W911SA-19-C-2009_Attachment_7_Drawings_with_Notes_Bldg_8.pdf
PDF 2 MB Posted
- Attached to
- Award Notice: Interior/Exterior Repair - USARC El Monte Federal contract opportunity
- Solicitation number
- W911SA-19-B-2011
About this file
W911SA-19-C-2009 Attachment 7 Drawings with Notes Bldg 8
View the file
Other files for this federal contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Building 8
1 2 3
CA010 Floor Plans 8 Training Building_ CADD Notes
Page: 1 Number: 1 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:36:49 PM Office 103
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch white faux wood blinds.
Number: 2 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:38:12 PM Womens Latrine
1. All fixtures in women’s restrooms shall be replaced with new toilet, toilet paper, hand towel, and soap dispensers.
2. Contractor shall remove existing nonoperational exhaust fan and install new exhaust ventilation in both bathrooms including controls.
3. Contractor shall remove existing mirror and install mirror with aluminum frame (size will be according to each bathroom space).
4. Contract shall install vanity shall be (3-5cm thickness), but not plastic and the color should complement the tile selection. Fixtures should be stainless steel kind or approved equivalent. The Contractor shall provide a samples prior to ordering. The colors and final design will be selected by the COR prior to ordering.
5. Vanity must be self-draining to a countersunk sink and have a 4-inch high back splash made from the same tile. All edges and corners shall be rounded for safety. Self-draining component shall be ¼”per foot. The height of vanity must be mounted at 34-inches above finished floor.
6. Contractor shall strip and repaint toilet partitions. Contractor shall consult with COR for color scheme.
7. Contractor shall remove existing wall tiles and replaced with dry wall/ green board textured to match existing walls texture. Flooring tiles shall be removed and replaced. Contractor shall consult with COR for tile color scheme to be utilized in the restrooms.
8. Contractor shall repair interior walls as needed and apply primer and two coats of paint. The contractor shall consult with the COR for the color scheme to be utilized in women’s restrooms.
Number: 3 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:57:57 PM Mens Latrine
1. All fixtures in Men’s restrooms shall be replaced with new toilet paper, hand towel, and soap dispensers.
2. Contractor shall remove existing nonoperational exhaust fan and install new exhaust ventilation in both bathrooms including controls.
Comments from page 1 continued on next page
3. Contractor shall remove existing mirror and install mirror with aluminum frame (size will be according to each bathroom space).
4. Contractor shall install vanity shall be non plastic and the color should complement the tile selection. Fixtures should be stainless steel kind or approved equivalent. The Contractor must provide a sample prior to ordering. The colors and final design will be selected by the COR prior to ordering.
5. Vanity must be self-draining to a countersunk sink and have a 4-inch high back splash shall be tile . All edges and corners shall be rounded for safety. Self-draining component shall be ¼”per foot. The height of counters must be mounted at 34-inches above finished floor.
6. Contractor shall strip and repaint toilet partitions will be stripped and repainted. The contractor shall consult with COR for color scheme.
7. Contractor shall remove existing urinals, reconfigure and install high efficiency urinals with manual, piston-type flushometer with maximum flush rate of 0.13 gallons per flush. Waterless urinals are not acceptable. Furnish and install partitions. Partition will same color as the toilets petitions
8. Contractor shall remove existing wall tiles and replaced with dry wall/ green board with 6" to 8' till border tile should match the flooring tile and texture to match existing walls texture. Flooring tiles shall be removed and replaced.
Contractor shall consult with COR for tile color scheme to be utilized in the restrooms. The contractor shall provide samples/submittal for approval prior to installation.
9. Contractor shall repair interior walls as needed and apply two coats of paint. The contractor shall consult with the COR for the color scheme to be utilized in both men’s and women’s restrooms.
10. Contractor shall remove existing toilet and replace with new. The toilet will be meet the following specifications.
Number: 4 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:37:48 PM Office 106
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch white faux wood blinds.
Number: 5 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:33:33 PM RM 101 Classroom
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch
6. Contractor shall only remove and replace damaged and stained ceiling tiles with like kind.
7. Contractor shall repair and or place existing ceiling lighting fixtures in all areas as necessary with like for like product to match existing.
8. Remove and replace flooring
Number: 6 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:37:04 PM Office 104
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch
Number: 7 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:37:20 PM Corridor The contractor shall remove and replace all exiting vinyl flooring of the interior of the building hallway corridor and drill hall. The carpet tiles in the offices and common work space is to remain in place.
