This is a Request for Quotations (RFQ) for potable water testing services at Buffumville Lake Park in Charlton, Massachusetts, issued by the U.S. Army Corps of Engineers. The solicitation number is W912WJ26QA072, with an offer due date of March 27, 2026 at 2:00 PM Eastern. The contract is set aside for Women-Owned Small Business (WOSB) concerns, with a 100% set-aside preference for North American American Business (NAICSIB). The base year contract period runs from April 1, 2026 through March 31, 2027, with two optional one-year extensions (through March 31, 2028 and October 31, 2028). Site visits are scheduled for March 19, 2026 at 9:00 AM and March 23, 2026 at 1:00 PM. The incumbent contractor is McClure Engineering, Inc., which was previously awarded $9,871.12. Quoters must be registered in the System for Award Management (SAM) at time of quote submission and remain registered through final payment.

The Performance Work Statement details comprehensive potable water testing services in accordance with 310 CMR 22.00 (Massachusetts Drinking Water Regulations). Key deliverables include five main service categories: (1) seasonal start-up procedures with written sampling plan and Mass DEP approval; (2) routine water testing at three sampling points (pump house entry point, restroom fountain, and storage barn hydrant) with five instances per year; (3) additional testing as required if contaminant levels exceed Maximum Contaminant Levels, limited to two instances; (4) corrective action treatment if testing exceeds MCL thresholds, limited to four instances; and (5) seasonal shutdown procedures. The contractor must be the primary communicator with Massachusetts Department of Environmental Protection (Mass DEP), complete all required submittals within 14 days of contract award (ENG Forms 6293, 6206, 6282, First Aid and CPR certificates, and SDS sheets), and comply with USACE safety requirements including EM 385-1-1 standards. Monthly invoicing based on actual services performed is required, with final payment withheld until all issued keys are returned. Services are performed Monday through Friday, 7:00 AM to 3:30 PM, May through September annually while the park operates.

View the file

Other files

File Type Posted
Amendment W912WJ26QA072-0004.pdf PDF
Amendment W912WJ26QA072-0003.pdf PDF
Amendment W912WJ26QA072-0002.pdf PDF
Amendment W912WJ26QA072-0001.pdf PDF
Attachments 26QA072.pdf PDF
Solicitation Survey 26QA072.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WOMEN-OWNED SMALL

BUSINESS (WOSB)

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES

1. REQUISITION NUMBER PAGE 1 OF

2. CONTRACT NUMBER 3. AWARD/EFFECTIVE

DATE

4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE

DATE

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME b. TELEPHONE NUMBER (No collect 8. OFFER DUE DATE/

LOCAL TIME

9. ISSUED BY

13b. RATING

14. METHOD OF SOLICITATION

CODE

15. DELIVER TO 16. ADMINISTERED BY CODE

18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/

OFFEROR

CODE

FACILITY

CODE

CODE

TELEPHONE NUMBER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK

BELOW IS CHECKED

REQUEST

FOR QUOTE

(RFQ)

INVITATION

FOR BID

(IFB)

REQUEST

FOR

PROPOSAL

(RFP)

SEE ADDENDUM

19.

ITEM NUMBER

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Government Use Only)

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH

AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND

ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS

SPECIFIED

29. AWARD OF CONTRACT: REFERENCE OFFER

DATED . . YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR

30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 11/2021)

Prescribed by GSA - FAR (48 CFR) 53.212

10. THIS ACQUISITION IS UNRESTRICTED OR

NORTH AMERICAN

INDUSTRY CLASSIFICATION

STANDARD (NAICS):

SIZE STANDARD:

13a. THIS CONTRACT IS A

RATED ORDER UNDER

THE DEFENSE PRIORITIES

AND ALLOCATIONS

SYSTEM - DPAS (15 CFR 700)

SET ASIDE: % FOR:

11. DELIVERY FOR FREE ON

BOARD (FOB) DESTINATION

UNLESS BLOCK IS MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

ARE ARE NOT ATTACHED

ARE ARE NOT ATTACHED

27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3

AND 52.212-5 ARE ATTACHED. ADDENDA

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

8(A)

ECONOMICALLY

DISADVANTAGED

WOMEN-OWNED SMALL

BUSINESS (EDWOSB)

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

(SDVOSB)

HUBZONE SMALL

BUSINESS

SMALL BUSINESS

NOTE: OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30.

calls)

