FY17 MUNS MUNITIONS STORAGE MAGAZINES 2093
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 45 00
QUALITY CONTROL
07/14
PART 1 GENERAL
1.1 REFERENCES
1.2 PAYMENT
1.3 SUBMITTALS
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 QUALITY CONTROL PLAN
3.2.1 Content of the CQC Plan
3.2.2 Additional Requirements for Design Quality Control (DQC) Plan
3.2.2.1 Additional Requirements for Hill AFB DQC Plan
3.2.3 Acceptance of Plan
3.2.4 Notification of Changes
3.3 COORDINATION MEETING
3.4 QUALITY CONTROL ORGANIZATION
3.4.1 Personnel Requirements
3.4.2 CQC System Manager
3.4.3 CQC Personnel
3.4.4 Additional Requirement
3.4.5 Organizational Changes
3.5 SUBMITTALS AND DELIVERABLES
3.6 CONTROL
3.6.1 Preparatory Phase
3.6.2 Initial Phase
3.6.3 Follow-up Phase
3.6.4 Additional Preparatory and Initial Phases
3.7 TESTS
3.7.1 Testing Procedure
3.7.2 Testing Laboratories
3.7.2.1 Capability Check
3.7.2.2 Capability Recheck
3.7.3 Onsite Laboratory
3.7.4 Furnishing or Transportation of Samples for Testing
3.8 COMPLETION INSPECTION
3.8.1 Punch-Out Inspection
3.8.2 Pre-Final Inspection
3.8.3 Final Acceptance Inspection
3.9 DOCUMENTATION
3.10 IMPLEMENTATION OF GOVERNMENT RESIDENT MANAGEMENT SYSTEM
3.11 SAMPLE FORMS
3.12 NOTIFICATION OF NONCOMPLIANCE
01 45 00 - 1 Amendment 0003
3.13 CONSTRUCTION CONTROL MANUAL
ATTACHMENTS:
Sample forms
Test Report Form
Daily Contractor Quality Control Form
Preparatory Inspection Report Form
CESPK FORM 437 - Materials Test Summary
-- End of Section Table of Contents --
01 45 00 - 2
SECTION 01 45 00
QUALITY CONTROL
07/14
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C1077 (2016) Standard Practice for Laboratories Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Laboratory Evaluation
ASTM D3666 (2013) Standard Specification for Minimum Requirements for Agencies Testing and Inspecting Road and Paving Materials
ASTM D3740 (2012a) Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction
ASTM E329 (2014a) Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction
INTERNATIONAL CODE COUNCIL (ICC)
ICC IBC (2015) International Building Code
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1110-1-12 (2006; Change 1) Engineering and Design -- Quality Management
U.S. ARMY CORPS OF ENGINEERS, SOUTH PACIFIC DIVISION (CESPD)
CESPD R 1110-1-8 (2002) Quality Management Plan
U.S. ARMY CORPS OF ENGINEERS, SACRAMENTO DISTRICT (CESPK)
CESPK PAM 415-1-2 (1989) Construction Control Manual
CESPK FORM 437 (1988) Materials Test Summary
1.2 PAYMENT
Separate payment will not be made for providing and maintaining an
01 45 00 - 3 effective Quality Control program, and all associated costs will be included in the applicable Bid Schedule unit or job prices.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Contractor Quality Control (CQC) Plan; G Design Quality Control (DQC) plan; G MTC validation; G
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Establish and maintain an effective quality control (QC) system in compliance with the Contract Clause titled "Inspection of Construction."
QC consist of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements. Cover all design and construction operations, both onsite and offsite, and be keyed to the proposed design and construction sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the contract. In this context the highest level manager responsible for the overall construction activities at the site, including quality and production is the project superintendent. The project superintendent must maintain a physical presence at the site at all times and is responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.
3.2 QUALITY CONTROL PLAN
Submit no later than 90 days prior to start of construction, the Contractor Quality Control (CQC) Plan proposed to implement the requirements of the Contract Clause titled "Inspection of Construction." The Government will consider an interim plan for the first 60 days of operation. Design and construction will be permitted to begin only after acceptance of the CQC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the accepted interim plan will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing the additional work.
