TECH LIBRARY 5-HPGSA-PV-230-VTE-20210121.pdf

PDF 505 KB Posted

Attached to
Launch Operations Support Contract (LOSC) Request for Proposal (RFP) – FINAL Federal contract opportunity
Solicitation number
FA4610-22-R-0001
Issued by
Department of the Air Force Space Command

About this file

This document includes a request for proposal for a Launch Operations Support Contract along with related technical files. The 30th Space Wing at Vandenberg Air Force Base is soliciting proposals to provide facilities support services for launch operations. Interested offerors must submit their responses by January 27, 2022. The North American Industry Classification System code for this effort is 561210 for facilities support services, with a small business size standard of $41.5 million. The performance work statement and appendices provide additional details on required services and property. Questions are due by January 4, 2022 with contract award dates and pricing terms to be determined. The solicitation includes standard forms, security requirements, and Department of Labor wage determinations for applicable service employees.

View the file

Other files for this federal contract opportunity

Other files attached to Launch Operations Support Contract (LOSC) Request for Proposal (RFP) – FINAL, newest first.
File Type Posted
Solicitation Amendment FA461022R00010005 SF 30.pdf PDF
RFP Amendment 0003 Conf SF33 - FA461022R00010003.pdf PDF
L-4_Section L dtd 19Nov21_Revised_18Jan2022.pdf PDF
Atch 2_Appendix A_Property and Equipment Responibility List_Final_6Jan2022.xlsx XLSX spreadsheet
Atch 7 DB WD CA20210018_Mod 28_20211203_12Jan2022.pdf PDF
Atch 10 SCA WD 1986-0431 Rev 54_20210219_12Jan2022.pdf PDF
Atch 11 CBA-2019-12949_12Jan2022.pdf PDF
L-4_Section L dtd 19Nov21_Revised_10Jan2022.pdf PDF
Solicitation Amendment FA461022R00010001_20220112(S).pdf PDF
TECH LIBRARY 0 List of documents_Tech Ref Library_07Jan2022.pdf PDF
L-1_Contractor Staffing Plan and Matrix_Final_9Dec2021.xlsx XLSX spreadsheet
L-3 _OCI_MitigationPlanChecklist_Final_9Dec2021.pdf PDF
L-4_Section L dtd 19Nov21_Final_9Dec2021.pdf PDF
Atch 2_Appendix C_D_E_F_Final_9Dec2021.pdf PDF
Atch 2_Appendix H_Acronyms and Abbreviations_Final_9Dec2021.pdf PDF
Atch 3_LOSC_GFP Attachment (cover page)_9Dec2021.docx DOCX document
Atch 8 SCA WD 2015-5637_Rev 19_20211020.pdf PDF
Exhibit A_CDRL_A004_Power Plant Operation and Maintenance Report_Final_9Dec2021.pdf PDF
Exhibit A_CDRL_A008_P-E Responsibility List_Final_9Dec2021.pdf PDF
Exhibit A_CDRL_A018_Contract Work Breakdown Structure_Final_9Dec2021.pdf PDF
TECH LIBRARY 0 List of documents Tech Ref Library_09DEC21.pdf PDF
TECH LIBRARY 1 SVPP Supplier Manuals Rockwell 1756-um540_-en-p 1756-IRT8I.pdf PDF
TECH LIBRARY 1 Func Desc Instrux - HMI - ACGAL020S000003_B.pdf PDF
TECH LIBRARY 1 SVPP Supplier Manuals Rockwell 1756-IB32 Contact Input Module.pdf PDF
TECH LIBRARY 1 SVPP Supplier Manuals EthosEnergy Customer Support Services.pdf PDF
TECH LIBRARY 1 SVPP Supplier Manuals Axiomatic corrected current-converter.pdf PDF
TECH LIBRARY 3-8310-PV-182-VTE-20210225.pdf PDF
TECH LIBRARY 12-Pillar Point Outfall Storm Drain Inspection Checklist example.pdf PDF
TECH LIBRARY 13-CDRL_A004_Power_example.pdf PDF
TECH LIBRARY 13-CDRL_A015_Solid Waste Report_example.pdf PDF
Solicitation - FA461022R0001_20211209.pdf PDF
L-2_SubcontractTeamingPartnerConsent_Final_9Dec2021.pdf PDF
Atch 2_Appendix B_Antenna Tower Responibility List_Final_9Dec2021.pdf PDF
Atch 2_Appendix G_Environmental Requirements_Final_9Dec2021.pdf PDF
Atch 2_Appendix J_Contract Data Requiremetns List (CDRL) Deliverables_Final_9Dec2021.pdf PDF
Atch 3_LOSC_GFP Attachment_9Dec2021.pdf PDF
Atch 7 DB WD CA20210018_Mod 28_20211203.pdf PDF
Atch 11 2019-2024 CBA_Redacted_w_Appendix A.pdf PDF
Atch 11 CBA-2019-12949.pdf PDF
Atch 12 DB WD CA20210014_Mod 14_20211029.pdf PDF
Exhibit A_CDRL_A001_Corrosion Prevention and Control Plan_Final_9Dec2021.pdf PDF
Exhibit A_CDRL_A006_Technical Report Waster Water Discharge_Final_9Dec2021.pdf PDF
Exhibit A_CDRL_A009_Program Management Plan_Final_9Dec2021.pdf PDF
Exhibit A_CDRL_A015_Solid Waste Report_Final_9Dec2021.pdf PDF
Exhibit A_CDRL_A016_HMMP Report_Final_9Dec2021.pdf PDF
Exhibit A_CDRL_A019_Cost Peformance Report_Final_9Dec2021.pdf PDF
Exhibit A_CDRL_A021_JOCAS Reports_Final_9Dec2021.pdf PDF
Exhibit A_CDRL_A023_RCM Plan_Final_9Dec2021.pdf PDF
Exhibit A_CDRL_A024_Work Order Status Report_Final_9Dec2021.pdf PDF
Exhibit A_CDRL_A026_System Safety Program Plan_Final_9Dec2021.pdf PDF
Show all 50

