ATTACHMENT_2_-_SOW_Renovate_B-17_Office_02222017.pdf

PDF 87 KB Posted

Attached to
Z2--Other Warehouse Buildings, REPAIR OR
Solicitation number
SP330017B0004
Issued by

About this file

Attachment 2 - revised SOW Renovate B-17 Office

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SP330017B0004

Amendment 0001

ATTACHMENT 2

Project Title: Building 17 Renovate Office Area

Location: Building 17, Bubble Office Area, Tracy Site, Tracy Ca.

Date: 1/31/2017

STATEMENT OF WORK

Enclosure (1): B-17 Renovate Office Area Drawing

(2): Carpet Specification.

(3): B-17 LAN Specification.

(4): LAN Jack Reference.

(5): Asbestos Survey Report.

1.0 GENERAL REQUIREMENTS

Provide construction services to include all labor, management, supervision, tools, materials, equipment, and transportation to renovate Room 9.

1.1 General Description

The scope of work includes but is not limited to the following:

a. Renovate B-17 Office Areas.

b. Remove Carpet tiles and adhesive in north office area (asbestos abatement requirements).

c. Construct New Walls with doors in north office area.

d. Paint all walls with a new coat of white paint.

e. Install New Carpet and Cove Base in north office area (carpet specifications attached).

f. Remove Cabinets and Sink in break area.

g. Remove Two Walls next to Training Room area (asbestos abatement requirements).

h. Install New Carpet and Cove Base in break area (carpet specifications attached).

i. Remove Carpet tiles in south office area (no asbestos requirements).

j. Install New Carpet and Cove Base in south office area (carpet specifications attached).

k. Install New Electrical Panel in the main office to provide 12 each 20 amp 120V circuits for the system furniture installation. Provide a 100 amp circuit breaker in main Panel 173A to feed the new panel for the system furniture.

l. Install New LAN and Electrical requirements for 20 new system furniture workstations. This work must be coordinated with the furniture installers in order to integrate the wiring into the furniture raceways (LAN Specification attached).

m. Contractor shall verify all existing conditions and dimensions.

n. All demolished material shall be disposed of off-site from DDJC property.

1.2 Submittals

Submittals are required for all material to be utilized and/or installed and shall be in compliance with the Unified Facilities Guide Specifications (UFGS), and the basic contract. All submittals shall be approved prior to commencement of work.

Submittals shall include but not limited to the following:

a. Task specific: Quality Control Plan, Hazard Analysis, and Safety/Health Plan.

b. Construction schedule and Phasing Plan.

c. Manufacturer’s data for suspended ceiling system, carpet floor tiles, cove base, doors and hardware, diffusers, registers, grilles, and cable.

d. As-built drawings.

1.3 Project Schedule and Time Constraints

Schedule and Completion of Work

The contractor is required to prosecute the work diligently and complete the entire work, ready for use no later than 180 calendar days after the award/NTP of the task order. The time stated for completion shall include final clean-up of the premises. (Section 00700, FAR 52.211-10)

Liquidated Damages

The liquidated damages for this task order are $ 0.00 per calendar day.

Preconstruction Meeting

Prior to the initiation of work, a meeting will be held with the contractor, USACE

COR, Depot PM/PE and COR/Inspector to discuss matters of mutual interest concerning the task order. General conditions, work schedule, phasing, and coordination, security, safety, permits, and other matters pertinent to work accomplishments will be discussed in this meeting.

1.4 Point of Contact (POC)

DEPOT: Norm Dalsis Project Engineer (209) 839-4086

Doug Betz COR/Inspector (209) 839-4232

2 WAGE DETERMINATION

Refer to contract section 00700, page 32, FAR52.222-13, Davis-Bacon and Related Acts.

Construction Wage Determination Number CA170029 Modification Number 11

Dated 05/12/2017 applies. Certified Payrolls are required to be submitted with each pay request.

3 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

Refer to contract section 0700, page 86, FAR 52.249-10, Default (Fixed-Priced

Construction). The monthly anticipated adverse weather delay work days for this task order have been provided on the contract page 01505-5.

4 AUTHORITIES

No person other than the USACE Contracting Officer has the authority to make any changes to this contract action that impact cost or schedule. Authority from the USACE

Contracting Officer to the contractor to make changes that impact cost or schedule will be in the form of an official, signed modification.

END OF RFP DESCRIPTION

File details come from the government source that posted it. Updated .