TEDS overview of work performed.pdf

PDF 3 MB Posted

Attached to
Screening Equipment Deployment Services - Checked Baggage
Solicitation number
TSA25-04-03883
Issued by

About this file

This document provides an overview of work performed under a checked baggage screening equipment deployment services contract. It details typical project lifecycles for both checkpoint and checked baggage systems including planning, design, construction, installation and closeout phases. It describes the equipment and configurations used for stand-alone and inline checked baggage screening systems. It also covers atypical projects involving special events, international locations and facility modifications. The related opportunity notice is for a draft statement of work for checked baggage screening equipment deployment services being re-competed by the Transportation Security Administration. Comments on the draft are due to TSA by January 6, 2020, with the request for proposal planned for the second quarter of fiscal year 2020 and draft evaluation criteria, pricing sheets and contract data requirements lists planned for release by December 20, 2019.

View the file

Other files

File Type Posted
SEDS Draft Labor Categories.pdf PDF
TEDS overview of work performed_r1.pdf PDF
Draft SEDS FFP Labor Categories.xlsx XLSX spreadsheet
Draft SEDS FFP Labor Categories.xlsx XLSX spreadsheet
CB SEDS IDIQ SOW_Final Draft_r1-2.6.20.docx DOCX document
Draft SEDS FFP Labor Categories.xlsx XLSX spreadsheet
CB SEDS IDIQ SOW_Final Draft_r1-2.6.20.docx DOCX document
Checked Baggage-SEDS Pricing Template.xlsx XLSX spreadsheet
Draft CDRL A004 Template - In-line Weekly Status Report.xlsx XLSX spreadsheet
CB-SEDS Pricing Template r2.xlsx XLSX spreadsheet
Draft CDRL D0001 template - In-line Decommission Report and Checklist.xlsx XLSX spreadsheet
Eval Criteria to post.docx DOCX document
DRAFT CDRL A003 Template - Monthly Status Report.docx DOCX document
Draft In-line SLIS Template.xlsx XLSX spreadsheet
DRAFT CDRL B0001 Template - OTA Invoice Review Report.docx DOCX document
Checked Baggage SEDS IDIQ SOW.docx DOCX document
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TEDS Re-compete Overview of work performed on current contract

Contents

• Typical lifecycle of Checkpoint projects

• Typical lifecycle of Checked baggage projects

– Stand-alone

– Inline

• Atypical projects and Special events

– Checkpoint

– Checked Baggage

• International support

Checkpoint Project Lifecycle Pr e- C on st ru ct io n

Ph as e C on st ru ct io n

Ph as e/ C lo se ou t

Planning Phase

Design Phase

Site Preparation Phase

Shipping and Rigging Phase

Installation and Decommission

Closeout Phase

Advanced Technology (AT)

• OEM(s): Smiths Detection, Rapiscan, L-3

• Training will impact schedule and speed of deployment sites

Checkpoint TSE Overview Advanced Imaging Technology (AIT)

• OEM(s): L-3

• Two Type: Legacy AIT and Reduced Size AIT

Credential Authentication Technology (CAT)

• Initial deployment TBD

Walkthrough Metal Detector

(WTMD)

• OEM(s): CEIA, Garrett

NextGen Explosive Trace Detection (ETD)

• OEM(s): Smiths Detection, Morpho Detection, Implant

Sciences

• Training will impact speed of deployment at sites

Bottled Liquid Scanners (BLS)

• OEM(s): Smiths Detection, CEIA

Planning Phase Design Phase

• Coordination between all stakeholders is critical to collect and assemble data.

• Key stakeholder tasks and requirements are defined.

• The Planning Phase requires the coordination and participation of many critical functions and stakeholders to collect and assemble pertinent data.

• This data is used to identify and define tasks, sequence, task duration, resource requirements, and select deployment sites.

• During this process, stakeholders are provided with defined tasks, system specifications, procurement schedules, OEM production delivery schedules, coordination requirements, facilities, training needs, and approvals and certifications.

DLDs pre-construction phase highlights the planning and design preparation required prior to the installation or decommissioning of any TSE used at an airport checkpoint.

• Airport specifics must be taken into account in regards to permitting and insurance requirements.

• Airport infrastructure must be validated (electrical loading, floor loading, ingress/egress paths).

• Concept drawings and Issue for Construction drawings

• Permitting, bonding, and badging requirements

• Site validation report

• Construction bid documents

Checkpoint: Planning & Design

• Site Surveys

• Site Surveys – Electrical and Data

• Site Surveys – Structural load Analysis

• Site Surveys – permitting documentation

New Checkpoint design and install

Site Preparation Shipping and Rigging Installation/Decom. Project Closeout

• The airport is prepared for installation.

• Site implementation plan created

• TSE is shipped to designated location and rigged into checkpoint.

• Completed Paperwork (ReMAG, DD-1149)

• New equipment is installed and configured.

• Ancillary equipment is installed.

• installation is validated.

• Existing TSE is decommissioned as needed.

