A.01.30_Attachment_D_Master_Move_Schedule_Example.xls
XLS spreadsheet 56 KB Posted
- Solicitation number
- W9127S17R6032
About this file
Attachment D - Master Move Schedule Example
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A.07.24_Amendment_0004_17R6032.pdf | ||
| Copy_of_A.01.30_Updated_Chesapeake_Bid_Schedule_(003).xlsx | XLSX spreadsheet | |
| A.07.24_Amendment_0003_17R6032.pdf | ||
| A.07.24_Amendment_0002_17R6032.pdf | ||
| W9127S17R6032_Amendment_0001.pdf | ||
| A.01.30_Attachment_H_Drawings.pdf | ||
| A.01.30_Attachment_B_Weekly_Report_Format.xls | XLS spreadsheet | |
| A.01.30_Attachment_E_DRMO_REUSE.pdf | ||
| A.01.30_Attachment_I_NEW_FFE.pdf | ||
| A.01.30_Attachment_G_Cut_Sheets.pdf | ||
| A.01.30_Attachment_A_Submittal_Requirements.pdf | ||
| A.01.30_Attachment_C_Change_Tracker.xlsx | XLSX spreadsheet | |
| A.01.30_Attachment_F_Project_Delivery_Team.xlsx | XLSX spreadsheet | |
| A.01.30_Chesapeake_Bid_Schedule.xlsx | XLSX spreadsheet | |
| A.07.23_Final_Solicitation_17R6032(1).pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Master Move Schedule
| Status | Phase Type | Move Phasing | Head Count | From | To | BOD | Outfitting Period | Move Date | OFB | Resource | Comments | Furniture | DRMO | Space Planning | ||
| Ph 1 - Construction 2/16/09 - 6/18/09 | ||||||||||||||||
| 4th Floor, East Tower | Y/N | Amount | Y/N | |||||||||||||
| X | Final | In Patient Psych (IPP) | 7 | 1E Tower | 4E | 06/08-06/17/09 | 6/17-6/19/09 | 06/22/09 | Contractor XYZ | Ribbon Cutting 6/16/10 | ||||||
| MOVE TOTAL: | 7 | |||||||||||||||
| Ph 2A - Construction 7/28/09 - 7/06/10 In Patient Pharm, Command Conf Ctr | ||||||||||||||||
| X | Temp | LRC | 1 | 2NE | 2NE | 08/06/09 | N/A | 08/14/09 | 08/15/09 | Contractor XYZ | Existing | Yes | Miscellaneous | Complete | ||
| X | Final | Radiology IT & Residents | 6 | 2NE | N/A | N/A | 08/28/09 | 08/31/09 | Contractor XYZ | From Rms #2B511 & 2B513 | ||||||
| X | Final | Infection Control | 2 | 2E Tower | N/A | N/A | 09/04/09 | 09/07/09 | Contractor XYZ | From Rm #2A621 | ||||||
| X | Final | HOLDSS | 7 | 2E Tower | 2NE | 09/01/09 | N/A | 09/11/09 | 09/14/09 | Contractor XYZ | Existing | Yes | Miscellaneous | Complete | ||
| X | Final | Primary Care | 2 | 2SW | TBD | N/A | N/A | 09/18/09 | 09/21/09 | Contractor XYZ | From Rm #2C402 | |||||
| X | Final | Civilian Personnel | 1 | 2E Tower | TBD | N/A | N/A | 09/22/09 | 09/23/09 | Contractor XYZ | From Rm #2A626 to #2A421.1 | |||||
| X | Final | RMO | 24 | 1C Tower | 2E Tower | 09/28/09 | N/A | 10/09/09 | 10/12/09 | Contractor XYZ | Existing | Yes | Miscellaneous | Complete | ||
| X | Temp | A&D | 5 | 1C Tower | 2E, 2SW | 10/01/09 | N/A | 10/09/09 | 10/12/09 | Contractor XYZ | Existing | Yes | Miscellaneous | Complete | ||
| X | Temp | Chapel & Chapel Ministry | 2NW | 1E | N/A | 10/29/09 | 10/30/09 | Contractor XYZ | Existing | Yes | Half of the furniture | No | ||||
