Pre-Bid RFI Log Replace R22 HVAC Systems Phase 2.xlsx
XLSX spreadsheet 13 KB Posted
- Attached to
- Replace R22 HVAC Systems Phase 2 Federal contract opportunity
- Solicitation number
- W50S8U-24-B-0002
- Issued by
- Department of the Army National Guard
About this file
This document is a Pre-Bid Request for Information (RFI) Log related to a federal contract opportunity to Replace R22 HVAC Systems Phase 2. The key details are:
The U.S. Army National Guard is issuing an Invitation for Bids (IFB) to award a single firm fixed-price contract to replace HVAC systems at a facility in Tulsa, Oklahoma. The base scope of work involves replacing AHU-8 and CU-8 at Building 501. The solicitation also includes option line items to replace additional HVAC units at other buildings. The contract duration is 180 calendar days after notice to proceed. The procurement is set aside 100% for small businesses under NAICS code 238220 with a size standard of $19M. The magnitude of construction is between $100,000 and $250,000. The site visit is scheduled for August 5th, 2024, and bids are due by August 28th, 2024. All questions must be submitted by August 19th, 2024. The key government responses in the RFI log address mechanical drawings, testing requirements, control valve replacement, and equipment preferences.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sealed Bid OF 1419 HVAC_signed.pdf | ||
| Amendment 24-B-0002-0002.pdf | ||
| Pre-Bid RFI Log Replace R22 HVAC Systems Phase 2.pdf | ||
| Conform Copy 24-B-0002-0001.pdf | ||
| Amendment 24-B-0002-0001.pdf | ||
| 501_AHU_CU-8 - Drawings.pdf | ||
| 314_CU-1 and CU-2 - Drawings.pdf | ||
| Site Visit Sign In HVAC R-22 Phase 2_Redacted.pdf | ||
| Site Visit Slides HVAC R-22 Phase 2.pdf | ||
| W50S8U-24-B-0002.pdf | ||
| SoW Base HVAC.pdf | ||
| HVAC Drawings.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Pre-Bid RFI Log for Replace R22 HVAC Systems Phase 2 | ||||
| Date: | RFI No. | RFI QUESTION | GOVERNMENT RESPONSE | |
| 7/30/24 | 1 | Can we get existing mechanical drawings for the areas within the scope of work? | 1. | Drawings attached for CU-1 and CU-2 at B314 and CU-8/AHU-8 at B501. Do not have drawings for CU-11/AHU-11 at B501. |
| 2 | Under the SOW Objectives, number 2 states, “Improve air distribution and balanced airflow throughout the conditioned space.” Does this mean we need a test and balance report? (If so, we definitely will need mechanical drawings.) Similarly, will a preconstruction test and balance be needed to establish a baseline? | Test and balance report not required. Ensure the unit is providing its factory specified CFMs and supply air temperature. | ||
| 3 | Under Project Guidelines, number 21 states, “All flow control valves & actuators are to be replaced on all equipment listed below.” These are condensing units with DX air handlers. As such, there should be no flow controls (typical to a hydronic system). Actuators would be unusual as well, but not out of the realm of possibility, mechanical drawings would clear any confusion. Please clarify. | If units have a hydronic heating coil, control valves will need to be replaced. | ||
| 4 | Under Project Guidelines, number 22 states, “to be equipped with new automated logic controls…” Who is the controls contractor currently in the building? | Controls contractor is Engineered Systems & Energy Solutions, Inc. (ES2). 918-279-6450 | ||
| 8/6/24 | 5 | Can we get existing mechanical drawings for the areas within the scope of work? | Drawings attached for CU-1 and CU-2 at B314 and CU-8/AHU-8 at B501. Do not have drawings for CU-11/AHU-11 at B501. | |
| 6 | Under the SOW Objectives, number 2 states, “Improve air distribution and balanced airflow throughout the conditioned space.” Does this mean we need a test and balance report? (If so, we definitely will need mechanical drawings.) Similarly, will a preconstruction test and balance be needed to establish a baseline? | Test and balance report not required. Ensure the unit is providing its factory specified CFMs and supply air temperature. | ||
| 7 | Under Project Guidelines, number 21 states, “All flow control valves & actuators are to be replaced on all equipment listed below.” These are condensing units with DX air handlers. As such, there should be no flow controls (typical to a hydronic system). Actuators would be unusual as well, but not out of the realm of possibility, mechanical drawings would clear any confusion. Please clarify. | If units have a hydronic heating coil, control valves will need to be replaced. | ||
| 8 | Under Project Guidelines, number 22 states, “to be equipped with new automated logic controls…” Who is the controls contractor currently in the building? | Controls contractor is Engineered Systems & Energy Solutions, Inc. (ES2). 918-279-6450 | ||
| 9 | Under Project Guidelines, number 25 states, “conduct comprehensive testing.” Can we get clarification of what is comprehensive? | Comprehensive testing includes startup of unit and/or accessories in all modes of operation. To include, but not limited to; verifying air flow, supply air temperature, super heat/pressures against the manufacture’s specifications, etc. | ||
| 10 | Under CLIN1 Base Bid, number 1. b. states, “have loads recalculated if new unit is heavier than existing.” Who is the structural engineer with the authority to make the decision? | Provide submittals for all units and the government will make a decision within our authority. | ||
| 11 | Under CLIN1 Base Bid, number 1. g. states, “Install a liquid line sight glass on each AHU and CU to enable visual inspection of the refrigerant flow.” Is this one sight glass at each piece of equipment or one sight glass per system? | One sight glass at each piece of equipment. | ||
| 12 | Under CLIN1 Base Bid, number 1. j. states, “3-phase monitor installation.” If equipment vendor does not offer this with the equipment, can either the controls contractor or electrician provide? | If not offered with equipment, licensed controls or electrician contractor will need to install IAW manufacturers specifications | ||
| 13 | Options 1, 2, and 3 have similar questions to the CLIN1 Base Bid. | Government responses pertain to identical line items only throughout the SOW. | ||
| 14 | Has there been any asbestos remediation done on the existing piping? | Current Base Asbestos Survey does not show any affected areas or piping within the scope of this project. | ||
| 8/13/24 | 15 | Does project require a local mechanical permit to be issued for inspection by city or county | Mechanical license required. Permit not required for inspection by city or county. | |
| 8/19/24 | 16 | Are equipment installed brand specific? We saw Carrier products during the visit. | Carrier is preferred, but not mandatory. Unit must be compatible with Automated Logic/DDC software system for proper monitoring. |
File details come from the government source that posted it. Updated .