Specifications_FINAL SUBMISSION_04-09-2020.pdf
PDF 25 MB Posted
- Attached to
- NCTCS Cutler Electrical Ductbank Relocation Federal contract opportunity
- Solicitation number
- N4008521B2512
About this file
This federal contract opportunity solicitation requests proposals for electrical ductbank relocation work at the NCTAMS LANT DET CUTLER facility in Cutler, Maine. The solicitation includes a base bid and four options. The base bid involves relocating an electric ductbank from Building 103 to Building 100. Option 1 deletes this ductbank and instead constructs a new six-way ductbank. Option 2 deletes it and constructs a two-way ductbank instead. Option 3 involves milling and overlaying the road between Buildings 100 and 103. Option 4 extends fiber optic work. All work must comply with project specifications as well as local, state and federal codes. The solicitation was issued by the Department of the Navy Naval Facilities Engineering Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Abstract N4008521B2512.pdf | ||
| Amendment 0005.pdf | ||
| CX101 - Relabel base bid note 1.pdf | ||
| Amendment 004.pdf | ||
| Amendment 003.pdf | ||
| PPI RESPONSE PART 2_8-6-21.pdf | ||
| SV Sign-In Sheet_21B2512.pdf | ||
| Amendment 0002.pdf | ||
| PPI RESPONSE PART 1_8-4-21.pdf | ||
| Amendment 0001.pdf | ||
| N4008521B2512 - Solicitation Document.pdf | ||
| 1583439_Drawings.pdf | ||
| 09-eOMSI WORKBOOK REV 6_MASTER - Ductbank.pdf | ||
| SECNAV 5512-1.pdf | ||
| Final Site4ROD.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTROLLED
DISTRIBUTION STATEMENT F. Further dissemination only as directed by Portsmouth Naval Shipyard, NAVFAC (December 3, 2018) or higher DoD authority.
NAVFAC MIDLANT, Public Works Department, Maine
WORK ORDER NO.
N40080-FY-eProjects WO #1583439
SPECIFICATION
NCTCS Cutler Electrical Ductbank Relocation
At the
NCTAMS LANT DET Cutler Cutler, Maine
PREPARED BY:
NAVFAC Midlant PWD ME Building 59
Portsmouth Naval Shipyard Kittery, Maine 03801-2032
REQUEST FOR PROPOSAL PREPARED BY:
Architectural: Jeffrey B. Luy, AIA Electrical: Dale C. Lincoln, II, P.E.
Civil: Jacques L. Gagnon, Jr., P.E. Fire Protection: N/A Structural: N/A Environmental: N/A Mechanical: N/A Estimating: Oak Point Associates
Peter F. Dunn, P.E.
Submitted By: Peter F. Dunn, P.E. Signature Date: April 9, 2020
Jeff Hoyt, P.E.
Approved By PME Signature Date:
Gregory W. Haggstrom Design Manager: Signature Date:
NCTCS CUTLER ELECTRICAL DUCTBANK RELOCATION 1583439
CUTLER, MAINE
PROJECT TABLE OF CONTENTS
DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS
00 01 15 LIST OF DRAWINGS
00 41 00 BID SCHEDULES
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 SUMMARY OF WORK
01 14 00.00 20 WORK RESTRICTIONS (PWD ME) (AOR)
01 20 00.00 20 PRICE AND PAYMENT PROCEDURES (PWD ME)
01 30 00 ADMINISTRATIVE REQUIREMENTS (PWD ME)
01 31 23.13 21 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT
MANAGEMENT SYSTEM
01 32 16.00 22 CONSTRUCTION PROGRESS SCHEDULES (PWD ME)
01 33 00 SUBMITTAL PROCEDURES
01 35 26.00 22 GOVERNMENT SAFETY REQUIREMENTS (PWD ME)
01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR
CONTAMINATED SITES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 20 QUALITY CONTROL (PWD ME)
01 50 00.00 22 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS (PWD ME)
01 57 19.00 20 TEMPORARY ENVIRONMENTAL CONTROLS (AOR)
01 74 19.00 22 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT (PWD ME)
01 78 00.00 22 CLOSEOUT SUBMITTALS (PWD ME)
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 24.00 22 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT
INFORMATION (eOMSI)
01 91 13 GENERAL COMMISSIONING REQUIREMENTS (PWD ME)
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 DEMOLITION
02 83 13.00 20 LEAD IN CONSTRUCTION (PWD ME AOR)
DI VI SI ON 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 13 53 ELASTOMERIC SHEET WATERPROOFING
07 84 00 FIRESTOPPING
DI VI SI ON 09 - FI NI SHES
09 90 00 PAINTS AND COATINGS
DI VI SI ON 26 - ELECTRI CAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 13.00 40 MEDIUM-VOLTAGE CABLES
26 08 00 APPARATUS INSPECTION AND TESTING
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 23 00.01 5 KV METAL-CLAD SWITCHGEAR
DI VI SI ON 27 - COMMUNI CATI ONS
PROJECT TABLE OF CONTENTS Page 1
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DI VI SI ON 31 - EARTHWORK
31 11 00 CLEARING AND GRUBBING
31 23 00.00 20 EXCAVATION AND FILL (CUTLER)
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 01 16.71 COLD MILLING ASPHALT PAVING