• As-built drawings produced

Checkpoint projects overview

Checkpoint: Rigging

Checkpoint: installation

• AIT2 examples:

• Relocation examples:

– Airport contruction

– Terminal expansions

– Checkpoint consolidations

– Airline changes, additional flights

• Relocation examples (cont):

• Checkpoint Expansion example:

– MCO

• New “CT in the checkpoint” example

Current Stand-alone EDS Units

• Screens bags up to 98.4” in length

• Primarily used to screen over length bags (golf bags, skis, etc.)

Reveal

CT80DRXL

• Not utilized for new installations

• May be used for temporary applications

L-3 6000 3DX

• Undergoing recapitalization

• May be used for temporary applications

Morpho Detection (MD)

CTX 5500

• Most SA EDS in fleet 500+

• Throughput: 200 bags per hour (bph)

• Screens bags up to 47” in length

• No longer in production

Reveal CT80DR

• Meets current requirements for

SA EDS

• 45 units deployed

• Throughput: 140-

160 bph

• Screens bags up to

63” in length

Reveal

CT80DR+

Stand-alone Project Lifecycle e- C on st ru ct io n

Ph as e C on st ru ct io n

Ph as e/ C lo se ou t

Planning Phase

Design Phase

Site Preparation Phase

Shipping and Rigging Phase

Installation and Decommission

Closeout Phase

Site Survey Phase

Stand-alone Checked Baggage Planning Phase Site Survey Phase Design Phase

• Initial contact TSA HQ and local

TSA

• Contractor assigns Site Lead

• Contractor should obtain specific information during the Site Survey phase including documented space requirements, obtaining local permits, and establishing phase requirements

• Prepare design drawings and Site Survey Report (SSR)

• Delivery and staging are

• Rigging paths

• Prepare a Site Implementation Plan

(SIP)

• Include a Site Lead Input Sheet

(SLIS)

Stand-alone: Survey Phase

• Site Lead and Designer travel to the site to survey the existing area with photos/dimensions/data on the site using the excel based checklist

• At SAN, this was done for the CT-80DR upgrade program of 5 units.

Stand-alone: Design

• Designer and site lead work together to produced 95% and 100% drawings, a trip report, and a

Site Survey report

Site Preparation Shipping and Rigging Installation/Decom. Project Closeout

• Executing projects in accordance with SIP

• Providing schedule updates and coordinating with local TSA

• Informing stakeholders

• Submitting the DD1149 5 days prior to shipment

• Providing shipping and rigging services

• Debris removal and clean up

• on-site Site Lead support for duration of installation and/or decommission

• Coordinating activities between stakeholders and local TSA

• Obtain written concurrence of project completion from local

TSA

• Closing out permits and returning badges

Stand-alone Checked Baggage

Stand-alone: Site Prep

• electricians install data and fiber for new EDS and computer stations.

• At SAN, the electricians relocated power poles and installed data fiber between the PVS and SVS for each upgraded unit

Relocated power pole Power panel used for new circuits

Stand-alone: Shipping / Rigging

• shippers and riggers deliver equipment to the site from TSALC or the OEM for install on site.

• They relocate TSE as necessary on site and reinstall appropriate equipment

• Riggers remove any TSE slotted for decom and ship back to TSALC

• Riggers remove all dunnage from the site and clean the area

Standalone: Install

Standalone: Close Out

• After install, a final trip report and record drawings are issued

Stand-alone Configurations Example of a Simplified Configuration

• Minimum of a 3 ft. EXIT roller conveyor for CT80DR

• Minimum of a 5 ft. EXIT roller conveyor for a CT80 DR+ or DRXL

• Flat exit conveyor is standard for all Reveal installations

Simplified Configuration – picture below

Lobby install not on pedestal Baggage room install on pedestal

Example of a Complex Configuration

• Minimizes lifting

• Can utilize several different components (roller conveyor, lift gates, pedestals, ball transfer tables, etc.)

Complex Configuration – picture below

No lift solution Integrated EDS

Stand-alone Shipping & Rigging

Consider tight spaces during shipping and rigging of EDS

Cranes may be used when rigging equipment into place

Alternative staging needs to be discussed during the site survey to account for inclement weather

Stand-alone installation

Stand-alone installation

• Upgrade examples

Inline EDS Models Active Procurement

Qualified EDS models

Certified EDS Models

Current Status

L-3 3DX 6700 and

ES

Medium speed Qualified

MDI CTX-9800

SEIO

Medium Speed Qualified

EDS must be qualified to be designed and deployed for Inline system unless under Operational Testing

L-3 3DX-6700 and ES MDI CTX-9800 SEIO

Inline Project Lifecycle e- C on st ru ct io n

Ph as e C on st ru ct io n

Ph as e/ C lo se ou t

Planning Phase

Design Phase

EDS Equipment Delivery

Integration, Pre-Testing and ISAT

Live Operations Run-in and Decommission

Closeout Phase

Construction Phase

Inline Checked Bagage Planning Phase Design Phase

• Airport has submitted an Inline application for design or a facility modification.

• Airport proceeds with design on own or received a TSA funded design OTA

• TSA determines a Site Lead is required for the project

• Airport submits the pre-design, schematic, 30%, 70% and 100% design packages to TSA for review

• Site Lead monitors progress, schedule and facilitates design package submittal

• A Facility Modification is awarded based on bid costs.

