This document is an amendment to a solicitation for the Building 82 Renovation project at the Defense Logistics Agency Distribution facility in New Cumberland, Pennsylvania. The amendment provides answers to vendor questions to clarify specifications for carpet, vinyl composition tile, rubber base, and light fixtures. It also addresses questions about existing steam lines, sidewalk repair, responsibility for utility costs including natural gas installation by UGI, types of electrical panels and wiring methods, and permit requirements. The solicitation seeks bids for renovations including mechanical, electrical and plumbing work along with new finishes and fixtures to modernize administrative offices, industrial hygiene labs, locker rooms and other spaces in the building.

View the file

Other files for this federal contract opportunity

Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

SP3300-20-B-5002

Amendment 0004

Amendment 0004 is incorporated into solicitation SP3300-20-B-5002.

Amendment 0004 is being issued to:

1. Answer the vendor questions seen below.

2. Revise the description of CLIN 0011 in section B to account for UGI pricing:

CLIN 0011: Provide the necessary labor, material and equipment to perform all work indicated in the contract documents to complete the following minor construction work for Natural Gas Piping not directly associated with Building 82 (exterior work) but not limited to:

• Install new natural gas branch line service from gas line main under “U” Avenue up to new gas meter to be installed by UGI.

• UGI to install new natural gas piping, fittings, valving from existing main "U" Ave. Since UGI is unable to provide a cost for this work at this time, the cost to be included in this CLIN for this item is $50,000.00. This is a Government estimated cost and should be added to the contractor’s bid for this CLIN to determine the total price of CLIN 0011. This UGI “plug value” will be adjusted up or down based on the actual cost provided by UGI after award, and in turn will adjust the total CLIN price.

***No new questions will be answered, only questions that may arise from the below answers may receive a response.

Vendor Questions:

Question 28: Specifications for carpet states a Shaw Industries Product (eco Q Solution nylon) 24x24 tile, but finish schedule says Interface Silk Routes 50 cm tile. Additionally, the Silk Routes is a 250 sq.yd. minimum unless end user has a prearranged agreement for less (this project requires 170 sq.yds). Please verify carpet, size, and ability to purchase less than minimum if applicable.

Answer 28: Use Shaw Industries Product as your basis of design, the product is brand name or equal.

Question 29: Mannington Progressions VCT was discontinued 2 years ago. Closest substitute from aesthetic and performance standpoint would be Armstrong Crown Textures, please advise.

Answer 29: Use Armstrong Crown Textures as your basis of design, the product is brand name or equal.

Question 30: Specifications state Roppe Pinnacle rubber cove base, finish schedule says Johnsonite 283 Toast 4 inch. Does the government desire rubber or vinyl, cove of toeless (straight)?

Answer 30: Use Roppe Pinnacle Rubber cove base as your basis of design, the product is brand name or equal.

Question 31: Does the existing steam lines removed on the East side of Bldg. 82 contain any asbestos?

Answer 31: Based on asbestos containing material (ACM) testing of similar steam piping, there is a high probability that this piping does contain ACM materials in the insulation for these lines. Insulation and felt paper are typically around 30% ACM.

Question 40: The existing sidewalk is listed to remain. It’s in really bad shape. With as much work as we have in the areas of the sidewalks and having to cross the sidewalks with equipment, I don’t think we will be able to protect them from getting broken up worse than they already are. Would the Government consider adding replacing the sidewalks as part of the contract?

Answer 40: These sidewalks were purposely skipped in the project scope as future plans will likely modify existing sidewalks in this area making any work we would do now an unnecessary expense.

Question 44: Is there an allowance to carry for the scope of work associated with UGI?

Answer 44: The contractor is responsible for the complete cost of the installation of the natural gas service. UGI owns all of the natural gas distribution piping on the Installation and utilizes their own subcontractor to run piping from the main to the building, including the gas meter. This UGI effort will have an associated cost to be paid as part of this contract. The prime contractor will be responsible for preparing the trench to run the natural gas piping.

UGI will install then install the natural gas piping, meter and complete the pressure testing, followed by backfilling the pipe trench with stone dust (provided by the prime contractor) to cover the pipe. The prime contractor will then complete the backfill of the trench and repair pavement.

The Government is providing the amount $50,000.00 for UGI cost for each bidder to use in pricing of CLIN 0011. This cost and the total amount to the CLIN will be adjusted either up or down based the actual UGI pricing. Additionally, CLIN 0011 description has been revised to item 2 above to reflect this revision.

Question 45: Please clarify the type of light fixtures required in the following rooms:

A) A101.2 1 - 2X2 NOT LABELED

B) A101.17 13 - 2X2 NOT LABELED

C) A101.11 2 - 2X2 NOT LABELED

D) A101.3 NO TYPE AD SHOWN ON FIXTURE SCHEDULE The fixture schedule only lists type EM, and type DE Answer 45: A) Printer Room A101.2 has two (2) fixtures. One is Type “B” and the second is Type “BE”.