| X | Final | Transcription Office | 6 | 4NE | 2NE | 11/02/09 | N/A | 11/06/09 | 11/09/09 | Contractor XYZ | Existing | Yes | Miscellaneous | Complete | ||
| Final | Chapel & Chapel Ministry | 1E | 1C Tower | 12/14/09 | 12/14-12/17/09 | 12/18/09 | 12/21/09 | Contractor XYZ | New | Yes | Remaining furniture | No | ||||
| Final | LRC | 1 | 2NE | 1C Tower | 12/14/09 | 12/14-12/30/09 | 01/05/10 | 01/06/10 | Contractor XYZ | New | Yes | All furniture | No | |||
| Final | On-Site Contractors | 2 | 4NE | Logistics | N/A | N/A | 01/08/10 | 01/11/10 | Contractor XYZ | From Rm #4B507 | ||||||
| Final | Fitness Center | 0 | 4NE | 1E | 01/07/10 | N/A | 01/12/10 | 01/13/10 | Contractor XYZ | Existing | Yes | Half of the equipment | No | |||
| Final | Commander's Conference Center | 0 | 4NE | 1C Tower | 12/14/09 | 12/18/09-01/14/10 | 01/15/10 | 01/18/10 | Contractor XYZ | New | Yes | All furniture | No | |||
| Final | In-Patient Pharmacy | 1SW | 4NE | 05/24/10 | 05/25-06/21/10 | 06/22-07/05/10 | 07/06/10 | Contractor XYZ | New | Yes | All furniture | No | ||||
| MOVE TOTAL: | 57 | |||||||||||||||
| Ph 2B - Construction 8/25/09 - 8/13/10 |
Hemo/Onc Pharm, Hemo/Nephro
| X | Final | ADAPT | 9 | 1E Tower | 1E Tower | 09/03/09 | 06/22-06/25/09 | 09/04/09 | 09/07/09 | Contractor XYZ | Existing | Yes | Miscellaneous | Complete | |
| X | Final | Systems Personnel | 3 | 2E Tower | N/A | N/A | 09/11/09 | 09/14/09 | Contractor XYZ | From Rm #2A622 | |||||
| X | Final | Tricare Flight | 12 | 1C Tower | 2E Tower | 09/28/09 | 06/15-06/18/09 | 10/02/09 | 10/05/09 | Contractor XYZ | Existing | Yes | Miscellaneous | Complete | |
| X | Temp | Tricare Service Center | 10 | 1C Tower | 2NE | 09/10/09 | N/A | 10/02/09 | 10/05/09 | Contractor XYZ | Existing | No | N/A | Complete | |
| Final | Hemodialysis | 3NE | 1E Tower | 02/25/10 | 02/26-03/25/10 | 03/26-03/31/10 | 04/01/10 | Contractor XYZ | Need Ribbon Cutting Date | New | Yes | All furniture | No | ||
| Final | Nephrology | 1SE | 1E Tower | 03/25/10 | 03/26-04/14/10 | 04/15-04/19/10 | 04/20/10 | Contractor XYZ | Need Ribbon Cutting Date | New | Yes | All furniture | No | ||
| Temp | Infusion Center | 12 | 1SE | 1SE | N/A | 04/07-04/26/10 | 04/27/10 | 04/28/10 | Contractor XYZ | Existing | Yes | Miscellaneous | Yes | ||
| Final | Hemo/Onc Pharm & Infusion Center | 1SE | 07/22/10 | 07/27-08/06/10 | 08/06-08/12/10 | 08/13/10 | Contractor XYZ | New | Yes | All furniture | No | ||||
| MOVE TOTAL: | 46 | ||||||||||||||
| Ph 2C - Construction 8/25/09 - 12/04/10 |
CVOR, CVICU, IMCU, ICU, Cath Lab
| X | Temp | Respiratory Therapy (RT) | 3SE | 3NE | N/A | N/A | 09/04/09 | 09/07/09 | Contractor XYZ | Temp Rm #3B525 | |||||
| X | Final | Cysto Procedure Room | 0 | 10/30/09 | 10/30-11/05/09 | 11/06/09 | 11/09/09 | Contractor XYZ | |||||||
