shall have a minimum of six years of project management experience in design and/or construction on projects of comparable complexity, scope and cost.
Construction Quality Control Manager: (Principal in Charge of Construction Quality Issues and Coordination of Construction Quality Control)
1) The Contractor shall identify the Construction Quality Control Manager as an individual within his organization that is completely responsible for all Construction Quality Issues and shall perform coordination between the contractor, subcontractors, and any Independent Testing Labs and have the authority to act in all construction quality control matters for the prime contractor. During design this person shall at a minimum attend the bi-monthly coordination meeting to discuss coordination and quality issues concerning the design of the project. During construction this person shall be onsite at all times performing Construction Quality Control duties to include, but not limited to, implementation of the three-phase inspection system for all aspects of the construction work specified. This person shall have complete authority in all aspects of Construction Quality control. The prime contractor shall provide a letter to designate the duties and responsibilities of this person.
2) The Construction Quality Control Manager shall meet one of the following requirements: a) Have a Bachelors of Science from an accredited engineering, architecture, or a construction management college and a minimum of two years experience in construction. b) Shall have a minimum of four years of construction experience at a minimum level of a project superintendent.
3) Attends a bi-monthly coordination meeting during the construction phase to discuss coordination and quality issues.
4) On-site at all times during construction performing construction quality control duties.
5) Directly employed by the prime contractor, or will be at the time of award with a signed letter of intention included.
Superintendent / Subcontractor Manager: (Overall Field Manager Responsible for Construction)
1) Performs all superintendent duties required of the Contractor.
2) Serves as the Governments’ On-site point of contact in all matters relating to the work including, but not limited to, scheduling of work, utility interruptions, and testing.
3) Attends all job meetings.
4) On-site at all time during all construction activities.
5) The On-Site Construction Superintendent shall have a minimum of six years construction experience on projects of comparable complexity, scope and cost.
Rating Guidelines for Factor 3
Acceptable: Proposal clearly meets the minimum requirements of the solicitation.
Unacceptable: Proposal does not clearly meet the minimum requirements of the solicitation.
d. Vol. 1 – TAB D – FACTOR 4 – SCHEDULE
Proposal shall include a schedule that illustrates the offeror’s approach to accomplishing the scope of work within the time allotted. The Offeror must meet or exceed the requirements in the Scope of Work. The schedule should include at a minimum the following:
1) Mobilization from notice to proceed
2) Hours of Operation
3) Major Milestone Completion Dates
4) Number of crews, including laborers and foreman
5) Equipment List – list must consist of the proper heavy site/civil equipment needed to perform the job in the required amount of time.
Rating Guidelines for Factor 4
Acceptable: Based on the information provided in the offeror’s schedule , the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Unacceptable: Based on the information provided in the offeror’s schedule, the Government has no reasonable expectation that the offeror will be able to successfully perform the required effort.
2. VOLUME 2 – PRICE PROPOSAL
Factor/Su b Factor
Location Description Relative Importance
N/A Vol. 2 TAB A Price (Standard Form 1442 and Proposal Bid Schedules)
Not Rated
N/A Vol. 2 TAB B Bid Bond Not Rated
N/A Vol. 2 TAB C Required Pre-Award Information Not Rated
N/A Vol. 2 TAB D Representations and Certifications Not Rated
N/A Vol. 2 TAB E Price Breakdown Sheet Not Rated
*NOTE - The Government will evaluate price independently from the technical evaluation. Price will not be rated, but will be evaluated for fairness and reasonableness through the use of a price analysis. The price evaluators will also check for appearance of unbalancing of bids. Offerors are cautioned to include costs in the appropriate bid items, and to evenly distribute indirect costs, such as job overhead, home office overhead, bond, etc. to the appropriate bid items.
a. GENERAL The price proposal shall be submitted in a separate binder labeled "Volume II – Price Proposal".
The sections shall parallel the submission requirements identified in the bid schedule. Provide six copies of bound written material (folded and bound in Volume II).
Submit the Pro Forma information in a separate envelope labeled: “Volume II - Pro Forma Requirements.”
b. TAB A - PRICE (STANDARD FORM 1442, PROPOSAL DATA SHEET AND
CONTRACT LINE ITEM SCHEDULE)
1) Submission Requirements: Submit the properly filled out and executed SF 1442, along with the CLIN Schedule, containing proposed line item and total pricing, as well as the proposed contract duration. See instructions in Section 00 21 00, “Instructions to Offerors”. Submit the Proposal Data Sheet, Attachment 10
2) Evaluation Criteria: Price will not be rated or scored, but will be evaluated for fairness and reasonableness through the use of a price analysis. The price evaluators will also check for appearance of unbalanced line item prices. Offerors are cautioned to distribute direct costs, such as material, labor, equipment, subcontracts, etc. and to evenly distribute indirect costs, such as job overhead, home office overhead, bond, etc., to the appropriate contract line items. Both parties shall presume that field overhead costs through the proposed contract duration are inclusive in the offered price for the contract.
c. TAB B - BID BOND
1) Submission Requirements: Submit the Bid Bond in accordance with the Instructions in Section 00 21 00, “Instructions to Offerors”.