Number: 8 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:38:58 PM Corridor/Hallway The contractor shall remove and replace all exiting vinyl flooring of the interior of the building hallway corridor and drill
Number: 9 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:39:17 PM Corridor/Hallway The contractor shall remove and replace all exiting vinyl flooring of the interior of the building hallway corridor and drill
Number: 10 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:44:45 PM Office 139
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch
Number: 11 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:39:37 PM Office 155
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
Number: 12 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:39:55 PM Office 142
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch
Number: 13 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:44:09 PM Office 140
14 1516
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch
Number: 14 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:43:47 PM Office 141
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch
Number: 15 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 3:01:53 PM Drill Hall 1 The contractor shall remove existing accordion partitions and tracks, and install new accordion tracks and partitions.
2 The contractor shall remove existing floor in the Drill Hall and replace with new vinyl flooring tiles. The contractor shall consult COR for the color scheme. Walls will be patched, fill in cracks and painted with two coats of paint. Doors and door frame window frames will be painted.
Number: 16 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:45:13 PM Office 138
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
19 20
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch
Number: 17 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 3:01:45 PM
1 The contractor shall remove existing accordion partitions and tracks, and install new accordion tracks and partitions.
2 The contractor shall remove existing floor in the Drill Hall and replace with new vinyl flooring tiles. The contractor shall consult COR for the color scheme. Walls will be patched, fill in cracks and painted with two coats of paint. Doors and door frame window
Number: 18 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:45:50 PM Office 137
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch
Number: 19 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 3:03:11 PM Common Area 131 Contractor shall repair and or place existing ceiling lighting fixtures in all areas as necessary with like for like product to match existing.
Number: 20 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 3:02:51 PM
1. The carpet tiles in the offices and common work space is to remain in place.
2. Contractor shall repair and or place existing ceiling lighting fixtures in all areas as necessary with like for like product
3. Contractor shall only remove and replace damaged and stained ceiling tiles with like kind.
Number: 21 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 3:01:28 PM
1 The contractor shall remove existing accordion partitions and tracks, and install new accordion tracks and partitions.
2 The contractor shall remove existing floor in the Drill Hall and replace with new vinyl flooring tiles. The contractor shall consult COR for the color scheme. Walls will be patched, fill in cracks and painted with two coats of paint. Doors and door frame window
Number: 22 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 3:02:22 PM
1. The carpet tiles in the offices and common work space is to remain in place.
2. Contractor shall repair and or place existing ceiling lighting fixtures in all areas as necessary with like for like product
3. Contractor shall only remove and replace damaged and stained ceiling tiles with like kind.
Number: 23 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:46:15 PM Office 136
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch
Number: 24 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:51:20 PM Office 126
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
25 26
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
Number: 25 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:46:29 PM Office 135
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch
Number: 26 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 3:01:07 PM Weight Room
1. The contractor will remove all the gym equipment and relocated. Location will be provided by ROFS?AFOS.
2. Remove rubber matting, steam clean and save for later use.
Remove vinyl flooring and place new vinyl flooring.
Number: 27 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:51:02 PM Office 127
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch
Number: 28 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:46:43 PM Office 134
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch
Number: 29 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:47:30 PM Office 132A
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch
Number: 30 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:46:54 PM Office 133
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch
Number: 31 Author: james.r.bir Subject: Sticky Note Date: 2019/05/29 2:47:11 PM Office 132
1. Contract shall ensure all holes, cracks and marks is repaired with fillers, sealant, and putties as appropriate for the finishing system and substrate, and treat to achieve the required finish in accordance with industry standards before painting. Tint the filler to match substrate if the finish is transparent. Walls should be wiped down as necessary before painting.
2. Contractor shall remove all hardware, hardware accessories and similar items in place and not to be painted or provide surface applied protection prior to surface preparation and painting operations After completions re-install all removed items Exceptional care must be taken to assure tidiness of work.
3. The contractor shall remove old caulking around windows and doors. The contractor shall reseal and caulk windows before painting window frames.
4. Contractor shall paint the interior doors and frames. The contractor shall consult with COR for color scheme
5. Contractor shall remove existing window blind, shades and curtains. Prepare windows as needed, install new 2 inch