| X | Prep | OR 5, 6, 7 & 8 | 3NW | 3NW | N/A | 11/10-11/17/09 | N/A | N/A | Contractor XYZ | Remove existing equip | Existing | Yes | Miscellaneous | No | |
| Final | Respiratory Therapy (RT) | 3NE | 3SE | 01/07/10 | N/A | 01/08/10 | 01/11/10 | Contractor XYZ | Existing | Yes | Miscellaneous | No | |||
| Final | OR 5 & 8 Re-Open | 3NW | 3NW | 03/18/10 | 03/19-03/22/10 | N/A | 03/23/10 | Contractor XYZ | |||||||
| Final | Cath Lab | 0 | NEW | 3SE | 01/14/10 | 02/04-03/31/10 | 04/01-04/02/10 | 04/05/10 | Contractor XYZ | Existing | Yes | Miscellaneous | No | ||
| Final | CVOR | 0 | NEW | 3NW | 02/25/10 | 02/26-05/04/10 | N/A | 05/10/10 | Contractor XYZ | Ribbon Cutting 5/06/10 | New | No | N/A | No | |
| Final | Lead Lined Patient Room | 4E Tower | 4C Tower | 08/17/09 | 05/11-06/21/10 | N/A | 06/22/10 | Contractor XYZ | Existing | No | N/A | No | |||
| Final | IMCU | 3NE | 3NE | 06/28/10 | 06/28-07/02/10 | 07/05-07/09/10 | 07/12/10 | Contractor XYZ | Back-fill Hemodialysis | Existing | Yes | Miscellaneous | No | ||
| Final | CVICU | NEW | 3NE | 09/08/10 | 09/10-09/22/10 | N/A | 09/23/10 | Contractor XYZ | Back-fill IMCU | New | No | N/A | No | ||
| Prep | ICU | 3NE | N/A | 09/22-09/24/10 | N/A | N/A | Contractor XYZ | Clear out existing unit for construction | N/A | No | N/A | No | |||
| Final | ICU | 3NE | 3NE | 11/29/10 | 11/30-12/13/10 | N/A | 12/14/10 | Contractor XYZ | Existing | Yes | Miscellaneous | No | |||
| MOVE TOTAL: | 0 | ||||||||||||||
| Ph 3A - Construction 9/08/09 - 8/27/10 |
OBGYN, CV Pulm, O-Res, Gen Surg
| X | Final | On-Call | 4NW | 1E Tower | 09/14/09 | N/A | 10/14/09 | 10/15/09 | Contractor XYZ | Existing | Yes | Miscellaneous | Complete | ||
| Temp | O-Res Consolidation | 3W Tower | 3W Tower | N/A | 01/18-01/28/10 | 01/29/10 | 02/01/10 | Contractor XYZ | Clear Rms #3A-202.1,.2, .3; 203, 204, 205, 206 | ||||||
| Final | Pre-Op | 3SW | 3W Tower | 02/25/10 | 02/26-03/04/10 | 03/05-03/12/10 | 03/15/10 | Contractor XYZ | Existing | Yes | Miscellaneous | Yes | |||
| Final | Women's Health (OBGYN) | 26 | 3SW | 3SW | N/A | N/A | 03/15-03/19/10 | 03/22/10 | Contractor XYZ | Consolidate within existing area | Existing | Yes | Miscellaneous | Yes | |
| Final | General Surgery Clinic | 3SE | 3SW | 06/07/10 | 06/08-06/15/10 | 06/16-06/18/10 | 06/21/10 | Contractor XYZ | Existing | Yes | Miscellaneous | Yes | |||
| Final | O-Res | 3W Tower | 4NW | 07/30/10 | 08/02-08/13/10 | 08/16-08/20/10 | 08/23/10 | Contractor XYZ | New | Yes | All furniture | No | |||
| Final | APU | 18 | 3E Tower | 3W Tower | 08/25/10 | N/A | 08/26-08/27/10 | 08/30/10 | Contractor XYZ | Existing | Yes | Miscellaneous | Complete | ||
| Final | Cardio/CV Pulmonary Clinics | 1SE | 3SE | 08/10/10 | 08/11-08/20/10 | 08/23-08/27/10 | 08/30/10 | Contractor XYZ | Existing | Yes | Miscellaneous | Yes | |||
| MOVE TOTAL: | 44 | ||||||||||||||
| Ph 3B - Construction 7/30/09-2/11/11 |