32 01 17.61 SEALING CRACKS IN ASPHALT PAVING
32 05 33 LANDSCAPE ESTABLISHMENT
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 17 23 PAVEMENT MARKINGS
32 92 19 SEEDING
DI VI SI ON 33 - UTI LI TI ES
33 40 00 STORM DRAINAGE UTILITIES
33 46 16 SUBDRAINAGE PIPING
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/11
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
DRAWING NAVFAC PWD ME
NO. DWG NO. DWG NO. TITLE
G-001 12811782 LF-20-667 COVER SHEET
G-002 12811783 LF-20-668 DATA SHEET
C-001 12811784 LF-20-669 CIVIL NOTES, LEGEND AND ABBREVIATIONS
CX101 12811785 LF-20-670 OVERALL EXISTING SITE PLAN
C-101 12811786 LF-20-671 ELEC DUCTBANK PLAN AND PROFILE STA 0+00 TO
8+00
C-102 12811787 LF-20-672 ELEC DUCTBANK PLAN AND PROFILE STA 8+00 TO
16+00
C-103 12811788 LF-20-673 ELEC DUCTBANK PLAN AND PROFILE STA 16+00 TO
23+00
C-104 12811789 LF-20-674 ELEC DUCTBANK PLAN AND PROFILE STA 23+00 TO
28+99.55
C-501 12811790 LF-20-675 EROSION AND SEDIMENTATION CONTROL NOTES AND
DETAILS
C-502 12811791 LF-20-676 SITE DETAILS-1
C-503 12811792 LF-20-677 SITE DETAILS-2
C-504 12811793 LF-20-678 SITE DETAILS-3
C-505 12811794 LF-20-679 B103 ENLARGED SITE PLAN
C-506 12811795 LF-20-680 B103 CONDUIT ENTRANCE DETAILS
C-507 12811796 LF-20-681 B100 ENLARGED SITE PLAN AND DETAILS
C-508 12811797 LF-20-682 B100 ENLARGED SITE PLAN AND DETAILS -
OPTIONS 1 AND 2
B-001 12811798 LF-20-683 SOIL TEST BORING LOGS-1
B-002 12811799 LF-20-684 SOIL TEST BORING LOGS-2
B-003 12811800 LF-20-685 SOIL TEST BORING LOGS-3
E-001 12811801 LF-20-686 ELECTRICAL SYMBOLS, ABBREVIATIONS AND
GENERAL NOTES
ED101 12811802 LF-20-687 B103 ELECTRICAL REMOVALS PLAN
E-101 12811803 LF-20-688 B103 ELECTRICAL PLAN
E-102 12811804 LF-20-689 B100 ELECTRICAL PLAN
E-201 12811805 LF-20-690 B103 ELECTRICAL ELEVATIONS AND PHOTOS
E-301 12811806 LF-20-691 B100 ELECTRICAL BUILDING SECTION AND PHOTOS
E-501 12811807 LF-20-692 POWER ONE-LINE DIAGRAM
ET501 12811808 LF-20-693 TECHNOLOGY ONE-LINE DIAGRAMS
-- End of Document --
DOCUMENT 00 01 15 Page 1
CUTLER, ME
DOCUMENT 00 41 00 Page 1
DOCUMENT 00 41 00
BID SCHEDULES
01/07
PART 1 GENERAL
1.1 BASIS OF BIDS
1. A minimum bid guarantee is required to be submitted with offer and shall be 20 percent of the aggregate amount of Items 0001 through 0005, or $3,000,000.00 whichever is less.
2. Payment and Performance Bonds will be required within 10 days of contract award. Payment and Performance bonds will be required for the base bid item 0001, however, if option Items 0002, 0003, 0004, and 0005 are exercised, additional bonding and consent of surety will be required. Consequently, the Performance Bond shall reflect 100 percent of the aggregate amount of Items 0001 through 0005. Payment Bonds shall reflect 100 percent of the aggregate amount of Items 0001 through 0005.
1.1.1 Unit Prices
This contract will be solicited with unit prices to be applied to estimated quantities for selected work. A description of the items and schedule of the unit price work is contained below. See Contract Clauses, “FAR 52.211- 18, Variation in Estimated Quantity” and “FAR 52.236-16, Quantity Surveys.”
Unit Prices Form
Item Description Quantity Unit Unit Price
0001a Rock Excavation. 1,025 CY $________
0001b Crack seal existing asphalt pavement after milling. 1,878 LF $________
0001c Remove and reinstall 1-inch rigid metallic conduit, include 2 elbows. 100 LF $ _______
0001d Remove and reinstall 1-1/2-inch rigid metallic conduit, include 2 elbows. 100 LF $ _______
0001e Remove and reinstall 2-inch rigid metallic conduit, include 4 elbows. 200 LF $ _______
0001f Remove and reinstall 4-inch rigid metallic conduit, include 4 elbows. 200 LF $ _______
0001g Remove and reinstall 6”x12” cable tray. 100 LF $ _______
0001h Remove and reinstall 6”x9” cable tray. 100 LF $ _______
0001i
Disconnect, remove, reinstall (in 4-inch conduit) and reconnect four (4) single #500 KCMIL conductors + #3G conductor.
(each conductor)
LF $ _______
DOCUMENT 00 41 00 Page 2
Item Description Quantity Unit Unit Price
0001j
Disconnect, remove, reinstall (in 2-inch conduit) and reconnect four (4) single #3/0 conductors + #6G conductor.
(each conductor)
LF $ _______
0001k
Disconnect, remove, reinstall (in 1- 1/2-inch conduit) and reconnect four
(4) single #1 conductors + #8G conductor.
(each conductor)
LF $ _______
0001l Disconnect, remove, reinstall (in 1-inch conduit) and reconnect four (4) single #6 conductors + #10G conductor.
(each conductor)
0001m
Provide 1-inch rigid metallic conduit and connect to existing conduit, include 1 elbow.