2) Evaluation requirements: This item is not rated. The Government will review the Bid
Bond for legal sufficiency.
d. TAB C - REQUIRED PRE-AWARD INFORMATION
1) Submission Requirements: Submit this information for the Contracting Officer’s determination of Offeror responsibility, which includes, but is not limited to the following:
i. A list of present commitments, including the dollar value thereof, and name of the organization under which the work is being performed. Include names and telephone numbers of personnel within each organization who are familiar with the prospective contractor’s performance.
ii. A certified statement listing; (1) each contract awarded within the preceding three month period exceeding $1,000,000.00 in value with a brief description of the contract; and (2) each contract awarded within the preceding three year period not already physically completed and exceeding $5,000,000.00 in value with a brief description of the contract.
iii. If the prospective contractor is a joint venture, each joint venture member will be required to submit the above defined certification.
iv. One copy of the following information shall be provided:
1. Proof of Financial Ability (Most recent financial statement covering assets and liabilities)
2. Number of years the firm has been in business
3. Name, address and telephone number of firm’s bonding company
4. Information showing Offeror’s bondability for this project. Include the bond rate.
5. Name, address and telephone numbers of two credit/trade references.
2) Evaluation Criteria: In addition to the other proposal information, the Contracting
Officer shall use this information in making an affirmative responsibility determination for award to the Successful Offeror, in accordance with FAR Part 9.
e. TAB D - REPRESENTATIONS & CERTIFICATIONS
1) Submission Requirements: Confirm that the Offeror’s representations and certifications have been completed and also include hard copies under this Tab.
2) Evaluation Criteria: The representations and certifications submitted under this tab and online will be reviewed to ensure the Offeror’s representations are consistent, accurate, and in accordance with regulation. It will not be rated.
f. TAB E - PRICE BREAKDOWN SHEET
1) Submission Requirements: If deemed necessary to evaluate the price proposals, the
Government’s will request a price breakdown of the Contract Line items in a sealed envelope marked “Price Breakdown Information”, in Excel format. The Government will provide details on where and how to send the breakdown. This information will not be needed sooner than three working days after the proposal submission due date.
This information may be required for the initial proposal and, if requested, for any revised proposals. This information is not an opportunity for an Offeror to revise its non-price or price proposal.
2) Evaluation Criteria: Price will not be rated or scored, but will be evaluated for fairness and reasonableness through the use of a price analysis. The price evaluators will also check for appearance of unbalanced line item prices. Offerors are cautioned to distribute direct costs, such as material, labor, equipment, subcontracts, etc. and to evenly distribute indirect costs, such as job overhead, home office overhead, bond, etc., to the appropriate contract line items. Both parties shall presume that field overhead costs through the proposed contract duration are inclusive in the offered price for the contract. If deemed necessary, the supplemental price breakdown information will be used to assist the Government in performing the price evaluations described above.
D. EVALUATION PROCEDURES
1. SOURCE SELECTION EVALUATION BOARD (SSEB): The SSEB will be established to conduct the evaluation of proposals received in response to this solicitation. The evaluation will be based on the content of the proposal and any subsequent discussions required, as well as information obtained from other sources, e.g. past performance information. The SSEB will not consider any information incorporated by reference.
2. EVALUATION: The SSEB will evaluate the pr oposals and assign a consensus rating for each evaluation factor, except that performance risk ratings are assigned to past performance (see below).
If discussions are held, the Government may engage in meaningful discussions with each offeror in the competitive range in accordance with FAR 15.306 (d). The contracting officer will tailor the discussions to each offeror’s proposal relative to the solicitation requirements and evaluation factors. To be meaningful, at a minimum, discussions must include identification of all evaluated deficiencies, significant weaknesses, weaknesses, and any adverse past performance information to which the offeror has not yet had an opportunity to respond. The contracting officer also is encouraged to discuss other aspects of the offeror’s proposal that could, in the opinion of the contracting officer, be altered or explained to enhance materially the proposal’s potential for award. However, the contracting officer will not discuss with individual offerors how their proposal compares to other offerors proposals (technical leveling and/or technical transfusion is not allowed). The Government will provide the Offeror an advance agenda for the discussions.
During discussions, the Government may ask the Offeror to further explain its proposal and to answer questions about it.
Upon conclusion of discussions, those Offerors, will be afforded an opportunity to submit their proposal revisions for final evaluation and selection.