Lab, Out-Patient Pharmacy
| X | Temp | Group Practice Manager (GPM) | 7 | 2NW | 4NW | 08/06/09 | N/A | 08/07/09 | 08/10/09 | Contractor XYZ | Existing | Yes | Miscellaneous | Complete | |
| X | Temp | Pathology Offices - 1st Move | 3 | 2NW | 2NW | N/A | N/A | 08/07/09 | 08/10/09 | Contractor XYZ | Existing | Yes | Miscellaneous | Complete | |
| X | Final | Red Cross | 6 | 2NW | 1E Tower | 09/21/09 | N/A | 09/22/09 | 09/23/09 | Contractor XYZ | Existing | Yes | Miscellaneous | Complete | |
| X | Final | Military Retiree (MRAO) | 2 | 2NW | 1E Tower | 09/21/09 | N/A | 09/22/09 | 09/23/09 | Contractor XYZ | Existing | Yes | Miscellaneous | Complete | |
| X | Temp | Tumor Registry | 3 | 2NW | 1E Tower | 09/23/09 | N/A | 09/25/09 | 09/28/09 | Contractor XYZ | Existing | Yes | Miscellaneous | Complete | |
| X | Temp | Referral Management (RMC) | 6 | 2W Tower | 2E Tower | 09/24/09 | N/A | 10/13/09 | 10/14/09 | Contractor XYZ | Med Group to handle Final move | Existing | Yes | Miscellaneous | Complete |
| X | Final | Utilization Management | 6 | 1W Tower | 2W Tower | N/A | N/A | 10/14/09 | 10/15/09 | Contractor XYZ | From #1A203, 1A204, 1A205, 1A224 | ||||
| X | Final | Education & Training | 3 | 1W Tower | 1W Tower | N/A | N/A | 10/29/09 | 10/30/09 | Contractor XYZ | From #1A206 | ||||
| X | Final | Med Photo | 2 | 2NW | 1W Tower | 10/29/09 | N/A | 10/30/09 | 10/31/09 | Contractor XYZ | Existing | Yes | Miscellaneous | Complete | |
| Final | Tumor Registry | 3 | 1E Tower | TBD | TBD | TBD | TBD | TBD | TBD | Existing | Yes | Miscellaneous | TBD | ||
| Final | Tumor Registry High Density Files | 0 | 2NW | TBD | TBD | TBD | TBD | TBD | N/A | Yes | Entire system | N/A | |||
| X | Temp | Lab Moves | 2NW | 2NW | |||||||||||
| X | Relocate Core Lab Equip | 09/28/09 | N/A | 10/03-10/04/09 | 10/05/09 | Contractor XYZ | Existing | Yes | Miscellaneous | No | |||||
| X | Relocate Microbiology Lab Equipment | 09/28/09 | N/A | 10/13 & 10/15/09 | 10/06/09 | Contractor XYZ | Existing | Yes | Miscellaneous | No | |||||
| X | Relocate Radiology Storage 2B504 | N/A | N/A | 10/08-10/09/09 | 10/14/09 | Contractor XYZ | Half of room to be used for Lab Storage | ||||||||
| X | Clear all Lab areas for construction | 10/09/09 | N/A | 10/12-10/16/09 | 10/19/09 | Contractor XYZ | N/A | Yes | Miscellaneous | N/A | |||||
| X | Relocate Lab Personnel | 30 | 09/28/09 | N/A | 10/23/09 | 10/26/09 | Contractor XYZ | Existing | Yes | Miscellaneous | Complete | ||||
| Final | Lab Moves | 2NW | 2NW | ||||||||||||
| Core Lab | 05/13/10 | 05/14-05/28/10 | 05/31-06/25/10 | 06/26/10 | Contractor XYZ | New | Yes | All furniture | No | ||||||
| Microbiology | 05/13/10 | 05/14-05/28/10 | 05/31-06/25/10 | 06/26/10 | Contractor XYZ | New | Yes | All furniture | No | ||||||
| Cytology/Histopathology | 05/13/10 | 05/14-05/28/10 | 05/31-06/25/10 | 06/26/10 | Contractor XYZ | New | Yes | All furniture | No | ||||||