3.2.1 Content of the CQC Plan
Include, as a minimum, the following to cover all design and construction operations, both onsite and offsite, including work by subcontractors, designers of record, consultants, architect/engineers (AE), fabricators, suppliers, and purchasing agents:
a. A description of the quality control organization, including a chart
01 45 00 - 4 showing lines of authority and acknowledgment that the CQC staff will implement the three phase control system for all aspects of the work specified. Include a CQC System Manager who reports to the project superintendent.
b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a CQC function.
c. A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities will be issued by the CQC System Manager. Copies of these letters must be furnished to the Government.
d. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, designers of record, consultants, architect engineers (AE), offsite fabricators, suppliers, and purchasing agents. These procedures must be in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.
e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Laboratory facilities approved by the Contracting Officer must be used.)
f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.
g. Procedures for tracking design and construction deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.
h. Reporting procedures, including proposed reporting formats.
i. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and may be identified by different trades or disciplines, or it may be work by the same trade in a different environment. Although each section of the specifications may generally be considered as a definable feature of work, there are frequently more than one definable features under a particular section. This list will be agreed upon during the coordination meeting.
j. Any special inspection requirements as required in accordance with
ICC IBC
3.2.2 Additional Requirements for Design Quality Control (DQC) Plan
The following additional requirements apply to the Design Quality Control (DQC) plan:
a. Provide and maintain a DQC Plan as an effective quality control program which will assure that all services required by this design-build
01 45 00 - 5 contract are performed and provided in a manner that meets professional architectural and engineering quality standards. Prepare the DQC Plan in accordance with CESPD R 1110-1-8, Appendix D. As a minimum, all documents must be technically reviewed by competent, independent reviewers identified in the DQC Plan. The same element that produced the product must not perform the independent technical review (ITR).
Correct errors and deficiencies in the design documents prior to submitting them to the Government.
b. Include the design schedule in the master project schedule, showing the sequence of events involved in carrying out the project design tasks within the specific contract period. This should be at a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work. Include review and correction periods associated with each item. This should be a forward planning as well as a project monitoring tool. The schedule reflects calendar days and not dates for each activity. If the schedule is changed, submit a revised schedule reflecting the change within 7 calendar days. Include in the DQC Plan the discipline-specific checklists to be used during the design and quality control of each submittal. Submit at each design phase as part of the project documentation these completed checklists. ER 1110-1-12 provided some useful information in developing checklists.
c. Implement the DQC Plan by an DQC Manager who has the responsibility of being cognizant of and assuring that all documents on the project have been coordinated. This individual must be a person who has verifiable engineering or architectural design experience and is a registered professional engineer or architect. Notify the Contracting Officer, in writing, of the name of the individual, and the name of an alternate person assigned to the position.
The Contracting Officer will notify the Contractor in writing of the acceptance of the DQC Plan. After acceptance, any proposed changes are subject to the acceptance of the Contracting Officer.
3.2.2.1 Additional Requirements for Hill AFB DQC Plan
Follow the approved DQC Plan throughout the course of the project to assure a quality end product. Should future events dictate revisions to the approved DQC Plan, notify the Contracting Officer in writing and submit the revised plan for approval. The plan must be prepared in 8-1/2" x 11" format. Any charts or schedules included in the plan that are larger than this size must be folded to conform to an 8-1/2" x 11" format. Include a title page and table of contents in the DQC Plan. Include the following elements in the DQC Plan:
a. Management Approach. Define the specific management methodology to be followed during the course of the contract including such aspects as design coordination procedures, quality control, communications, managerial continuity, flexibility and the following:
1. Identify competent, independent reviewers in the DQC Plan to technically review all documents. The same element that produced the product must not perform the independent technical review
(ITR).
2. The following elements must affix a personal stamp to each drawing and specification section verifying their review and general
01 45 00 - 6 compliance with the contract documents, as well as compliance as indicated:
- Design discipline - Compliance to the RFP
- Independent Technical Reviewer - Compliance to the RFP
- CQC Staff member for each discipline identified in paragraph CQC Personnel - Constructability and Operability.