50 LF $ _______
0001n Provide 1-1/2-inch rigid metallic conduit and connect to existing conduit, include 1 elbow.
50 LF $ _______
0001o Provide 2-inch rigid metallic conduit and connect to existing conduit, include 1 elbow.
50 LF $ _______
0001p Provide 4-inch rigid metallic conduit and connect to existing conduit, include 1 elbow.
50 LF $ _______
0001q Provide 6”x12” cable tray and connect to existing tray.
0001r Provide 6”x9” cable tray and connect to existing tray.
50 LF $ _______
0001s
Provide four (4) single #500 KCMIL conductors + #3G conductor (in 4-inch conduit) and connect to existing conductors.
(each conductor)
LF $ _______
0001t Provide four(4) single #3/0 conductors + #6G conductor (in 2-inch conduit) and connect to existing conductors.
(each conductor)
LF $ _______
0001u
Provide four (4) single #1 conductors + #8G conductor (in 1-1/2-inch conduit) and connect to existing conductors.
(each conductor)
LF
0001v Provide four (4) single #6 conductors + #10G conductor (in 1-inch conduit) and connect to existing conductors.
(each conductor)
Note:
1. The unit prices provided shall be the same dollar amount for both adding and deducting quantities of the items.
DOCUMENT 00 41 00 Page 3
1.1.2 Bid Schedule
This contract will be awarded as one lump sum with Options as required for specifically selected work.
Bid Schedule
Basis of Bid for Item 0001 (Base Bid) shall be the Total Amount for Item 0001 (Item 000101), complete in accordance with the drawings and specifications, but not including the work indicated or specified to be provided under Option Items 0002, 0003, 0004, and 0005.
Item Description Estimated
Quantity Unit Unit
Price Amount
000101
Construct an electric and communications ductbank, associated manholes, and electric and communications conductors from B103 to B100 and between B100, existing Manhole #2W, existing Manhole Vault N1A, and existing Tunnel, including work also within B100 and B103.
1 LS XXX $______
Total Amount for Item 0001 $______
1.1.3 Options
This contract will be solicited with options. A description of the options is contained in Standard Form 1442, “Solicitation, Offer and Award.”
Option Schedule
Options, Items 0002, 0003, 0004, and 0005, may be exercised at the time of award or within 120 calendar days after award by the Contracting Officer. A firm fixed bid price is required for each option. No provision is made for economic price adjustment. Method for evaluation of bids for award purposes is specified below.
Basis of Bid for each item shall be the addition and/or deletion of the full scope of work complete. If any or all Options are exercised, the contract completion date remains the same.
Item Description Estimated Quantity Unit Unit
Price Amount
Option 1: Delete Ductbank, exterior and interior conduit and conductors from MH 1W-2019 to existing B100 transmitter power switchgear A1 and B1 and construct 6 way underground electric ductbank and conductors from MH1W-2019 to existing MH 1W. Provide conductors to existing B100 to transmitter power switchgear A1 and B1.
1 LS XXX $_________
DOCUMENT 00 41 00 Page 4
Item Description Estimated Quantity Unit Unit
Price Amount
Option 2: Delete Ductbank, exterior and interior conduit and conductors from MH 1W-2019 to existing B100 house power switchgear A1 and B1 and construct 2-way underground electric ductbank and conductors from MH1W-2019 to existing MH 1W. Provide conductors to existing B100 house power switchgear A1 and B1.
1 LS XXX $_________
Option 3: Remove two existing culverts and provide two culverts at stations 8+67± and 16+45±. Mill and overlay both lanes of pavement at Ridge Road between B103 and B100.
Pavement shall be removed by milling. Cracks remaining after the milling shall be sealed and the roadways shall receive an overlay with new pavement markings (includes Unit Price Item 0001b in Paragraph 1.1.1).
1 LS XXX $_________
Option 4: Extend fiber optic cable from P-308 termination point in B103 to inside B100.
1 LS XXX $_________
1.1.4 Explanation of Base Bid
The Total Amount for Item 0001 shall provide the full project scope, excluding Options, complete and in place in accordance with the drawings and specifications even if not specifically listed below.
The Basis of Item 0001 is as follows:
000101: Includes the price for all work associated with constructing an electric and communications ductbank, associated manholes, and providing electric and communications conductors from B103 to B100 and between B100 and existing Manhole #2W, and associated miscellaneous work required, including within B100 and B103.
The Basis of Bid for each Option is subdivided as follows:
0002 Option 1: Delete Ductbank, exterior and interior conduit and conductors from MH 1W-2019 to existing B100 transmitter power switchgear A1 and B1 and construct 6 way underground electric ductbank and conductors from MH1W-2019 to existing MH 1W. Provide conductors to existing B100 to transmitter power switchgear A1 and B1.
DOCUMENT 00 41 00 Page 5
0003 Option 2: Delete Ductbank, exterior and interior conduit and conductors from MH 1W-2019 to existing B100 house power switchgear A1 and B1 and construct 2 way underground electric ductbank and conductors from MH1W-2019 to existing MH 1W. Provide conductors to existing B100 house power switchgear A1 and B1.
0004 Option 3: Remove two existing culverts and provide two culverts at stations 8+67± and 16+45±. Mill and overlay both lanes of pavement at Ridge Road between B103 and B100. Pavement shall be removed by milling. Cracks remaining after the milling shall be sealed and the roadways shall receive an overlay with new pavement markings.
0005 Option 4: Extend fiber optic cable from P-308 termination point in
B103 to inside B100.
