Amendment 0004

View the file

Other files

File Type Posted
St John's Interim Hospital Dv Lay.pdf PDF
W912DS-12-R-0002 0008.pdf PDF
W912DS-12-R-0002 0007.pdf PDF
W912DS-12-R-0002 0006.pdf PDF
W912DS-12-R-0002 0005.pdf PDF
W912DS-12-R-0002 0003.pdf PDF
Site Visit - Sign-in Sheet - dtd 2011-10-25.pdf PDF
W912DS-12-R-0002 0002.pdf PDF
E505 ELECTRICAL DETAILS.pdf PDF
1980DR_E502.pdf PDF
1980DR_ES101.pdf PDF
1980DR_GI_CVR.pdf PDF
26 20 00.pdf PDF
63095_Site_Add01.pdf PDF
22 00 70.pdf PDF
W912DS-12-R-0002 0001.pdf PDF
00902.pdf PDF
10 14 01.pdf PDF
33 40 00.pdf PDF
00901.pdf PDF
33 70 02.00 10.pdf PDF
63095_Site_Final_Specs.pdf PDF
63095_Site_Final_Dwgs.pdf PDF
W912DS-12-R-0002.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

Revise Draw ings Revise Specs Answ er questions from prospective offerors for informational purposes only The proposal due date remains 10 November 2011 at 2:00 P.M. EST Note: Offeror must acknow ledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the follow ing methods: in the space provided on the SF 1442, by separate letter, or by telegram by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208)

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 08-Nov-2011

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS-12-R-0002

X 9B. DATED (SEE ITEM 11)

11-Oct-2011

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

08-Nov-2011

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 1843

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS-12-R-0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The following have been added by full text:

AMENDMENT 0004

DRAWINGS

The following Drawings have been REVISED BUT ARE NOT REISSUED WITH THIS

AMENDMENT:

� CP100, CS101, CS102, CS103, CS104, and detail 3/CS503 � The description for Asphalt Parking Lot has been changed to the following:

1.5” Asphaltic Concrete Surface, 2.5” Asphaltic Concrete Base, 6” Aggregate Base Course

SPECIFICATIONS

The following specification has been REVISED BUT IS NOT REISSUED WITH THIS

AMENDMENT:

� In spec section 32 12 16, table 4, page 7, the following descriptions have been added:

o Gradation 1 (Asphaltic Concrete Base) o Gradation 2 (Asphaltic Concrete Binder) o Gradation 3 (Asphaltic Concrete Surface)

BIDDER’S QUESTIONS AND GOVERNMENT REPLY

RFI 3 Question #1: Will the government accept an aluminized CSP material for the underground detention system for the subject project?

RFI 3 Answer #1: The drawings and specifications indicate performance requirements for the underground detention system. Alternative products and manufacturers are acceptable provided the product meets the requirements identified on CU100 such as:

1) detention volume requirements as indicated

2) be contained within the limits defined

3) capable of discharging to points as indicated

4) capable of handling HS20 loads

W912DS-12-R-0002

Upon award, shop drawings and calculations of the proposed product and system shall be sealed by a registered professional engineer and provided for approval.

RFI 4 Question 1: Please clarify which aggregate gradations are to be used for the asphaltic concrete base as well as the asphaltic concrete surface? We assumed the following:

Gradation #1: Asphaltic concrete base

Gradation #3: Asphaltic concrete surface

RFI 4 Question #1: The assumptions were correct. Per Amendment 4, these clarifications have been added