- Prime and Key Subcontractors - Constructability and Operability
3. Correct errors and deficiencies in the design documents prior to submitting them to the Government.
b. Management Structure. Delineate the organizational composition of the firm to clearly show the interrelationship of the management and design team components including all consultants. Include an organization chart to identify the key design and review team members showing their specific responsibilities.
c. Planning and Scheduling. Include the design schedule, showing the sequence of events involved in carrying out the project tasks within the specific contract period. Provide sufficient detail of scheduling to identify all major tasks including those that control the flow of work. Include review and correction periods associated with each in the schedule. This should be a forward planning as well as a project-monitoring tool. The schedule reflects calendar days and not dates for each activity. Submit a revised schedule reflecting changes within seven calendar days of the change.
d. Contractor Review Effort. The Design Quality Control Plan must include, but not be limited to the following contractor performed review elements:
Design Development Review Criteria Review Presentation of Data Review Editing of Guide Specification Review Inter-Disciplinary Review Final Review
e. Quality Control. The professional quality, technical accuracy and the coordination of all design documents and other services to be provided by the Architect-Engineer and any subcontractors/consultants used is of major importance. It is therefore a requirement to have a logical and functional quality control program to assure that errors and deficiencies in all submittals are minimal. To meet this requirement, perform technical and inter-disciplinary reviews and correct all errors and deficiencies in the design documents prior to submitting them to for review. The cover letter, which transmits the design documents for review, must include a statement of certification, co-signed by both the Design Quality Control Manager and the Design Coordination Manager, that a detailed review and coordination of the submitted documents was performed.
f. Design Quality Control Checklists. The DQC Plan must include the checklist and lessons learned. Discipline-specific checklists and lessons learned are to be used during the design and quality control of each submittal. The purpose of these lists is to provide a useful tool for the contractor to assure a quality contract package. The lists point out numerous areas which, when appropriately considered during the design, will help ensure a quality project. The lists should not
01 45 00 - 7 be taken as covering all aspects of the project. These completed checklists must be submitted at each design phase as part of the project documentation. If, during COE review of the final design documents, it becomes apparent that items initialed off have in fact not been completed/coordinated, the COE will notify the Prime Contractor and appropriate action taken. Possible actions include return of the final design package to the contractor for correction, withholding of contract payments and/or completion of an interim "unfavorable" contractor evaluation.
g. Design Review Check-off Matrix. In addition to the Design Quality Control Checklist noted above, prepare a Quality Control Review Matrix.
This Matrix must be developed from SECTION 01 10 10 SPECIFIC TECHNICAL ENGINEERING AND DESIGN CRITERIA. Each individual paragraph must be entered into the matrix and signed off by the Construction Design Coordination Manager, Design Quality Control Manager, and the Independent Technical Reviewer, indicating that the requirements identified have been incorporated in the design documents. See example below:
Administrative
RFP
Requirements
Reviewing Office
Discipline CDC Manager
DQC
Manager
ITR Designer Location in Docs
h. Design Quality Control Manager. The Design Quality Control Manager must implement the DQC Plan. The DQC Manager is an assigned person within the Design Team organization who is present at all internal design reviews, design review conferences, weekly meetings during construction, and cognizant of and assure that all documents on the project have been coordinated. During construction the Design Quality Control Manager must also coordinate all field changes with respective design disciplines. This individual must have verifiable engineering or architectural design experience and is a registered professional engineer or architect (See requirements in Section 01 10 10).
i. Design Coordination Manager. The DQC Plan must identify key subcontractors and a Design Coordination Manager who is an employee of the construction contractor. The Design Coordination Manager assures all requirements of the RFP are incorporated into the design. The Design Coordination Manager coordinates the design and review process within his own organizations with all key subcontractors, and with the design team members. Describe in the DQC Plan how this process is to be performed. This individual must have verifiable engineering or architectural design experience and is a registered professional engineer or architect. (See requirements in Section 01 10 10).
j. Design Quality Control Manager-Design Coordination Manager. Clearly demonstrate in the DQC Plan the interface and responsibilities of the designer (Design Quality Control Manager) and the constructor (Design Coordination Manager).