-- End of Document --
SECTION 01 11 00
SUMMARY OF WORK
08/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E2114 (2008) Standard Terminology for Sustainability Relative to the Performance of Buildings
1.2 DEFINITIONS
Definitions pertaining to sustainable development are as defined in ASTM E2114 and as specified.
a. "Environmentally preferable products" have a lesser or reduced effect on the environment in comparison to conventional products and services. This comparison may consider raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product.
b. "Indoor environmental quality" is the physical characteristics of the building interior that impact occupants, including air quality, illumination, acoustics, occupant control, thermal comfort, daylighting, and views.
c. "Operational performance" is the functional behavior of the building as a whole or of the building components.
d. "Sustainability" is the balance of environmental, economic, and societal considerations.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Work Sequencing, Phasing, and Preparation Plan ; G
1.4 WORK COVERED BY CONTRACT DOCUMENTS
1.4.1 Project Description
The work includes the following and incidental related work:
SECTION 01 11 00 Page 1
Base Bid -
Base Bid scope of work includes:
a. Construct an electric and communications ductbank and associated manholes from B103 to MH 1W-2019.
b. Construct an electrical ductbank between MH 1W-2019 and existing Manhole 1W (for Helix House power).
c. Construct ductbanks between MH 1W-2019 and B100 (for house and transmitter power).
d. Construct de-icing power ductbank from MH 10W-2019 t MH 3W-2019.
e. Provide electric feeders and communications cables within conduit from B103 to B100 and between B100 and existing Manhole #2W.
f. The conductors within the existing electrical and communications ductbanks that are being abandoned shall be either abandoned in place or removed at the Contractor's option. The existing ductbank to be abandoned in place between B103 and B100 shall be cut and capped adjacent to B103 and adjacent to existing Manhole #2W.
g. Attempt to provide new transmitter power feeders from existing electric manhole 1W to the two existing B100 transmitter switchgear cabinets (A1 and B1) utilizing the existing 6-way ductbank beneath the building floor slab.
h. Attempt to provide new house power feeders from existing electric manhole 1W to the existing two B100 house power switchgear cabinets (A1 and B1) utilizing the existing 2-way ductbank beneath the building floor slab.
i. Remove brush and sediment build-up at the culvert entrances and exits at Ridge Road, provide rip-rap inlets and outlets.
j. Provide System Operational Verification Test (SOVT) for equipment and systems affected by this project. This includes Power Distribution, Communications, De-icing Control, and Fire Alarm Systems. Provide as specified in Section 01 91 13 GENERAL COMMISSIONING REQUIREMENTS
(PWD ME).
k. Incidental related work.
Project Options include:
Option 1: Delete Ductbank, exterior and interior conduit and conductors from MH 1W-2019 to existing B100 transmitter power switchgear A1 and B1 and construct 6 way underground electric ductbank and conductors from MH1W-2019 to existing MH 1W. Provide conductors to existing B100 to transmitter power switchgear A1 and B1.
Option 2: Delete Ductbank, exterior and interior conduit and conductors from MH 1W-2019 to existing B100 house power switchgear A1 and B1 and construct 2 way underground electric ductbank and conductors from MH1W-2019 to existing MH 1W. Provide conductors to existing B100 house power switchgear A1 and B1.
SECTION 01 11 00 Page 2
Option 3: Remove two existing culverts and provide two culverts at stations 8+67± and 16+45±. Mill and overlay both lanes of pavement at Ridge Road between B103 and B100. Pavement shall be removed by milling.
Cracks remaining after the milling shall be sealed and the roadways shall receive an overlay with new pavement markings.
Option 4: Extend fiber optic cable from P-308 termination point in B103 to inside B100.
1.4.2 Location
The work shall be located at the NCTAMS LANT DET CUTLER, Cutler, Maine, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.5 PROJECT SEQUENCING REQUIREMENTS
Provide Work Sequencing, Phasing, and Preparation Plan indicating how the work is to be accomplished and incorporating Government directives and restrictions specified in Section 01 14 00.00 20 WORK RESTRICTIONS (PWD ME) (AOR). The intent of this Plan is for the Contractor to show the Government that a complete understanding of the project requirements are understood by the Contractor and his/her subcontractors. The Plan shall be carefully prepared and shall include every aspect of the project and how it is to be accomplished with an absolute minimum of disruption to Government operations on the NCTAMS LANT DET CUTLER. No work may begin on the project until this plan is reviewed and approved by the Government.
Coordinate this plan with the Demolition/Deconstruction Plan specified in Section 02 41 00 DEMOLITION AND DECONSTRUCTION.
Phasing plan shall incorporate the following requirements:
Phasing is necessary to reduce outage times and ensure uninterrupted service to the Transmitter Building, Helix Houses and antenna array.
Downtime and cutover phasing work will need to be closely coordinated with NCTAMS. The following construction sequence is anticipated:
Electric Service Once the new electric ductbanks are complete, provide power feeders ready for final connections. Outages and final connections must be made only at times approved by the Contracting Officer's Representative. Each outage shall last no longer than one 8-hour working day, and be scheduled to coincide with regularly scheduled "down days" (one day per week, typically Mondays). It is anticipated that the work required to connect to the existing switchgear in B103 for B100 house power will take longer than one day. The Contractor shall provide a temporary generator to provide power.
Communication Service Construct ductbank between B103 and existing MH 1W. Install new communication cables ready for final connection. Outages and final connections must be made only at times approved by the contracting officer. Each outage shall last no longer than one day.
