Attachment 02 - Pre Bid Inquiries 01.pdf
PDF 105 KB Posted
- Attached to
- Construct Hydrazine Facility
- Solicitation number
- W50S95-22-B-0001
- Issued by
-
Department of the Army National Guard
About this file
This document contains questions and answers related to solicitation number W50S95-22-B-0001 for constructing a hydrazine facility. The solicitation seeks a firm fixed-price contract to provide all plant, labor, materials, equipment and supervision necessary to construct a new hydrazine storage facility at McEntire Joint National Guard Base in Eastover, South Carolina. The scope of work includes site work, concrete foundations and sidewalks, a standing seam metal roof, building utilities, interior finishes, and fire protection systems. The period of performance was extended from 180 to 270 days after notice to proceed. The bid opening date was postponed to July 19, 2022 to allow time for architect responses, and bid results will be posted to SAM.gov. The contract is set aside for small businesses with a NAICS code of 236220 and $39.5 million size standard.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Number: W5S09522B0001 Title: Construct Hydrazine Facility Questions and Answers 01
Question 01 Section 00010-page notes section 4 g states mark the front of the envelope with the following W912QG-21-B-0002” This does not match the solicitation number. Which are we to use?
RESPONSE – This is a typographical error; the correct solicitation number:
W50S95-22-B-0001 was captured in Amendment 01.
Question 02 Solicitation “Attachment 01-Part1Plans Construct Hydrazine PSTE172020” design drawings provided by the Government are labeled “PRELIMINARY NOT FOR CONSTRUCTION OR RECORDING”. Per discussions at this site visit, can the Government please provide the 100% - Issued for Construction Design Documents?
RESPONSE – Attachments 01 – Parts 1 and Parts 2 were revised in Amendment 01 to include Final 100% Drawings and Specifications.
Question 03 Do you think this requirement will be postponed past 01 July?
RESPONSE – Amendment 02 extends the bid opening date until 19 JUL 2022 at 1400 hrs EST to allow sufficient time for the architect to provide responses for the remaining RFI’s. No further extensions to the bid opening date are anticipated.
Question 04 Proposal Submission Requirements - Can the proposal be submitted via Email or are hard copies required?
RESPONSE – Amendment 02 includes a revision to section 00100 Instructions to Bidders. Although mail and electronic mail are still unauthorized, changes have been made to address day of bid opening procedures, hand carried bids, and a process for electronic bid submission.
Question 05 Can the period of performance be extended?
RESPONSE – The performance period for this contract will be increased from 180 days ANP to 270 days ANP via amendment 02.
Question 06 Will the Bid Opening Results be posted on SAM.gov
RESPONSE – Yes, a copy of the bid tabulation report will be posted to Sam.gov.
Question 07 Can the NTP be issue after submittal and materials order?
RESPONSE – The notice to Proceed will be issued at the Preconstruction Conference; material submittals cannot be approved prior to contractor acknowledgement of the NTP.