• A Site Lead Input Sheet (SLIS) for OEM task order support may be created to meet project schedule

Construction Phase EDS Delivery Integration and Testing

• Airport constructs building infrastructure and baggage handling system

• TEDS Site Lead monitors project progress against schedule throughout the project lifecycle

• Site Lead coordinates EDS equipment needs and schedule

(SLIS)

• TEDS performs invoice validation for work performed

• Coordinating with Airport, OEM, Local TSA for delivery dates

• Ensuring readiness of site prior to arranging shipment

• Submitting the DD1149 5 days prior to shipment

• Providing shipping and rigging services

• Airport and OEM performs integration activities

• Airport performs pre-testing activities

• Site Lead performs pre-testing activities (TRR and TRN)

• Acceptance Testing performs ISAT activities (SSTP and QLR)

• RDC provides Operational Decision Letter and QLR to Airport

Inline Checked Baggage

• Delivery and Rigging examples

• Delivery and Rigging examples examples

– MCO POD A – 115 ton crane used to remove and install EDS units through the terminal roof hatches.

examples

– MCO POD B – 165 ton crane, crane needed to be slightly dismantled to get under the overpass.

Atypical projects and Special events

- Checkpoint

Inauguration Support

• 60 Walk through Metal Detectors across 5 locations. Shipped, rigged, installed and then de-installed, packed and shipped all within a 36 hour window

2nd Ave Subway grand opening

• This was an urgent request to install two WTMDs on 12/30/16 (in less than 24 hours) and provide technician support on 12/31/16 ( New Year’s Eve) for the opening. The WTMDs were decommissioned and returned to the LGA warehouse immediately after.

Complex support for OCONUS locations

• Support to STT after hurricane

– Checked Baggage area damaged by water. We tasked the SI to move two units to an area of the airport that wasn’t damaged.

– Due to the unusual situation, our SI had to be responsive and creative

• Forklift had to be borrowed from the Army

• Remote personal brought in to assist

• Parts flown in from California (OEM) to repair damaged units

Special event support – Rose Bowl

False alarm – WTMD assessment

Floor Analysis

Atypical projects -Checked Baggage

Lead abatement

• Lead abatement - SFO

Meterwide tunnel replacement - PVD

Meter wide tunnel replacement

PIT Gantry Bearing Replacement

International Support

Panama

• Ad-Hoc project to deploy 20 Smiths Detection X-Ray systems from the TSA Logistics Center to Panama. Leidos provided custom crates; performed vapor/vacuum sealing, full crating of 20 Smiths TRX and corresponding UPS units, loaded into ocean containers; ocean transit, local delivery, and inside placement of all 20 units to 5 locations within Panama within a 1-month period. The effort involved significant coordination with stakeholders from TSA Deployment, TSA OGS, U.S. Department of State, Panamanian government, Smiths Detection, and Smiths Detection’s local suppliers.

Panama (cont.)

Mexico

• Conducted site surveys and produced high-quality designs for the 8 most critical Last Point of Departure (LPD) Airports in Mexico. This Task Order was unprecedented in nature involving inter-agency coordination of US government TSA and Department of State (DoS) personnel as well as cross-border coordination with Mexican (national and local) government agency representatives and Mexican Airport Concessionaires. It was also the first TEDS Task Order to involve this level of both conducting detailed surveys and producing designs to US standards in another country and required the team to travel to Mexico for weeks at a time.

Slide Number 1
Contents
Checkpoint Project Lifecycle
Checkpoint TSE Overview
Checkpoint: Planning & Design
Checkpoint: Planning & Design
Checkpoint: Planning & Design
Checkpoint: Planning & Design
Checkpoint: Planning & Design
New Checkpoint design and install
Checkpoint projects overview
Checkpoint: Rigging
Checkpoint: installation
Checkpoint: installation
Checkpoint: installation
Checkpoint: installation
Checkpoint: installation
Current Stand-alone EDS Units
Stand-alone Project Lifecycle
Stand-alone Checked Baggage
Stand-alone: Survey Phase
Stand-alone: Design
Stand-alone Checked Baggage
Stand-alone: Site Prep
Stand-alone: Shipping / Rigging
Standalone: Install
Standalone: Close Out
Stand-alone Configurations
Stand-alone Configurations
Stand-alone Configurations
Stand-alone Configurations
Stand-alone Shipping & Rigging
Stand-alone installation
Stand-alone installation
Inline EDS Models �Active Procurement
Inline Project Lifecycle
Inline Checked Bagage
Inline Checked Baggage
Inline Checked Baggage
Inline Checked Baggage
Inline Checked Baggage
Inline Checked Baggage
Atypical projects and Special events�- Checkpoint
Inauguration Support
2nd Ave Subway grand opening
Complex support for OCONUS locations
Special event support – Rose Bowl
False alarm – WTMD assessment
Floor Analysis
Atypical projects�-Checked Baggage
Lead abatement
Meterwide tunnel replacement - PVD
Meter wide tunnel replacement
PIT Gantry Bearing Replacement
International�Support
Panama
Panama (cont.)
Mexico