1.6 PROJECT ENVIRONMENTAL GOALS
Contractor shall distribute copies of the Environmental Goals to each subcontractor and the Contracting Officer. The overall goal for design, construction, and operation is to produce a building that meets the
SECTION 01 11 00 Page 3 functional program needs and incorporates the principles of sustainability. Specifically:
a. Perform work and utilize equipment, materials and procedures to minimize environmental impact.
b. Preserve and restore the site ecosystem and biodiversity; avoid site degradation and erosion. Minimize offsite environmental impact.
c. Use the minimum amount of energy, water, and materials feasible to meet the design intent. Select energy and water efficient equipment and strategies.
d. Use environmentally preferable products and decrease toxicity level of materials used.
e. Use renewable energy and material resources.
f. Manage construction site and storage of materials to ensure no negative impact on the indoor environmental quality of the building and adjacent facilities.
g. Reduce construction waste through reuse, recycling, and supplier take-back.
1.7 OCCUPANCY OF PREMISES
Adjacent facilities will be occupied and operational during performance of work under this Contract.
Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.8 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.9 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation by contacting the Contracting Officer 15 calendar days in advance . Scan the construction site and floor and roof structures as applicable with Ground Penetrating Radar and electromagnetic or sonic equipment, and mark the surface of the ground, paved surface, and floor and roof structures as applicable where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to
SECTION 01 11 00 Page 4 be conducted or installed.
1.9.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work. Contact Dig Safe 48 hours prior to excavating.
Contractor is responsible for marking all utilities not marked by Dig Safe.
1.10 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged shall remain the property of the Government.
The salvaged property shall be segregated, itemized, delivered, and off-loaded at the Government designated storage area located within 10 miles of the construction site.
Contractor shall maintain property control records for material or equipment designated as salvage. Contractor's system of property control may be used if approved by the Contracting Officer. Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 5
SECTION 01 14 00.00 20
WORK RESTRICTIONS (PWD ME) (AOR)
04/17
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 241 (2009) Standard for Safeguarding Construction, Alteration, and Demolition Operations
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel ; G
Vehicle List ; G
1.3 SPECIAL SCHEDULING REQUIREMENTS
a. During the implementation of the project, if differing site conditions are encountered that generate an RFI which requires technical review by the DOR and the Government for the electrical design, a minimum of 7 working days will be required to provide the vetted response. The Contractor shall include this requirement in his/her project schedule.
b. A minimum 3-week notice to the Contracting Officer's Representative is required for a driveway outage (both B100 and B103).
c. The VLF Facility site will remain in operation during the entire construction period. The Contractor shall conduct his/her operations so as to cause the least possible interference with normal operations of the Activity.
d. During the entire construction period for this project, other construction projects and maintenance activities will be occurring on the Activity. The Contractor shall coordinate the work of this contract with the other projects and maintenance activities.
SECTION 01 14 00.00 20 Page 1
e. Permission to interrupt any Activity roads and/or utility services shall be submitted to the Contracting Officer in writing a minimum of 15 calendar days prior to the desired date of interruption.
f. Coordinate the work with the sequencing/phasing requirements outlined in Section 01 11 00 SUMMARY OF WORK. The project must be phased to limit power and communication outages to the periods of time as indicated and as directed.
g. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work. Specific items of work to which this requirement applies include:
(1) Environmental protection components.
(2) Work within B100.
(3) Work within B103.
(4) Work within existing ductbanks.
h. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations.
Identify on the construction schedule each factor which constitutes a potential interruption to operations.
The following conditions apply:
(1) VLF signal transmission operations.
(2) Work in certain areas, as indicated on Drawings, will be subject to increased restriction. Work in these areas will be allowed for approximately one 8-hour period, once each week, during scheduled 'down days'. Down days may be cancelled or extended as directed by the Contracting Officer.
(3) Coordination with Activity operations.
(4) Coordination with other construction projects on the Activity.
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations. Keep within the limits of the work and avenues of ingress and egress. Do not enter restricted areas unless required to do so and until cleared for such entry.
All Contractors' equipment shall be conspicuously marked with company signage for identification.
1.4.1 Subcontractors and Personnel Contacts
Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
SECTION 01 14 00.00 20 Page 2
1.4.2 Vehicle List
Submit an original list of vehicles to be utilized at the work site with the following information for each vehicle:
a. Make
b. Year
c. Model
d. License number
e. Registered owner
f. Current Base pass expiration date (if applicable).
1.4.3 Identification Badges and Installation Access
a. Application for and use of badges will be as directed. Obtain access to the installation by submitting the Northern Sites Access Request Form ALF 103 (Attachment A) a minimum of 7 working days in advance for vetting and approval, or by obtaining passes each day from the Activity's Pass and Identification/Security Office.
One-day passes, issued through the Station's Pass and Identification Office, will be furnished without charge. Report any instances of lost or stolen badges to the Contracting Officer immediately.
b. All Contractors who possess a Commercial Access Control (CAC) System Card are required to present a second form of valid ID to the Gate Sentry, if requested, upon arrival at the Installation's Entrance Gate.
All Contractor personnel without CAC cards will need two forms of approved identification for access to the Installation.
See Attachment B for the list of acceptable identification documents.
c. One-Day Passes: Participation in the vetting process is not mandatory, and if the Contractor chooses to not participate in the vetting process, the Contractor's personnel will have to obtain daily passes, be subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government will not be responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the vetting process.
