This document provides an overview of work performed under a checked baggage screening equipment deployment services contract. It details typical project lifecycles for both checkpoint and checked baggage systems including planning, design, construction, installation and closeout phases. It describes the equipment and configurations used for stand-alone and inline checked baggage screening systems. It also covers atypical projects involving special events, international locations and facility modifications. The related opportunity notice is for a draft statement of work for checked baggage screening equipment deployment services being re-competed by the Transportation Security Administration. Comments on the draft are due to TSA by January 6, 2020, with the request for proposal planned for the second quarter of fiscal year 2020 and draft evaluation criteria, pricing sheets and contract data requirements lists planned for release by December 20, 2019.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SEDS Draft Labor Categories.pdf | ||
| TEDS overview of work performed_r1.pdf | ||
| Draft SEDS FFP Labor Categories.xlsx | XLSX spreadsheet | |
| Draft SEDS FFP Labor Categories.xlsx | XLSX spreadsheet | |
| CB SEDS IDIQ SOW_Final Draft_r1-2.6.20.docx | DOCX document | |
| Draft SEDS FFP Labor Categories.xlsx | XLSX spreadsheet | |
| CB SEDS IDIQ SOW_Final Draft_r1-2.6.20.docx | DOCX document | |
| Checked Baggage-SEDS Pricing Template.xlsx | XLSX spreadsheet | |
| Draft CDRL A004 Template - In-line Weekly Status Report.xlsx | XLSX spreadsheet | |
| CB-SEDS Pricing Template r2.xlsx | XLSX spreadsheet | |
| Draft CDRL D0001 template - In-line Decommission Report and Checklist.xlsx | XLSX spreadsheet | |
| Eval Criteria to post.docx | DOCX document | |
| DRAFT CDRL A003 Template - Monthly Status Report.docx | DOCX document | |
| Draft In-line SLIS Template.xlsx | XLSX spreadsheet | |
| DRAFT CDRL B0001 Template - OTA Invoice Review Report.docx | DOCX document | |
| Checked Baggage SEDS IDIQ SOW.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TEDS Re-compete Overview of work performed on current contract
Contents
• Typical lifecycle of Checkpoint projects
• Typical lifecycle of Checked baggage projects
– Stand-alone
– Inline
• Atypical projects and Special events
– Checkpoint
– Checked Baggage
• International support
Checkpoint Project Lifecycle Pr e- C on st ru ct io n
Ph as e C on st ru ct io n
Ph as e/ C lo se ou t
Planning Phase
Design Phase
Site Preparation Phase
Shipping and Rigging Phase
Installation and Decommission
Closeout Phase
Advanced Technology (AT)
• OEM(s): Smiths Detection, Rapiscan, L-3
• Training will impact schedule and speed of deployment sites
Checkpoint TSE Overview Advanced Imaging Technology (AIT)
• OEM(s): L-3
• Two Type: Legacy AIT and Reduced Size AIT
Credential Authentication Technology (CAT)
• Initial deployment TBD
Walkthrough Metal Detector
(WTMD)
• OEM(s): CEIA, Garrett
NextGen Explosive Trace Detection (ETD)
• OEM(s): Smiths Detection, Morpho Detection, Implant
Sciences
• Training will impact speed of deployment at sites
Bottled Liquid Scanners (BLS)
• OEM(s): Smiths Detection, CEIA
Planning Phase Design Phase
• Coordination between all stakeholders is critical to collect and assemble data.
• Key stakeholder tasks and requirements are defined.
• The Planning Phase requires the coordination and participation of many critical functions and stakeholders to collect and assemble pertinent data.
• This data is used to identify and define tasks, sequence, task duration, resource requirements, and select deployment sites.
• During this process, stakeholders are provided with defined tasks, system specifications, procurement schedules, OEM production delivery schedules, coordination requirements, facilities, training needs, and approvals and certifications.