01 45 00 - 8
3.2.3 Acceptance of Plan
Acceptance of the Contractor's plan is required prior to the start of design and construction. Acceptance is conditional and will be predicated on satisfactory performance during the design and construction. The Government reserves the right to require the Contractor to make changes in his CQC Plan and operations including removal of personnel, as necessary, to obtain the quality specified.
3.2.4 Notification of Changes
After acceptance of the CQC Plan, notify the Contracting Officer in writing of any proposed change. Proposed changes are subject to acceptance by the Contracting Officer.
3.3 COORDINATION MEETING
After the Postaward Conference, before start of design or construction, and prior to acceptance by the Government of the CQC Plan, meet with the Contracting Officer or Authorized Representative and discuss the Contractor's quality control system. Submit the CQC Plan a minimum of 14 calendar days prior to the Coordination Meeting. During the meeting, a mutual understanding of the system details must be developed, including the forms for recording the CQC operations, design activities, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance. Minutes of the meeting will be prepared by the Government, signed by both the Contractor and the Contracting Officer and will become a part of the contract file. There may be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the CQC system or procedures which may require corrective action by the Contractor.
3.4 QUALITY CONTROL ORGANIZATION
3.4.1 Personnel Requirements
The requirements for the CQC organization are a CQC System Manager, a Design Quality Manager, and sufficient number of additional qualified personnel to ensure safety and contract compliance. The Safety and Health Manager must report directly to a senior project (or corporate) official independent from the CQC System Manager. The Safety and Health Manager will also serve as a member of the CQC Staff Personnel identified in the technical provisions as requiring specialized skills to assure the required work is being performed properly will also be included as part of the CQC organization. The Contractor's CQC staff must maintain a presence at the site at all times during progress of the work and have complete authority and responsibility to take any action necessary to ensure contract compliance. The CQC staff will be subject to acceptance by the Contracting Officer. Provide adequate office space, filing systems and other resources as necessary to maintain an effective and fully functional CQC organization. Promptly complete and furnish all letters, material submittals, shop drawing submittals, schedules and all other project documentation to the CQC organization. The CQC organization must be responsible to maintain these documents and records at the site at all times, except as otherwise acceptable to the Contracting Officer.
01 45 00 - 9
3.4.2 CQC System Manager
Identify as CQC System Manager an individual within the onsite work organization who is responsible for overall management of CQC and have the authority to act in all CQC matters for the Contractor. The CQC System Manager must be a graduate engineer, or a graduate architect with a minimum of 5 years construction experience on construction similar to this contract. This CQC System Manager must be on the site at all times during construction and be employed by the prime Contractor. The CQC System Manager must be assigned no other duties. Identify in the plan an alternate to serve in the event of the CQC System Manager's absence. The requirements for the alternate are the same as the CQC System Manager.The Contractor shall identify as CQC System Manager an individual within his organization at the site of the work who shall be responsible for overall management of CQC and have the authority to act in all CQC matters for the Contractor. The CQC System Manager shall be a construction person , with a 4 year degree in Construction Management or Engineering, plus a minimum of 5 years construction experience on construction similar to this contract.
This CQC System Manager shall be on the site at all times during construction and will be employed by the prime Contractor. The CQC System Manager shall be assigned no other duties. An alternate for the CQC System Manager will be identified in the plan to serve in the event of the System Manager's absence. The requirements for the alternate will be the same as for the designated CQC System Manager.
3.4.3 CQC Personnel
In addition to CQC personnel specified elsewhere in the contract, provide as part of the CQC organization specialized personnel to assist the CQC System Manager for the following areas: electrical, mechanical, civil, structural, environmental, and architectural. These individuals must be directly employed by the prime Contractor and may not be employed by a supplier or subcontractor on this project ; be responsible to the CQC System Manager; be physically present at the construction site during work on their areas of responsibility; have the necessary education and/or experience in accordance with the experience matrix listed herein. These individuals may perform other duties but must be allowed sufficient time to perform their assigned quality control duties as described in the Quality Control Plan.
Experience Matrix
Area Qualifications
Civil Graduate Civil Engineer with 52 years experience in the type of work being performed on this project or technician with 5 years related experience.
