A07_Q&As_10_27_17.pdf

PDF 28 KB Posted

Attached to
Work Bench Systems
Solicitation number
W25G1V18R0021
Issued by

About this file

Questions and Answers 10 27 17

View the file

Other files

File Type Posted
A07_Q&As_11_7_17.pdf PDF
A07_Q&As_11_6_17.pdf PDF
A07_Q&As_11_2_17.pdf PDF
Atch_5_Map.PDF PDF
Atch_4_1A_Enclosure_Redacted.pdf PDF
A07_Q&As_10_26_17.pdf PDF
A07_Q&A__10_18_17.pdf PDF
A07_W25G1V-18-R-0021.pdf PDF
Atch_1_Submission_Instructions_and_Evaluation_Criteria.pdf PDF
Atch_2_PWS_Workbenches.pdf PDF
Atch_3_Concept_Dwgs.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers – 10/27/17

The following answers are provided for questions that were not answered on 10/26/17:

Q1. 9.0 DELIVERY & Care of Items and Schedule:

Building 1C bay 6 to the point of use in Building 1A (The indoor distance is approximately 1,500 feet to the point of use). Will this project require any Masonite to be placed in the surrounding area?

A1. Yes. The Electronics Enclosure is a NEW Raised Floor that must be protected from marks, marring, scratches, gouges, etc.

Q5. Can we obtain a floor plan for the job site?

A5. Yes. Drawings were uploaded and incorporated as Atch(s) 4 & 5.