1.4.4 Identification Badges and Installation Access (NCTS Cutler)
Contractor shall submit the company name, names of employee's, date of birth, place of birth and contracted period of performance using SECNAV Form 5512-1 (Attachment A) a minimum of 7 working days in advance for vetting and approval. The employees will be placed on an access list for the duration of the contract as requested for up to 365 days. At the end of that time period the Contractor shall resubmit access request information. The Contractor shall follow this procedure each year for the duration of the contract. A picture ID (i.e., driver's license) will be required to enter the facility. State of Maine driver's licenses are not "Real ID" compliant. Refer to OPNAVINST 5530.14E Chapter 12, Table 12-2, SECTION 01 14 00.00 20 Page 3 for a list of acceptable forms of ID for Base access (refer to Attached A). All vehicles are required to have current registration, inspection and insurance. Refer to Attachment A for Access Request Form. For concerns regarding access contact the Base Police at 207-259-8267.
Submit to:
Burnett, Richard M CIV NAVFAC MIDLANT, PWD Maine (richard.m.burnett@navy.mil) O: 207-259-8347 F: 207-259-8205
Maker, Seth R CIV NAVFAC MIDLANT, PWD Maine (mailto: Seth.maker@navy.mil) Seth Maker, EIT Construction Manager NAVFAC MIDLANT, PWD Maine Cutler Field Office O: 207-259-8301 C: 207-317-2674
1.4.5 Contractor Daily Check-In
Contractors must report to the NCTAMSLANT DET CUTLER Administration Office for check-in and issue of a building/facility access badge before proceeding to their work site. The contractor must return the access badge to the NCTAMS LANT DET Cutler Administration Office once their work is completed. For contractors that will be working onboard Naval Station Cutler for periods longer than one week, an inventory of the company's employee's access badges must be verified with the NCTAMS LANT DET Cutler Administration Office by COB every Monday.
1.5 ACTIVITY REGULATIONS
1.5.1 Radiological
1.5.1.1 Radioactive Sources
All contracts involving radiation generating devices shall conform to the requirements listed in Section 01 35 26.00 22 GOVERNMENT SAFETY REQUIREMENTS (PWD ME) and U.S. Army Corps of Engineers Safety Manual EM 385-1-1 . All requirements are to be submitted to the Contracting Officer at least 14 days prior to commencement of operations involving radiation generating devices. A requirements checklist will be provided by NAVFAC (COTs) Contractor Oversight Technician and also available on PWD Maine website:
https://www.navfac.navy.mil/navfac_worldwide/atlantic/fecs/ mid-atlantic/pwd_maine/about_us/construction.html
1.5.2 Laser Control
Contractor shall comply with laser safety requirements under 21 CFR 1040 and ANSI 2136.1-1986 for any work under this contract utilizing lasers.
1.5.3 Energy Conservation
In cooperation with Government representatives, the Contractor shall participate in an active program directed toward the efficient use of energy. Government furnished utilities will not be provided for air
SECTION 01 14 00.00 20 Page 4 conditioning of Contractor trailers or office areas.
1.5.4 Fire Prevention
Contractor shall familiarize and require all their employees to become familiar with fire prevention regulations within the Station to include the proper method of turning in a fire alarm, storage of flammable and combustible materials and control of combustible waste and trash. Any HOT WORK (welding, burning, grinding, cutting, etc.) requires a HOT WORK PERMIT prior to commencing such work. This permit is obtained from the Activity's Fire Department via the Contracting Officer.
1.5.5 Pesticide and Herbicide Control
Contractor shall not apply pesticides nor herbicides unless specifically required by this contract. Where application of pesticides or herbicides is required, provide the submittals required by the specification and obtain written approval prior to any application. Contracting Officer will require review and approval of pesticides or herbicides submittals.
1.5.6 Smoking Policy
In accordance with NAVFAC policy, smoking is prohibited inside all buildings and other facilities except those areas specifically identified as smoking areas (e.g., smoking shelters). Smoking is not permitted within 20 feet of air intakes, doorways or windows.
1.6 WORKING HOURS
Regular working hours shall consist of a period established by the Contracting Officer between 7 AM and 3:30 PM, Monday through Friday, excluding Government holidays. The regular working hours shall be confirmed with the Contracting Officer.
1.6.1 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Provide written requests fifteen (15) Calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer.
1.7 WORK IN OCCUPIED BUILDING(S)
Work under this contract may be located in an occupied building. Move unfixed furniture away from Contractor's working area as required to perform the work; protect; and replace in original locations upon completion of the work. Leave fixed equipment in place and protect against damage or temporarily disconnect, relocate, protect, and reinstall at completion of work. If determined necessary by the Contracting Officer, the Government will remove and relocate other Government property in the areas of the buildings scheduled to receive work. Allow 15 calendar days after written notification from the Contractor for the Government to relocate Government property.
1.8 UTILITY CUTOVERS AND INTERRUPTIONS
Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays as approved by the Contracting
SECTION 01 14 00.00 20 Page 5
Officer. Conform to procedures required in the paragraph "Work Outside Regular Hours." Anticipated costs shall be included in the bid.
Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
Interruption to Water, Sanitary Sewer, Storm Sewer, Telephone Service, Electric Service, Air Conditioning, Heating, Fire Alarm, Compressed Air, and other utilities shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours." This time limit includes time for deactivation and reactivation.
Operation of Station Utilities: The Contractor shall not operate nor disturb the setting of control devices in the Station's utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor shall notify the Contracting Officer in writing within 15 calendar days when such operation is required.
1.9 GENERAL RESTRICTIONS
(1) Exterior work shall not be performed when the wind velocity exceeds 35 mph measured at 30 feet above the ground or when thunderstorms or any other violent weather and/or winds of 50 mph or more are predicted. The Contractor shall verify wind speed and weather conditions.