DLDs pre-construction phase highlights the planning and design preparation required prior to the installation or decommissioning of any TSE used at an airport checkpoint.
• Airport specifics must be taken into account in regards to permitting and insurance requirements.
• Airport infrastructure must be validated (electrical loading, floor loading, ingress/egress paths).
• Concept drawings and Issue for Construction drawings
• Permitting, bonding, and badging requirements
• Site validation report
• Construction bid documents
Checkpoint: Planning & Design
• Site Surveys
• Site Surveys – Electrical and Data
• Site Surveys – Structural load Analysis
• Site Surveys – permitting documentation
New Checkpoint design and install
Site Preparation Shipping and Rigging Installation/Decom. Project Closeout
• The airport is prepared for installation.
• Site implementation plan created
• TSE is shipped to designated location and rigged into checkpoint.
• Completed Paperwork (ReMAG, DD-1149)
• New equipment is installed and configured.
• Ancillary equipment is installed.
• installation is validated.
• Existing TSE is decommissioned as needed.
• As-built drawings produced
Checkpoint projects overview
Checkpoint: Rigging
Checkpoint: installation
• AIT2 examples:
• Relocation examples:
– Airport contruction
– Terminal expansions
– Checkpoint consolidations
– Airline changes, additional flights
• Relocation examples (cont):
• Checkpoint Expansion example:
– MCO
• New “CT in the checkpoint” example
Current Stand-alone EDS Units
• Screens bags up to 98.4” in length
• Primarily used to screen over length bags (golf bags, skis, etc.)
Reveal
CT80DRXL
• Not utilized for new installations
• May be used for temporary applications
L-3 6000 3DX
• Undergoing recapitalization
• May be used for temporary applications
Morpho Detection (MD)
CTX 5500
• Most SA EDS in fleet 500+
• Throughput: 200 bags per hour (bph)
• Screens bags up to 47” in length
• No longer in production
Reveal CT80DR
• Meets current requirements for
SA EDS
• 45 units deployed
• Throughput: 140-
160 bph
• Screens bags up to
63” in length
Reveal
CT80DR+
Stand-alone Project Lifecycle e- C on st ru ct io n
Ph as e C on st ru ct io n
Ph as e/ C lo se ou t
Planning Phase
Design Phase
Site Preparation Phase
Shipping and Rigging Phase
Installation and Decommission
Closeout Phase
Site Survey Phase
Stand-alone Checked Baggage Planning Phase Site Survey Phase Design Phase
• Initial contact TSA HQ and local
TSA
• Contractor assigns Site Lead
• Contractor should obtain specific information during the Site Survey phase including documented space requirements, obtaining local permits, and establishing phase requirements
• Prepare design drawings and Site Survey Report (SSR)
• Delivery and staging are
• Rigging paths
• Prepare a Site Implementation Plan
(SIP)
• Include a Site Lead Input Sheet
(SLIS)
Stand-alone: Survey Phase
• Site Lead and Designer travel to the site to survey the existing area with photos/dimensions/data on the site using the excel based checklist
• At SAN, this was done for the CT-80DR upgrade program of 5 units.
Stand-alone: Design
• Designer and site lead work together to produced 95% and 100% drawings, a trip report, and a
Site Survey report
Site Preparation Shipping and Rigging Installation/Decom. Project Closeout
• Executing projects in accordance with SIP
• Providing schedule updates and coordinating with local TSA
• Informing stakeholders
• Submitting the DD1149 5 days prior to shipment
• Providing shipping and rigging services
• Debris removal and clean up
• on-site Site Lead support for duration of installation and/or decommission
• Coordinating activities between stakeholders and local TSA
• Obtain written concurrence of project completion from local
TSA
• Closing out permits and returning badges
Stand-alone Checked Baggage
Stand-alone: Site Prep
• electricians install data and fiber for new EDS and computer stations.