Electrical Graduate Electrical Engineer with 2 yrs related experience or person 5 years of experience supervising electrical features of work in the field with a construction company
Mechanical Graduate Mechanical Engineer with 2 years' experience in the type of work being performed on this project or technical person with 5 years' related experience.
01 45 00 - 10
Experience Matrix
Area Qualifications
Structural Graduate Civil Engineer (with Structural Track or Focus) or Construction Manager with 2 yrs experience or person 5 years of experience supervising structural features of work in the field with a construction company
Architectural Graduate Architect with with 52 yrs related experience or technical person with 5 years related experience.
Environmental Graduate Environmental Engineer with 32 yrs experience or environmental person with 5 years related experience.
Design Quality Control Manager
Registered Architect or Professional Engineer
3.4.4 Additional Requirement
In addition to the above experience and/or education requirements the CQC System Manager must have completed the course entitled "Construction Quality Management For Contractors." This course is periodically offered by the Sacramento District, contact the Contracting Officer for more information.
3.4.5 Organizational Changes
Maintain the CQC staff at full strength at all times. When it is necessary to make changes to the CQC staff, revise the CQC Plan to reflect the changes and submit the changes to the Contracting Officer for acceptance.
3.5 SUBMITTALS AND DELIVERABLES
Submittals, if needed, must comply with the requirements in Section 01 33 00 SUBMITTAL PROCEDURES. The CQC organization is responsible for certifying that all submittals and deliverables are in compliance with the contract requirements. When Section 23 08 00 COMMISSIONING OF HVAC SYSTEMS is included in the contract, the submittals must be coordinated with Section 01 33 00 SUBMITTAL PROCEDURES to ensure adequate time is allowed for each type of submittal required.
3.6 CONTROL
Contractor Quality Control is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract. At least three phases of control must be conducted by the CQC System Manager for each definable feature of the construction work as follows:
3.6.1 Preparatory Phase
This phase is performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and
01 45 00 - 11 after copies are at the work site. This phase includes:
a. A review of each paragraph of applicable specifications, reference codes, and standards. Make available during the preparatory inspection a copy of those sections of referenced codes and standards applicable to that portion of the work to be accomplished in the field. Maintain and make available in the field for use by Government personnel until final acceptance of the work.
b. Review of the contract drawings.
c. Check to assure that all materials and/or equipment have been tested, submitted, and approved.
d. Review of provisions that have been made to provide required control inspection and testing.
e. Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the contract.
f. Examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawings or submitted data, and are properly stored.
g. Review of the appropriate activity hazard analysis to assure safety requirements are met.
h. Discussion of procedures for controlling quality of the work including repetitive deficiencies. Document construction tolerances and workmanship standards for that feature of work.
i. Check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Officer.
j. Discussion of the initial control phase.
k. The Government must be notified at least 48 hours in advance of beginning the preparatory control phase. Include a meeting conducted by the CQC System Manager and attended by the superintendent, other CQC personnel (as applicable), and the foreman responsible for the definable feature. Document the results of the preparatory phase actions by separate minutes prepared by the CQC System Manager and attach to the daily CQC report. Instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications.
3.6.2 Initial Phase
This phase is accomplished at the beginning of a definable feature of work. Accomplish the following:
a. Check work to ensure that it is in full compliance with contract requirements. Review minutes of the preparatory meeting.
b. Verify adequacy of controls to ensure full contract compliance. Verify required control inspection and testing.
c. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with required sample panels
01 45 00 - 12 as appropriate.
d. Resolve all differences.
e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.
f. The Government must be notified at least 48 hours in advance of beginning the initial phase. Prepare separate minutes of this phase by the CQC System Manager and attach to the daily CQC report. Indicate the exact location of initial phase for future reference and comparison with follow-up phases.
g. The initial phase should be repeated for each new crew to work onsite, or any time acceptable specified quality standards are not being met.
3.6.3 Follow-up Phase
Perform daily checks to assure control activities, including control testing, are providing continued compliance with contract requirements, until completion of the particular feature of work. Record the checks in the CQC documentation. Conduct final follow-up checks and correct all deficiencies prior to the start of additional features of work which may be affected by the deficient work. Do not build upon nor conceal non-conforming work.