(2) Work will be prohibited any time that operational commitments dictate as directed by the Contracting Officer.
(3) Contractor personnel shall not perform any work unless they have the following minimum equipment:
a. Hard hats
b. Long pants
c. Gloves.
d. Safety shoes
e. Safety glasses
f. Portable radios
g. Appropriate class reflective vests
h. Fall protection
i. Hearing protection
(4) The klaxon for the north or south shall be checked before working in the arrays.
(5) Contractor personnel shall assure that the de-ice breakers located at the Power Plant are locked out.
(6) Work areas shall be kept clear of all debris.
(7) Osprey nests, if encountered, shall not be disturbed. The Contractor shall notify the Contracting Officer. Osprey nests shall be relocated by the Government only between September 1 and April 15.
1.10 SPECIFIC RESTRICTIONS
a. Work required by this project and specific procedures and outages
SECTION 01 14 00.00 20 Page 6 shall be closely coordinated and approved by the Contracting Officer and NCTAMS personnel.
b. Contractor shall limit operations within roadways and driveways so that at least one lane is open at all times. Limit the length of one lane travel to 150 feet at one time.
c. Access drive from Ridge Road to B103 parking area shall not be out of use for longer than 12 hours at a time. Outage times shall be submitted 14 days in advance and shall be coordinated with the Contracting Officer.
d. Outage times for the excavation work in the area within the restricted area at B100 shall be submitted 14 days in advance and shall be coordinated with the Contracting Officer.
e. Excavations within the vicinity of the B100 security fence shall be backfilled to within 2 inches of the bottom of the fence prior to leaving the site each day. Fence shall be secure before leaving each day.
1.11 WORK ADJACENT TO AN OVERHEAD CRANE
Provide a minimum vertical clearance of three (3) inches between the highest point of the crane and the lowest overhead obstruction. For buildings where truss sag becomes a factor, increase the clearance as necessary to maintain the minimum required clearance.
The horizontal clearance between the end of the crane and the building columns, knee braces or any other obstructions shall not be less than two
(2) inches with the crane centered on the runway rails. Pipes, conduits, etc. shall not reduce this clearance.
The vertical clearance beneath a bridge crane is to be at least three (3) inches. This clearance is not applicable to the hook block unless it is in its up most position.
For work involving installation, adjustment, or replacement of rail fasteners (e.g. clips/bolts), the Contractor shall verify the existing crane envelope and clearance measurements around the rail head prior to beginning work. The Contractor shall notify the Government if the work will reduce the clearance between the bridge crane and rail fasteners and ensure newly installed items will not obstruct bridge crane travel.
The Contractor shall notify the Government to verify that crane clearance has been maintained when the work performed may have changed any physical dimensions of objects or structures adjacent to the crane (e.g., changing or servicing lighting fixtures/pendant assemblies, removal and reinstallation of pipes, conduits, junction boxes, etc.). If the crane is not available (e.g., undergoing maintenance, inspection, etc.), the Contractor shall verify crane clearance by taking measurements using reference points (e.g., vertical and horizontal distance from the top of crane rail with respect to the crane envelope, vertical distance from the floor with respect to the crane envelope, etc.).
SECTION 01 14 00.00 20 Page 7
1.12 FIRE PROTECTION
1.12.1 Compliance
The Contractor shall comply with COE EM 385-1-1 , NFPA 241 , Utility and Facility Outages, and Activity's fire regulations. Obtain approval from the Activity's Fire Chief via the Contracting Officer prior to commencement of hot work operations.
1.12.2 Fired Kettles
Melt kettles for tar, asphalt, and similar materials shall not be closer than 25 feet to buildings or combustible materials. The final location of the materials shall be approved by the Activity Fire Department. Provide a minimum of two 20 pound ABC all-purpose type extinguishers at the melting kettle and the area of hot material application. Equip kettles with proper heat controls and means of agitation to assure controlled uniform temperatures throughout contents to prevent spot heating. Do not heat contents above flash point.
1.12.3 Notification of Fire
Post Activity's fire poster in conspicuous locations and at telephones in Contractor trailers.
1.13 SECURITY REQUIREMENTS
1.13.1 General
Contractor employees and representatives performing work under this contract are required to be United States citizens. If naturalized, the individual shall present his naturalization papers to the Security Officer for inspection. Foreign born personnel shall present evidence of citizenship regardless of citizenship of parents, as required by immigration laws.
1.13.2 Application and Issue of Security Badges
"Temporary" Security Badges will be issued to Contractor personnel requiring access for up to two (2) work days upon satisfactory proof of U.S. citizenship, in the form of an original or certified birth certificate, passport, or naturalization papers. A "Real ID" compliant picture ID is required in addition to satisfactory proof of citizenship.
See Attachment B.
"Permanent" (photo) Standard Access Control Badges will be issued to Contractor personnel requiring access for three (3) or more work days.
Contractor personnel will be required to complete an authorization application form for local record check, and a personal information sheet. The forms will be furnished to the Contractor following award of any contract resulting from this solicitation, at time of pre-performance or pre-construction conference.
In the event the Contractor requires access to contract work areas not permitted by the level of security badge issued, such need shall be demonstrated and an escort obtained. The escort shall remain visible to the Contractor at all times within areas requiring escort.
STANDARD ACCESS CONTROL BADGES SHALL BE ATTACHED TO THE OUTER GARMENT AND
SECTION 01 14 00.00 20 Page 8
DISPLAYED AT ALL TIMES WHILE ON THE ACTIVITY.