• At SAN, the electricians relocated power poles and installed data fiber between the PVS and SVS for each upgraded unit
Relocated power pole Power panel used for new circuits
Stand-alone: Shipping / Rigging
• shippers and riggers deliver equipment to the site from TSALC or the OEM for install on site.
• They relocate TSE as necessary on site and reinstall appropriate equipment
• Riggers remove any TSE slotted for decom and ship back to TSALC
• Riggers remove all dunnage from the site and clean the area
Standalone: Install
Standalone: Close Out
• After install, a final trip report and record drawings are issued
Stand-alone Configurations Example of a Simplified Configuration
• Minimum of a 3 ft. EXIT roller conveyor for CT80DR
• Minimum of a 5 ft. EXIT roller conveyor for a CT80 DR+ or DRXL
• Flat exit conveyor is standard for all Reveal installations
Simplified Configuration – picture below
Lobby install not on pedestal Baggage room install on pedestal
Example of a Complex Configuration
• Minimizes lifting
• Can utilize several different components (roller conveyor, lift gates, pedestals, ball transfer tables, etc.)
Complex Configuration – picture below
No lift solution Integrated EDS
Stand-alone Shipping & Rigging
Consider tight spaces during shipping and rigging of EDS
Cranes may be used when rigging equipment into place
Alternative staging needs to be discussed during the site survey to account for inclement weather
Stand-alone installation
Stand-alone installation
• Upgrade examples
Inline EDS Models Active Procurement
Qualified EDS models
Certified EDS Models
Current Status
L-3 3DX 6700 and
ES
Medium speed Qualified
MDI CTX-9800
SEIO
Medium Speed Qualified
EDS must be qualified to be designed and deployed for Inline system unless under Operational Testing
L-3 3DX-6700 and ES MDI CTX-9800 SEIO
Inline Project Lifecycle e- C on st ru ct io n
Ph as e C on st ru ct io n
Ph as e/ C lo se ou t
Planning Phase
Design Phase
EDS Equipment Delivery
Integration, Pre-Testing and ISAT
Live Operations Run-in and Decommission
Closeout Phase
Construction Phase
Inline Checked Bagage Planning Phase Design Phase
• Airport has submitted an Inline application for design or a facility modification.
• Airport proceeds with design on own or received a TSA funded design OTA
• TSA determines a Site Lead is required for the project
• Airport submits the pre-design, schematic, 30%, 70% and 100% design packages to TSA for review
• Site Lead monitors progress, schedule and facilitates design package submittal
• A Facility Modification is awarded based on bid costs.
• A Site Lead Input Sheet (SLIS) for OEM task order support may be created to meet project schedule
Construction Phase EDS Delivery Integration and Testing
• Airport constructs building infrastructure and baggage handling system
• TEDS Site Lead monitors project progress against schedule throughout the project lifecycle
• Site Lead coordinates EDS equipment needs and schedule
(SLIS)
• TEDS performs invoice validation for work performed
• Coordinating with Airport, OEM, Local TSA for delivery dates
• Ensuring readiness of site prior to arranging shipment
• Submitting the DD1149 5 days prior to shipment
• Providing shipping and rigging services
• Airport and OEM performs integration activities
• Airport performs pre-testing activities
• Site Lead performs pre-testing activities (TRR and TRN)
• Acceptance Testing performs ISAT activities (SSTP and QLR)
• RDC provides Operational Decision Letter and QLR to Airport
Inline Checked Baggage
• Delivery and Rigging examples
• Delivery and Rigging examples examples
– MCO POD A – 115 ton crane used to remove and install EDS units through the terminal roof hatches.
examples
– MCO POD B – 165 ton crane, crane needed to be slightly dismantled to get under the overpass.
Atypical projects and Special events
- Checkpoint
Inauguration Support
• 60 Walk through Metal Detectors across 5 locations. Shipped, rigged, installed and then de-installed, packed and shipped all within a 36 hour window
2nd Ave Subway grand opening
• This was an urgent request to install two WTMDs on 12/30/16 (in less than 24 hours) and provide technician support on 12/31/16 ( New Year’s Eve) for the opening. The WTMDs were decommissioned and returned to the LGA warehouse immediately after.