| Blood Bank | 05/13/10 | 05/14-05/28/10 | 05/31-06/25/10 | 06/26/10 | Contractor XYZ | New | Yes | All furniture | No | ||||||
| Drawing Lab | 05/13/10 | 05/14-05/28/10 | 05/31-06/25/10 | 06/26/10 | Contractor XYZ | New | Yes | All furniture | No | ||||||
| Clear all Lab areas for construction | 05/13/10 | 05/14-05/28/10 | 05/31-06/25/10 | 06/26/10 | Contractor XYZ | N/A | Yes | Miscellaneous | No | ||||||
| Relocate Lab Personnel | 05/13/10 | 05/14-05/28/10 | 05/31-06/25/10 | 06/26/10 | Contractor XYZ | New | Yes | All furniture | No | ||||||
| Temp | Pathology Offices - 2nd Move | 2NW | TBD | TBD | N/A | 06/18/10 | 06/21/10 | Contractor XYZ | Existing | Yes | Miscellaneous | Yes | |||
| Final | Pahology Offices | TBD | 2NW | 07/30/10 | 07/31-08/02/10 | 08/03/10 | 08/04/10 | Contractor XYZ | New | Yes | All furniture | No | |||
| Final | Out-Patient Pharmacy | 2SW | 2NW | 01/10/11 | 12/30-01/27/11 | 01/28-02/11/11 | 02/14/11 | Contractor XYZ | New | Yes | All furniture | No | |||
| Final | Tri-Care Service Center to PSC | 10 | 1C Tower | 2NW | 01/10/11 | 01/11-01/24/11 | 02/11/11 | 02/14/11 | Contractor XYZ | Part of new PSC | New | Yes | All furniture | No | |
| Final | A&D to PSC | 5 | TBD | 2NW | 01/10/11 | 01/11-01/24/11 | 02/11/11 | 02/14/11 | Contractor XYZ | Part of new PSC | New | Yes | All furniture | No | |
| Final | Patient Advocacy to PSC | 1 | 1C Tower | 2NW | 01/10/11 | 01/11-01/24/11 | 02/11/11 | 02/14/11 | Contractor XYZ | Part of new PSC | New | Yes | All furniture | No | |
| MOVE TOTAL: | 87 | ||||||||||||||
| Ph 3C - Construction 7/28/09-1/29/10 |
Medical Records, GI Lab
| Final | Medical Records | |||||||||||||
| In-Patient | 2C Tower | 1NW | 11/23/09 | 11/24-12/01/09 | 12/14-12/19/09 | 12/21/09 | Contractor XYZ | New | Yes | Miscellaneous | No | |||
| Out-Patient | 2SE | 1NW | 11/23/09 | 11/24-12/01/09 | 12/14-12/19/09 | 12/21/09 | Contractor XYZ | New | Yes | Miscellaneous | No | |||
| Final | Medical Readiness Office | 13 | 2E Tower | 2C Tower | 01/15/09 | N/A | 01/18/09 | 01/19/09 | Contractor XYZ | Back-fill In-Patient Records | Existing | Yes | Miscellaneous | Complete |
| Final | GPM | 7 | TBD | 2E Tower | 01/22/09 | N/A | 01/22/09 | 01/25/09 | Contractor XYZ | Back-fill Medical Readiness | Existing | Yes | Miscellaneous | Yes |
| Final | GI Lab Prep | 3E Tower | TBD | 02/18/10 | N/A | 02/19-03/05/10 | N/A | Contractor XYZ | Clear Lab for construction | N/A | Yes | Miscellaneous | No | |
| Final | GI | 3E Tower | 3E Tower | 04/05/10 | TBD | TBD | TBD | Existing | Yes | Miscellaneous | No | |||
| MOVE TOTAL: | 20 | |||||||||||||
| TOTAL MOVE COUNT: | 261 |
&L&"Arial,Bold"&12Travis AFB&C&"Arial,Bold"&12DGMC Hospital Modernization Project &R&"Arial,Bold"&12Master Move Schedule &L&9&F&C&9Page &P&R&9Prepared by Cazador for Planning Purposes Only