CONTRACTOR PERSONNEL SHALL NOT ENTER AREAS FOR WHICH THEY HAVE NOT BEEN
CLEARED. WHERE A NEED HAS BEEN DEMONSTRATED TO ENTER SUCH AREAS,
CONTRACTOR SHALL BE UNDER CONSTANT ESCORT BY PERSONNEL WHO HAVE BEEN
CLEARED. FAILURE TO ADHERE TO POSTED SECURITY REQUIREMENTS MAY RESULT IN
REMOVAL OF THE EMPLOYEE FROM THE ACTIVITY WITH FUTURE ACCESS DENIED.
1.13.3 Application and Issue of Crane Passes
Comply with EM 385-1-1 .
1.13.4 Return of Badges and Vehicle Passes
Contractor shall ensure all vehicle access permits and personnel badges are returned to the Security Officer when the need has ended. Contractor shall account in writing for each missing pass or badge prior to final payment being made on the contract.
1.13.5 Contractor Security Responsibilities
Contractor employees shall not transport, drink, or have in their possession any alcoholic beverages. Possession of any controlled substances without a physician's prescription is also prohibited. Any Contractor employee appearing to be under the influence of intoxicating liquor or narcotics will be apprehended by Activity Police, escorted off of the Activity, and turned over to the local Police Department.
Any vehicle found to contain controlled substances, including usable residue, may be seized and impounded. Within 24 hours of the work day following any vehicle seizure, the Activity Police will have determined whether forfeiture of the vehicle is required. If not, the vehicle will be returned to the owner or authorized agent. If the vehicle is determined to be appropriate for forfeiture, the Activity's Legal Officer will notify the Drug Enforcement Administration of such seizure and impoundment, for initiation of forfeiture proceedings pursuant to Title 2l, U.S. Code, Section 88l. Such actions may be taken regardless of whether the owner/operator of the vehicle had knowledge of the presence of drugs in the vehicle. The Government may pursue criminal or other disciplinary actions pursuant to Title l8, U.S. Code, Section l382.
Possession of firearms, ammunition and/or explosives is prohibited. In the event explosives are required for construction work, specific handling requirements and approvals shall be obtained from the Security Officer via the Contracting Officer.
Cameras, video equipment, or similar photographic equipment shall not be introduced into nor removed from the Activity. In the event such equipment is required for performance of contract work, approvals shall be obtained from the Security Officer via the Contracting Officer.
Laptop computers shall not be introduced into nor removed from the Activity. If laptop computers are required to perform work, obtain approvals from the Security Officer via the Contracting Officer.
Driver use of a hand-held cellular phone in a moving vehicle on the Activity is prohibited. This prohibition does not include hands-free cellular phone devices. Hands-free devices include console/dash-mounted or otherwise secured cellular phones with integrated features such as
SECTION 01 14 00.00 20 Page 9 voice-activation, speed dial, speakerphone or other similar technology for sending and receiving calls.
Driver use of any portable, personal listening device worn inside the aural canal, around or covering the driver's ear while operating a motor vehicle is prohibited. Listening devices include wired or wireless earphones and headphones (including blue tooth or similar technology), and do not include hearing aids or devices designed and required for hearing protection.
The use of radar or laser detection devices to indicate the presence of speed recording instruments or to transmit simulated erroneous speeds is prohibited in accordance with OPNAVINST 5100.2H.
The Contractor shall indoctrinate personnel on access limitations to ensure security control is maintained as an integral part of their work pattern and habit.
Contractor shall indoctrinate his/her personnel on escorting procedures and responsibilities. Contractor personnel acting as escorts for other Contractor personnel assume full responsibility for their actions.
Escorts shall be within sight of the persons being escorted at all times.
Contractor is advised that any unescorted personnel found in security areas requiring a higher level clearance than the level represented by the badge displayed will be removed from the area with possible confiscation of security badges and vehicle passes.
1.13.6 Access to Unclassified Information
Access to U.S. Navy technical information manuals, documents, drawings, plans, specifications, and other information (e.g., photos, presentations, renderings, papers, etc.) is government property and restricted to an official need-to-know basis. Handle, control, and safeguard to prevent oral, visual, and documentary disclosure to the public, to foreign sources, and to personnel not having an official need-to-know.
1.13.7 Disclosure of Information
a. The Contractor shall not release to anyone outside the Contractor's organization any unclassified information, regardless of medium (e.g., hard copies, computer files, film, tape, document), pertaining to any part of this contract or any program related to this contract, unless the Contracting Officer has given prior written approval.
b. Requests for approval under paragraph (a) shall identify the specific information to be released, the medium to be used, and the purpose for the release. The Contractor shall submit its request to the Contracting Officer at least 10 business days before the proposed date for release.
c. The Contractor agrees to include a similar requirement, including this paragraph (c), in each subcontract under this contract.
Subcontractors shall submit requests for authorization to release through the prime contractor to the Contracting Officer.
1.14 CONSTRUCTION VEHICLES
The Contractor shall not utilize any vehicle that will exceed an HS20
SECTION 01 14 00.00 20 Page 10 wheel load. The use of "off road", "utility", or "ATV" vehicles which cannot be legally operated on State roadways or highways is prohibited.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 14 00.00 20 Page 11
SECTION 01 20 00.00 20
PRICE AND PAYMENT PROCEDURES (PWD ME)
03/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP-1110-1-8 (2016) Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Schedule of Prices ; G
1.3 SCHEDULE OF PRICES
1.3.1 Data Required
Within 15 calendar days of notice of award, prepare and deliver to the Contracting Officer a Schedule of Prices (construction…
This is the start of the file's text. The full file is on GovTribe.