Complex support for OCONUS locations
• Support to STT after hurricane
– Checked Baggage area damaged by water. We tasked the SI to move two units to an area of the airport that wasn’t damaged.
– Due to the unusual situation, our SI had to be responsive and creative
• Forklift had to be borrowed from the Army
• Remote personal brought in to assist
• Parts flown in from California (OEM) to repair damaged units
Special event support – Rose Bowl
False alarm – WTMD assessment
Floor Analysis
Atypical projects -Checked Baggage
Lead abatement
• Lead abatement - SFO
Meterwide tunnel replacement - PVD
Meter wide tunnel replacement
PIT Gantry Bearing Replacement
International Support
Panama
• Ad-Hoc project to deploy 20 Smiths Detection X-Ray systems from the TSA Logistics Center to Panama. Leidos provided custom crates; performed vapor/vacuum sealing, full crating of 20 Smiths TRX and corresponding UPS units, loaded into ocean containers; ocean transit, local delivery, and inside placement of all 20 units to 5 locations within Panama within a 1-month period. The effort involved significant coordination with stakeholders from TSA Deployment, TSA OGS, U.S. Department of State, Panamanian government, Smiths Detection, and Smiths Detection’s local suppliers.
Panama (cont.)
Mexico
• Conducted site surveys and produced high-quality designs for the 8 most critical Last Point of Departure (LPD) Airports in Mexico. This Task Order was unprecedented in nature involving inter-agency coordination of US government TSA and Department of State (DoS) personnel as well as cross-border coordination with Mexican (national and local) government agency representatives and Mexican Airport Concessionaires. It was also the first TEDS Task Order to involve this level of both conducting detailed surveys and producing designs to US standards in another country and required the team to travel to Mexico for weeks at a time.
| Slide Number 1 |
| Contents |
| Checkpoint Project Lifecycle |
| Checkpoint TSE Overview |
| Checkpoint: Planning & Design |
| Checkpoint: Planning & Design |
| Checkpoint: Planning & Design |
| Checkpoint: Planning & Design |
| Checkpoint: Planning & Design |
| New Checkpoint design and install |
| Checkpoint projects overview |
| Checkpoint: Rigging |
| Checkpoint: installation |
| Checkpoint: installation |
| Checkpoint: installation |
| Checkpoint: installation |
| Checkpoint: installation |
| Current Stand-alone EDS Units |
| Stand-alone Project Lifecycle |
| Stand-alone Checked Baggage |
| Stand-alone: Survey Phase |
| Stand-alone: Design |
| Stand-alone Checked Baggage |
| Stand-alone: Site Prep |
| Stand-alone: Shipping / Rigging |
| Standalone: Install |
| Standalone: Close Out |
| Stand-alone Configurations |
| Stand-alone Configurations |
| Stand-alone Configurations |
| Stand-alone Configurations |
| Stand-alone Shipping & Rigging |
| Stand-alone installation |
| Stand-alone installation |
| Inline EDS Models �Active Procurement |
| Inline Project Lifecycle |
| Inline Checked Bagage |
| Inline Checked Baggage |
| Inline Checked Baggage |
| Inline Checked Baggage |
| Inline Checked Baggage |
| Inline Checked Baggage |
| Atypical projects and Special events�- Checkpoint |
| Inauguration Support |
| 2nd Ave Subway grand opening |
| Complex support for OCONUS locations |
| Special event support – Rose Bowl |
| False alarm – WTMD assessment |
| Floor Analysis |
| Atypical projects�-Checked Baggage |
| Lead abatement |
| Meterwide tunnel replacement - PVD |
| Meter wide tunnel replacement |
| PIT Gantry Bearing Replacement |
| International�Support |
| Panama |
| Panama (cont.) |
| Mexico |