W912DS-12-R-0002 0002.pdf

PDF 29 KB Posted

Attached to
Site work for temporary hospital building Joplin MO
Solicitation number
W912DS-12-R-0002
Issued by

About this file

Amendment 0002

View the file

Other files

File Type Posted
St John's Interim Hospital Dv Lay.pdf PDF
W912DS-12-R-0002 0008.pdf PDF
W912DS-12-R-0002 0007.pdf PDF
W912DS-12-R-0002 0006.pdf PDF
W912DS-12-R-0002 0005.pdf PDF
W912DS-12-R-0002 0004.pdf PDF
W912DS-12-R-0002 0003.pdf PDF
Site Visit - Sign-in Sheet - dtd 2011-10-25.pdf PDF
E505 ELECTRICAL DETAILS.pdf PDF
1980DR_E502.pdf PDF
1980DR_ES101.pdf PDF
1980DR_GI_CVR.pdf PDF
26 20 00.pdf PDF
63095_Site_Add01.pdf PDF
22 00 70.pdf PDF
W912DS-12-R-0002 0001.pdf PDF
00902.pdf PDF
10 14 01.pdf PDF
33 40 00.pdf PDF
00901.pdf PDF
33 70 02.00 10.pdf PDF
63095_Site_Final_Specs.pdf PDF
63095_Site_Final_Dwgs.pdf PDF
W912DS-12-R-0002.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

Revise Draw ings Provide the sign in sheet from the site visit Answ er questions to prospective offerors for informational purposes only The proposal due date remains the same Note: Offeror must acknow ledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the follow ing methods: in the space provided on the SF 1442, by separate letter, or by telegram by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208)

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 02-Nov-2011

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS-12-R-0002

X 9B. DATED (SEE ITEM 11)

11-Oct-2011

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

01-Nov-2011

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 1843

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS-12-R-0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The following have been added by full text:

AMENDMENT 0002

DRAWINGS

The following Drawings have been REVISED and REISSUED:

� E502

� ES101

The following drawing is being reissued:

� E505

BIDDER’S QUESTIONS AND GOVERNMENT REPLY

Site Visit Question #1: There appears to be discrepancy between notes ‘9’ and ‘13’ on sheet ES101. Please clarify.

Site Visit Answer #1: Notes and ‘9’ and ‘13’ have been reissued in Amendment 2 and state the following:

Note 9: Furnish and Install (1) 1” Empty conduit with pullstring from in-grade junction box to hot box. Conductors provided by others.

Note 13: Furnish and Install in-grade junction box within 5’-0” of interim hospital.

Coordinate final location with hospital contractor.

Site Visit Question #2: Are contractors responsible for their own staking.

Site Visit Answer #2: Yes. As noted in Section 00 80 00.00 18, paragraph 1.c, “The Contractor shall furnish all labor, materials, equipment, and services (except those furnished by the Government) for the following work: All site work to include but not limited to underground utilities, earthwork, paving, etc.” Survey services are not provided by the government.

Site Visit Question #3: Can the sign-in sheet for the site visit be posted?

Site Visit Answer #3: For information purposes only, the sign-in sheet has been posted with amendment 2.

W912DS-12-R-0002

RFI 1 Question #1: In looking at the drawings provided in amendment 1, Sheet E505 cannot be found. Can this sheet still be issued into the contract documents?

RFI 1 Answer #1: For clarity, sheet E505 has been reissued in Amendment 2. It shall be noted that the sheet has not been revised.

RFI 1 Question #2: What is the conductor size for the future ground cabling connection shown on Sheet E502 details 2 and 3?

RFI 1 Question #2: Sheet E502 has been revised and reissued in Amendment 2. A summary of the changes is as follows:

The clouded note on detail 2 of sheet E502 was eliminated.

The clouded note on detail 3 of sheet E502 notes the following: "Provide bare #4/0 copper ground conductor for interconnection of future Central Utility Plant grounding system to future Interim Hospital grounding system."

(End of Summary of Changes)

File details come from the government source that posted it. Updated .