3.6.4 Additional Preparatory and Initial Phases
Conduct additional preparatory and initial phases on the same definable features of work if: the quality of on-going work is unacceptable; if there are changes in the applicable CQC staff, onsite production supervision or work crew; if work on a definable feature is resumed after a substantial period of inactivity; or if other problems develop.
3.7 TESTS
3.7.1 Testing Procedure
Perform specified or required tests to verify that control measures are adequate to provide a product which conforms to contract requirements.
Upon request, furnish to the Government duplicate samples of test specimens for possible testing by the Government. Testing includes operation and/or acceptance tests when specified. Procure the services of a Corps of Engineers approved testing laboratory or establish an approved testing laboratory at the project site. Perform the following activities and record and provide the following data:
a. Verify that testing procedures comply with contract requirements.
b. Verify that facilities and testing equipment are available and comply with testing standards.
c. Check test instrument calibration data against certified standards.
d. Verify that recording forms and test identification control number system, including all of the test documentation requirements, have been prepared.
01 45 00 - 13
e. Record results of all tests taken, both passing and failing on the CQC report for the date taken. Specification paragraph reference, location where tests were taken, and the sequential control number identifying the test. If approved by the Contracting Officer, actual test reports may be submitted later with a reference to the test number and date taken. Provide an information copy of tests performed by an offsite or commercial test facility directly to the Contracting Officer. Failure to submit timely test reports as stated may result in nonpayment for related work performed and disapproval of the test facility for this contract.
3.7.2 Testing Laboratories
The listing of validated testing laboratories is available at http://gsl.erdc.usace.army.mil/SL/MTC/.
3.7.2.1 Capability Check
The Government reserves the right to check laboratory equipment in the proposed laboratory for compliance with the standards set forth in the contract specifications and to check the laboratory technician's testing procedures and techniques. Laboratories utilized for testing soils, concrete, asphalt, and steel must meet criteria detailed in ASTM D3740, ASTM C1077, ASTM D3666, and ASTM E329.
Use an independent commercial laboratory that has been validated by abbreviated audit by the Corps of Engineers, Materials Testing Center (MTC), for the required test methods. To receive validation by abbreviated audit by the MTC, the laboratory must complete the required form and submit copies of its AASHTO accreditation certificate, applicable AMRL and/or CCRL inspection reports, and responses to any deficiencies to the MTC no later than 7 days after the Notice to Proceed. The cost for the validation by the MTC is the responsibility of the Contractor.
Any on-site laboratory that is used by the Contractor will require a separate validation by this MTC. All costs associated with this validation will be the responsibility of the Contractor.
Submit the above MTC validation for Government Approval as part of the Contractor's Quality Control Plan. No materials testing must be performed until the laboratory has been validated by the MTC and approved by the Resident Engineer. Include the inspection report(s) and the written response(s) to any noted deficiencies with the Contractor Quality Control Plan and is subject to approval by the Contracting Officer.
3.7.2.2 Capability Recheck
If the selected laboratory fails the capability check, the Contractor will be assessed a charge to reimburse the Government for each succeeding recheck of the laboratory or the checking of a subsequently selected laboratory. Such costs will be deducted from the contract amount due the Contractor.
3.7.3 Onsite Laboratory
The Government reserves the right to utilize the Contractor's control testing laboratory and equipment to make assurance tests, and to check the Contractor's testing procedures, techniques, and test results at no additional cost to the Government.
01 45 00 - 14
3.7.4 Furnishing or Transportation of Samples for Testing
Costs incidental to the transportation of samples or materials are borne by the Contractor. Samples of materials for test verification and acceptance testing by the Government must be delivered to the QA laboratory designated by the Contracting Officer.
Coordination for each specific test, exact delivery location, and dates will be made through the Area Office.
3.8 COMPLETION INSPECTION
3.8.1 Punch-Out Inspection
Conduct an inspection of the work by the CQC Manager near the end of the work, or any increment of the work established by a time stated in the SPECIAL CONTRACT REQUIREMENTS Clause, "Commencement, Prosecution, and Completion of Work", or by the specifications. Prepare and include in the CQC documentation a punch list of items which do not conform to the approved drawings and specifications, as required by paragraph DOCUMENTATION. Include within the list of deficiencies the estimated date by which the deficiencies will be corrected. Make a second inspection the CQC System Manager or staff to ascertain that all deficiencies have been corrected. Once this is accomplished, notify the Government that the facility is ready for the Government Pre-Final inspection.