Launch Operations Support Contract (LOSC) Request for Proposal (RFP) – FINAL has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LOSC ISI Program

CHI-PV-230-VTE-2021

Bld. Number

N/A

A/R/F/O

Acceptable

Acceptable

Other

Acceptable

N/A

Acceptable

A/R/F/O

Acceptable

Acceptable

Acceptable

Acceptable

Acceptable

Acceptable

A/R/F/O

Other

Acceptable

N/A

N/A

Drain

Other No Comments

No Comments

Evidence of Leakage

Dents/Deformations

Insulation/CUI

Paint

Condition of Shell No Comments

Comments

No Comments

Welds

Head to Shell Welds

No Comments

Areas of minor corrosion

No Comments

No Comments

No Comments

No Comments

No CommentsGrayloc Connection

Skirt/Band Welds

Additional Component Welds

Bolts/Flanges

No Comments

No Comments

Comments

Leak detected at bottom nozzle flange connection (dissimilar metals)

Attachments

Longitudinal Weld(s)

Nozzle Welds

Support/Saddle Welds

The vessel was located at the High Pressure Gas Storage Area (HPGSA) on SLC-4. Access must be set up in advance with the facility operator, Space X.

Previous Inspection Documentation

Manufacturer & Year Built

Taylor Forge

Inspector/Level

Brett Strickland / II

Client

Call Henry Inc.

National Board Number

N/A

MAWP Temp. Range

6,000 PSI

Vessel ID

Location/Area

SLC-4/HPGSA

Commodity

Gaseous Nitrogen

Required Equipment

Exterior Pressure Vessel Inspection Report Number: CHI-PV-230-VTE-2021

Leak detected at bottom nozzle flange connection

No Comments

Date

1/21/2021

Serial Number

750400-1V8

PV-230

Vessel Type

Horizontal Pressure Vessel

Exam Type

External

Ladder, flashlight, mirror, bubble leak, picks, hammer, ruler, camera

Condition of Heads

Room Number

-25 to 140 °F

VTE: 2020

GP-R-142002 (2010)

Access Notes

Vessel Inspection

CommentsPrimary

N/A

A/R/F/O

Acceptable

Acceptable

Acceptable

Acceptable

N/A

Acceptable

Acceptable

N/A

N/A

N/A

N/A

A/R/F/O

Acceptable

N/A

N/A

Other

Acceptable

N/A

Inspection Findings/Code Violations

No Comments

No Comments

Additional Notes/Recommendations

Parties are exploring the option of constructing a new panel to eliminate the leaks, updates will be available upon request. The leak should be monitored for any increase in severity until corrective action is taken. Both relief valves are due for calibration and are to be replaced with calibrated relief valves as part of schedule work to the system. The vessel isolation valve has areas of moderate corrosion. This item should be addressed before the corrosion impacts the function of the valve.

Other

There was a slight offset in the foundation concrete (1.25"-1.5"). It is recommended that this continue to be monitored.

There was not notable change in the offset severity. The relief valves were missing system reference designators. This is a violation of AFSPCMAN 91-710 LOSC Tailored 11.2.1.7.6.7. The vessel had dissimilar metals on the flange head. It could not be determined if the dissimilar metals were properly isolated as they were painted over. It is recommended that this area continued to be monitored for signs of accelerated corrosion. There was a minor leak at the bottom nozzle flange connection. The leak should be monitored for any increase in severity until corrective action is taken. There was no notable increase in severity.

Comments

No Comments

No Comments

No Comments

Vessel Inspection Cont. Vessel SN: 750400-1V8

Releif valves planned to be changed out

Comments

No Comments

No Comments

No Comments

Gauges

Sensors/Transducer

Sight Glass/Liquid Level

Relief Valve

Grounding

Anchor Bolting

Saddle/Steel Support Structure

Supports

Platforms

Grating

Handrails/Kickplates

Auxiliary Equipment

Pedestal/Grouting

Concrete Pad

Foundation

Containment

Ladders/Stairs

No Comments

No Comments

1.5" offset in foundation

No Comments

No Comments

No Comments

No Comments

No Comments

Skirts/Bands

Area Overview Vessel Overview

Nameplate Pressure Gauges/Relief Valves

External Pressure Vessel Inspection

External Photographs Vessel SN: 750400-1V8

Dissimilar Metals Leak at Drain Flange

External Pressure Vessel Inspection

External Photographs Vessel SN: 750400-1V8

Offset Foundation Minor Corrosion

File details come from the government source that posted it. Updated .