3. DEFINITIONS
a. Deficiency – A material failure of a proposal to meet a Government requirement, where correction of this error is not possible without major revisions to the proposal, or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level or when a failure to meet the RFP requirements is a life/safety issue.
b. Weakness – A flaw in the proposal that increases the risk of unsuccessful contract performance but is easily correctable. Successful contract performance is defined by customer satisfaction.
c. Significant Weakness – As flaw in the proposal that appreciably increases the risk of unsuccessful contract performance. Successful contract performance is defined by customer satisfaction.
d. Uncertainty – Any aspect of the proposal for which the intent of the Offeror is unclear because there may be more than one way to interpret the offer or because inconsistencies in the offer indicate that there may be an error, omission, or mistake.
e. Deviation – Proposal implies or specifically offers a deviation below the specified criteria. The Offeror may or may not have called the deviation to the Government’s attention. A deviation is a deficiency. The proposal must conform to the solicitation requirements for award.
4. PAST PERFORMANCE RISK RATINGS
Risk ratings shall be assigned to Past Performance. Past Performance Risk Ratings assess the risks associated with each Offeror's likelihood of success in performing the requirements stated in the RFP based on the Offeror's demonstrated performance on recent contracts. SSEB members and the SSA may use personal knowledge or information from other sources in its evaluation of an Offeror’s past performance, provided such information is consistent with the established evaluation criteria of the RFP. Offerors that have no relevant performance record will be given a neutral/unknown risk rating for these factors.
Risk Rating System
a. Neutral /Unknown Risk. No relevant performance record is identifiable upon which to base a meaningful performance risk prediction. A search was unable to identify any relevant past performance information for the Offeror or key team members/subcontractors. This is neither a negative or positive assessment.
b. Low Risk. Based on the Offeror's past performance record essentially no doubt exists that the Offeror will successfully perform the required effort.
c. Moderate Risk. Based on the Offeror's past performance record some doubt exists that the Offeror will successfully perform the required effort.
d. High Risk. Based on the Offeror's past performance record extreme doubt exists that the Offeror will successfully perform the required effort.
4. EVALUATION RATING SYSTEM
a. General: The Government will review the proposals and rate the quality of each evaluation factor. The SSEB will rate each proposal against the specified evaluation criteria in the Solicitation requirements. They will not compare proposals at this time.
After all proposals are rated, the Government will compare the ratings and relative advantages and disadvantages of proposals against each other.
b. Review Write-up: The Government will support each rating with a narrative, separately listing all strengths or advantages, weaknesses or disadvantages, deficiencies, and required clarifications.
E. BASIS OF AWARD
1. The Government will award a firm fixed price contract to the responsible Offeror whose technically acceptable proposal represents the lowest price.
2. The basis of award will be the Government’s assessment as to which proposal receives an acceptable rating and is the lowest price. Offerors that do not receive an acceptable rating, will not be selected, regardless of their price (lowest Offeror may not be selected). Price will be evaluated for fairness and reasonableness.
3. Offerors have been reminded to include their best technical and price terms in their initial offer and not to automatically assume that they will have an opportunity to participate in discussions or be asked to submit a revised offer. The Government may make award of an acceptable proposal without discussions, if deemed to be in the best interests of the Government.
F. REVELANT PROJECT INFORMATION SHEET
PRIME CONTRACTOR/SUBCONTRACTOR EXPERIENCE
Offeror’s Name: _______________________________________________________________________
Project Name: ________________________________________________________________________
Project Location: ______________________________________________________________________
Project Size (i.e.; square foot area): ________________________________________________________
Project Description (scope and complexity): _________________________________________________
Facility Type (i.e.; office, educational, etc.): _________________________________________________
Role (i.e. prime, joint venture, sub-contractor) and work Company/Firm self-performed on this project:
Project Award Amount: _________________ Project Completion Amount: ______________________
Project Original Contract Duration and Completion Date: ______________________________________
Project Final Contract Duration and Completion Date: _________________________________________
Client/Agency (if Government, give contract number and name of Contracting Officer):
Client/Agency Point of Contact, Phone Number and Address (if Government, give contract number and name of Contracting Officer):
Construction Contractor and Subcontractor(s): ______________________________________________
G. PAST PERFORMANCE CUSTOMER QUESTIONNAIRE
The Offeror/Contractor listed is being considered in a Source Selection by the US Army Corps of Engineers, New York District. This is a request for past performance information on a project the Offeror has identified as being relevant to this solicitation. This information will be used in the evaluation of the Offeror's performance of that project. The following information, once submitted, will be treated as confidential and will not be released. This information will only be used to evaluate this Offeror for this solicitation. Please complete the following questionnaire utilizing the following guidance:
a. Handwritten responses are sufficient.
b. Circle a rating as listed below and provide a brief supporting narrative for your area of administrative responsibility. In the event of any unsatisfactory performance, please describe the cause and corrective actions, and any other pertinent information relative to the contractor's inadequate performance.
PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0)
CONTRACT INFORMATION (Contractor to complete Blocks 1-4)
1. Contractor Information Firm Name: CAGE Code:
Address: DUNs Number:
Phone Number:
Email Address:
Point of Contact: Contact Phone Number:
2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of project work performed:
If subcontractor, who was the prime (Name/Phone #):
3. Contract Information Contract Number:
Delivery/Task Order Number (if applicable):
Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):
Contract Title:
Contract Location:
Award Date (mm/dd/yy):
Contract Completion Date (mm/dd/yy):
Actual Completion Date (mm/dd/yy):
Explain Differences:
Original Contract Price (Award Amount):
Final Contract Price (to include all modifications, if applicable):
Explain Differences:
4. Project Description:
Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)
CLIENT INFORMATION (Client to complete Blocks 5-8)
5. Client Information Name:
Title:
Phone Number:
Email Address:
6. Describe the client’s role in the project:
7. Date Questionnaire was completed (mm/dd/yy):
8. Client’s Signature:
NOTE: NAVFAC/USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNAIRE AND SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATIONS.
CLIENTS ARE HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER, QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE. PLEASE CONTACT THE OFFEROR FOR USACE POC INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO VERIFY ANY AND ALL INFORMATION ON THIS FORM.
ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT
YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE
RATING DEFINITION NOTE
(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.
An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating.
Also, there should have been NO significant weaknesses identified.
(VG) Very Good Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.
(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract.
There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.
(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.
A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.
(U) Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.
An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.
(N) Not Applicable No information or did not apply to your contract Rating will be neither positive nor negative.
TO BE COMPLETED BY CLIENT
PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS
YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.
1. QUALITY:
a) Quality of technical data/report preparation efforts E VG S M U N
b) Ability to meet quality standards specified for technical performance E VG S M U N
c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance E VG S M U N
d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)
E VG S M U N
2. SCHEDULE/TIMELINESS OF PERFORMANCE:
a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)
E VG S M U N
b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract E VG S M U N
3. CUSTOMER SATISFACTION:
a) To what extent were the end users satisfied with the project? E VG S M U N
b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes;
responsiveness to administrative reports, businesslike and communication)
E VG S M U N
c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer? E VG S M U N
d) Overall customer satisfaction E VG S M U N
4. MANAGEMENT/ PERSONNEL/LABOR
a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force? E VG S M U N
b) Ability to hire, apply, and retain a qualified workforce to this effort E VG S M U N
c) Government Property Control E VG S M U N
d) Knowledge/expertise demonstrated by contractor personnel E VG S M U N
e) Utilization of Small Business concerns E VG S M U N
f) Ability to simultaneously manage multiple projects with multiple disciplines E VG S M U N
g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes E VG S M U N
h) Effectiveness of overall management (including ability to effectively lead, manage and control the program) E VG S M U N
5. COST/FINANCIAL MANAGEMENT
a) Ability to meet the terms and conditions within the contractually agreed E VG S M U N price(s)?
b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client E VG S M U N
c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)
E VG S M U N
d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section. Yes No
e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.
Yes No
f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below. Yes No
6. SAFETY/SECURITY
a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues?
(Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)
E VG S M U N
b) Contractor complied with all security requirements for the project and personnel security requirements. E VG S M U N
7. GENERAL
a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).
E VG S M U N
b) Compliance with contractual terms/provisions (explain if specific issues) E VG S M U N
c) Would you hire or work with this firm again? (If no, please explain below) Yes No
d) In summary, provide an overall rating for the work performed by this contractor. E VG S M U N
Please provide responses to the questions above (if applicable) and/or additional remarks.
Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):
I. KEY PERSONNEL RESUME FORM
Name:________________________________________________________________________
Title:_________________________________________________________________________
Number of Years: With this firm _______________________ With other firms______________
Number of Years in this position or role: ___________________________________________
Specialization: _________________________________________________________________
Professional Registration (Type and State of Registration): _____________________________
Experience and Qualifications Relevant to this Project (provide dates and how it is comparable to the solicitation): ___________________________________________________________________
ATTACHMENT A
Sample Organizational Chart
CONTRACTOR
PROJECT MANAGER
SUPERINTENTDENT
SUBCONTRACTOR
MANAGER
CONSTRUCTION
QUALITY CONTROL
G
SUBCONTRACTORS
Section 00600 - Representations & Certifications
52.203-11 Certification And Disclosure Regarding Payments To
Influence Certain Federal Transactions
SEP 2007
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2011)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 238910 .
(2) The small business size standard is $14,000,000
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the clause at 52.204-7, Central Contractor Registration, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the clause at 52.204-7 is not included in this solicitation, and the offeror is currently registered in CCR, and has completed the ORCA electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:
(__) Paragraph (d) applies.
(__) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in ORCA are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless--
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and…