3.8.2 Pre-Final Inspection
The Government will perform the pre-final inspection to verify that the facility is complete and ready to be occupied. A Government Pre-Final Punch List may be developed as a result of this inspection. Ensure that all items on this list have been corrected before notifying the Government, so that a Final inspection with the customer can be scheduled. Correct any items noted on the Pre-Final inspection in a timely manner. These inspections and any deficiency corrections required by this paragraph must be accomplished within the time slated for completion of the entire work or any particular increment of the work if the project is divided into increments by separate completion dates.
3.8.3 Final Acceptance Inspection
The Contractor's Quality Control Inspection personnel, plus the superintendent or other primary management person, and the Contracting Officer's Representative must be in attendance at the final acceptance inspection. Additional Government personnel including, but not limited to, those from Base/Post Civil Facility Engineer user groups, and major commands may also be in attendance. The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the Pre-Final inspection. Notify the Contracting Officer at least 14 days prior to the final acceptance inspection and include the Contractor's assurance that all specific items previously identified to the Contractor as being unacceptable, along with all remaining work performed under the contract, will be complete and acceptable by the date scheduled for the final acceptance inspection. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance with the contract clause titled "Inspection of Construction".
01 45 00 - 15
3.9 DOCUMENTATION
Maintain current records providing factual evidence that required quality control activities and/or tests have been performed. Include in these records the work of subcontractors and suppliers on an acceptable form that includes, as a minimum, the following information:
a. Contractor/subcontractor and their area of responsibility.
b. Operating plant/equipment with hours worked, idle, or down for repair.
c. Work performed each day, giving location, description, and by whom.
When Network Analysis Schedule (NAS) is used, identify each phase of work performed each day by NAS activity number.
d. Test and/or control activities performed with results and references to specifications/drawings requirements. Identify the control phase (Preparatory, Initial, Follow-up). List of deficiencies noted, along with corrective action.
e. Quantity of materials received at the site with statement as to acceptability, storage, and reference to specifications/drawings requirements.
f. Submittals and deliverables reviewed, with contract reference, by whom, and action taken.
g. Offsite surveillance activities, including actions taken.
h. Job safety evaluations stating what was checked, results, and instructions or corrective actions.
i. Instructions given/received and conflicts in plans and/or specifications.
j. Provide documentation of design quality control activities. For independent design reviews, provide, as a minimum, identification of the Independent Technical Review (ITR) team, the ITR review comments, responses and the record of resolution of the comments.
k. Contractor's verification statement.
Indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered. Cover both conforming and deficient features and include a statement that equipment and materials incorporated in the work and workmanship comply with the contract. Furnish the original and one copy of these records in report form to the Government daily within 24 hours after the date covered by the report, except that reports need not be submitted for days on which no work is performed. As a minimum, prepare and submit one report for every 7 days of no work and on the last day of a no work period. All calendar days must be accounted for throughout the life of the contract. The first report following a day of no work will be for that day only. Reports must be signed and dated by the CQC System Manager. Include copies of test reports and copies of reports prepared by all subordinate quality control personnel within the CQC System Manager Report.
01 45 00 - 16
3.10 IMPLEMENTATION OF GOVERNMENT RESIDENT MANAGEMENT SYSTEM
Use the Government furnished CQC Daily Report Form. This form may be in addition to other Contractor desired reporting forms. However, all other such reporting forms are consolidated into this one Government furnished Daily CQC Report Form. Complete Government furnished Input Forms which lists but is not limited to, Prime Contractor staffing; letter codes;
planned cumulative progress earnings; subcontractor information showing trade, name, address,and insurance expiration dates; definable features of work; pay activity and activity information; required Quality Control tests tied to individual activities; planned User Schooling tied to specific specification paragraphs and Contractor activities; and submittal information relating to specification section, description, activity number, review period and expected procurement period. The sum of all activity values must equal the contract amount, and all Bid Items separately identified, in accordance with the PRICING SCHEDULE. Complete these forms to the satisfaction of the Contracting Officer prior to any contract payment (except for Bonds, Insurance and/or Mobilization, as approved by the Contracting Officer) and must be updated as required.