B) Industrial Hygiene Office A101.17 fixtures are existing to remain as noted on E-401 Key note 7.

C) Women’s Locker A.101.11 the two (2) fixtures not labelled are Type “B”, similar to Men’s Locker room.

D) Office A101.3 are both Type “A”, but the LED driver for those fixtures will be controlled by a compatible dimmer described by Key Note 12.

Question 47: Has the glue on the exiting floor been tested for ACM?

Answer 47: It has not been tested, however, mastic adhesive / glue used underneath tiling is well known to contain asbestos as a binding material especially prior to 1980. These materials definitely fall into this time frame.

Question 62: Who is responsible for Utility Co. costs? If it is to be the GC, the GC will need a contact at the Utility Co. and Owner's permission to represent the Owner.

Answer 62: See answer to Question 44.

The cost for use of utilities such as electricity, natural gas, and water will be paid for by the Government.

Question 65: What is the manufacturer of the existing electrical panelboards?

Answer 65: For the most part the panels noted to remain are SQ”D”, but not exclusively. Panels that were of current manufacture and deemed in “good” condition were reused.

Question 66: The floor plans and demo plans for bays 1-5 show emergency signs and exit fixtures in bold with no notes or direction. Is it the intent that those fixtures are to be replaced in place with new fixtures?

Answer 66: Demolition drawings note what is to be removed. Exit and battery wall packs are not noted to be removed, so they are to remain. Those same fixtures appear on the new work plans. The 1/16” scale makes the fixture appear “bold”.

Question 67: Is MC cable acceptable in the admin level?

Answer 67: MC cables are not indicated in Specification 26 20 00, Part 2 Products, nor mentioned in Part 3.1.3 Wiring Methods. So, unless COR authorizes its use, the answer is no.

Question 68: VCT-1 flooring is called out to be Mannington commercial vinyl tile Progressions collection which is discontinued. Please the standard Excelon Armstrong VCT is acceptable.

Answer 68: The Government confirms that standard Excelon Armstrong VCT is acceptable.

Question 69: Our translucent panel installer noticed that the panels are to meet blast requirements, the blast load and standoff distance should be noted on the drawings, but it isn’t. Is this building more at risk of blast loading? Or was the wrong spec inserted? This will make a big difference in price.

Answer 69: The warehouse is exempt from the requirements of UFC 4-040-01, DoD Minimum Antiterrorism Standards for Buildings due to it being a “Low Occupancy Building.”

Definition: Low occupancy building. Any building or portion of a building routinely occupied by fewer than 11 DoD personnel or with a population density of less than one person per 430 gross square feet (40 gross square meters).

Question 70: Will contractors be able to deactivate the existing water line(s) to install the proposed post indicator valves, or will the use of line stops be required to keep the waterlines active? If line stops are required, what size diameter is the existing water main around the building?

Answer 70: When proposed PIVs and new laterals are ready to be tied into the fire water main, the contractor shall notify the COR. The COR will have maintenance personnel isolate the water main at either end of Building 82. This outage may be no longer than 8 hours. Line stops will not be required or permitted. Corporation stops are to be installed at the lateral tie-in location to the main for new 8” laterals only.

Question 71: What size diameter of pipe are the existing water laterals to determine what size post indicator are required?

Answer 71: Water laterals on the south side of Building 82 are 6” laterals. Record drawings indicate that all laterals are ACP. For those laterals where PIVs are being relocated (3 bays), the contractor is to include the cost of replacing entire lateral with 8” ductile iron pipe. This includes increasing the connection to the main to 8”. The main line is 12” ductile iron. Remaining two bays will not be affected.

Question 72: How are the permits handled? All on base or what outside agency and fees apply?

Answer 72: All permits are handled on base, unless it’s an environmental permit for excavating, which is handled through the York county conservation district.

All other terms and conditions remain unchanged.

Amendment 0004
Amendment 0003
Amendment 0002
Amendment 0001
Amendment 0001
Amendment 0001
Amendment 0001

Amendment 0004 wording

IDCode:
Page: 1
Pages: 5
AmendNo: 0004
EffDate: 25-Aug-2020
ReqNo: N/A
ProjNo:
IssCode: SP3300
IssuedBy: DLA DISTRIBUTION

ACQUISITION OPERATIONS J7-AB

5404 J AVENUE BUILDING 404

NEW CUMBERLAND PA 17070-5059

AdmCode: SP3300
AdminBy: JOSHUA WOODWORTH

717-770-4192 joshua.woodworth@dla.mil

ContName:
ContStrt:
ContCnty:
ContSt:
ContZIP:
Code:
FacCode:
SolChgYs: Yes
SolChgNo: Off
SolAmdNo: SP3300-20-B-5002
AmendDate: 16-Jul-2020
ModNo:
ModDate: 05 JUL 20
NoCopies: 1
Amended: Yes
OffrExt: Off
OffrNoEx: No
ApprData:
ChgeOrd: Off
ChgeOrder:

File details come from the government source that posted it. Updated .