a. During the course of the contract, the Contractor will receive various Quality Assurance comments from the Government that will reflect corrections needed to Contractor activities or reflect outstanding or future items needing the attention of the Contractor. Acknowledge receipt of these comments by specific number reference on the Daily CQC Report, and also reflect on the Daily CQC Report when these items are specifically completed or corrected.
b. The schedule system must include, as specific and separate activities, all Preparatory Phase Meetings (inspections); all O&M Manuals; and all Test Plans of Electrical and Mechanical Equipment or Systems that require validation testing or instructions to Government representatives.
3.11 SAMPLE FORMS
Sample forms enclosed at the end of this section.
1. Test Report Form
2. Daily Contractor Quality Control Form
3. Preparatory Inspection Report Form
4. CESPK FORM 437 - Materials Test Summary. One set of this form (6 pages), is included in the bid package issued by the Sacramento District Office. This form will be used to summarize the minimum number of materials testing to be made during construction. Submit three copies of the form to the Contracting Officer during the preconstruction meeting. To complete the form, the use of the Construction Control Manual is mandatory.
3.12 NOTIFICATION OF NONCOMPLIANCE
The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. Take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, will be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders will be made the subject of claim for
01 45 00 - 17 extension of time or for excess costs or damages by the Contractor.
3.13 CONSTRUCTION CONTROL MANUAL
In addition to the requirements specified in the various Technical Specifications hereinafter, test procedures and minimum number of tests will be performed in accordance with CESPK PAM 415-1-2. Neither the specified minimum number of tests nor the lack of them must in any way limit or relieve the Contractor of his responsibility to perform adequate tests to assure compliance with the quality requirements of these specifications. The referenced standards listed in this Construction Control Manual must be of the latest issue unless otherwise specified.
-- End of Section --
01 45 00 - 18
| 01 45 00 - QUALITY CONTROL |
| 01 45 00 - QUALITY CONTROL |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 PAYMENT |
| 1.3 SUBMITTALS |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 3.1 GENERAL REQUIREMENTS |
| 3.2 QUALITY CONTROL PLAN |
| 3.2.1 Content of the CQC Plan |
| 3.2.2 Additional Requirements for Design Quality Control DQC Plan |
| 3.2.2.1 Additional Requirements for Hill AFB DQC Plan |
| 3.2.3 Acceptance of Plan |
| 3.2.4 Notification of Changes |
| 3.3 COORDINATION MEETING |
| 3.4 QUALITY CONTROL ORGANIZATION |
| 3.4.1 Personnel Requirements |
| 3.4.2 CQC System Manager |
| 3.4.3 CQC Personnel |
| 3.4.4 Additional Requirement |
| 3.4.5 Organizational Changes |
| 3.5 SUBMITTALS AND DELIVERABLES |
| 3.6 CONTROL |
| 3.6.1 Preparatory Phase |
| 3.6.2 Initial Phase |
| 3.6.3 Follow-up Phase |
| 3.6.4 Additional Preparatory and Initial Phases |
| 3.7 TESTS |
| 3.7.1 Testing Procedure |
| 3.7.2 Testing Laboratories |
| 3.7.2.1 Capability Check |
| 3.7.2.2 Capability Recheck |
| 3.7.3 Onsite Laboratory |
| 3.7.4 Furnishing or Transportation of Samples for Testing |
| 3.8 COMPLETION INSPECTION |
| 3.8.1 Punch-Out Inspection |
| 3.8.2 Pre-Final Inspection |
| 3.8.3 Final Acceptance Inspection |
| 3.9 DOCUMENTATION |
| 3.10 IMPLEMENTATION OF GOVERNMENT RESIDENT MANAGEMENT SYSTEM |
| 3.11 SAMPLE FORMS |
| 3.12 NOTIFICATION OF NONCOMPLIANCE |
| 3.13 CONSTRUCTION CONTROL MANUAL |