Continuation of Supplies or Services and Prices/Costs

Additional Information/Notes

BID SCHEDULE:

U.S. ARMY CORPS OF ENGINEERS

POTABLE WATER TESTING SERVICES

BUFFUMVILLE LAKE

CHARLTON, MA

Base Year Bid Schedule (2026)

TASK/ITEM NUMBER UNIT QUANTITY UNIT

PRICE

TOTAL

1. Buffumville Lake Park Seasonal Start-up Procedures

JOB 1 $ $

2. Buffumville Lake Park Routine Water Testing

Each 5 $ $

3. Buffumville Lake Park Additional Testing as Required

Each 2 $ $

4. Buffumville Lake Park Corrective Action Treatment

Each 4 $ $

5. Buffumville Lake Park Seasonal Shutdown Procedures

JOB 1 $ $

TOTAL $

W912WJ26QA072

Option Year 1 Bid Schedule (2027)

TASK/ITEM NUMBER UNIT QUANTITY UNIT

PRICE

TOTAL

1. Buffumville Lake Park Seasonal Start-up Procedures

JOB 1 $ $

2. Buffumville Lake Park Routine Water Testing

EACH 5 $ $

3. Buffumville Lake Park Additional Testing as Required

EACH 2 $ $

4. Buffumville Lake Park Corrective Action Treatment

EACH 4 $ $

5. Buffumville Lake Park Seasonal Shutdown Procedures

JOB 1 $ $

TOTAL $

Option Year 2 Bid Schedule (2028)

TASK/ITEM NUMBER UNIT QUANTITY TOTAL

UNIT

PRICE

1. Buffumville Lake Park Seasonal Start-up Procedures

JOB 1 $ $

2. Buffumville Lake Park Routine Water Testing

EACH 5 $ $

3. Buffumville Lake Park Additional Testing as Required

EACH 2 $ $

4. Buffumville Lake Park Corrective Action Treatment

EACH 4 $ $

5. Buffumville Lake Park Seasonal Shutdown Procedures

JOB 1 $ $

TOTAL $

*** END OF NARRATIVE ***

Continuation of Description

INTERESTED VENDORS SHALL REVIEW THE "ADDENDUM TO 52.212-1" AND

"ADDENDUM TO EVALUATION" FOR INSTRUCTIONS AND EVALUATION CRITERIA.

VENDORS ARE RESPONSIBLE FOR ENSURING THEIR QUOTE SUBMISSION MEETS

ALL REQUIREMENTS. FAILURE TO DO SO MAY RESULT IN QUOTES BEING DEEMED

NON-RESPONSIVE AND REMOVED FROM CONSIDERATION.

THE MANDATORY SOLICITATION SURVEY SHALL BE COMPLETED IN ITS ENTIRETY

AND RETURNED WITH QUOTES. FAILURE TO DO SO MAY RESULT IN QUOTES BEING

DEEMED NON-RESPONSIVE AND REMOVED FROM CONSIDERATION.

PERFORMANCE WORK STATEMENT:

POTABLE WATER TESTING SERVICES

U.S. ARMY CORPS OF ENGINEERS

BUFFUMVILLE LAKE

CHARLTON, MA

PERFORMANCE WORK STATEMENT

I. GENERAL

1. Summary:

Provide all labor, materials, equipment, and transportation necessary to sample and test potable water at Buffumville Lake Park. All procedures will be in accordance with 310 CMR 22.00: The Massachusetts Drinking Water Regulations. The Contractor shall be the primary communicator between the Government and the Massachusetts Department of Environmental Protection (Mass DEP). The Contractor shall complete and submit all required documents and forms to allow for the public water supply to operate in accordance with the Mass DEP.

*Note: This work requires the following submittals prior to the commencement of work (Refer to Section II. Technical Requirements for a full list of submittals):

ENG Form 6293 (Accident Prevention Plan Worksheet)

ENG Form 6206 (Activity Hazard Analysis)

ENG Form 6282 (Site Safety and Health Officer Designation Letter)

First Aid and CPR Certificates

SDS sheets

All Certification(s) and License(s) as required by 310 CMR 22.00: The Massachusetts Drinking Water Regulations

2. Location:

Buffumville Lake Park is located at 229 Oxford Rd. Charlton, MA 01507. See the attached informational maps for more detailed location information.

3. Site Visits and Requests for Information:

Site visits are strongly recommended to gauge the full scope of work and provide an accurate quote. Interested vendors should conduct a site visit to confirm understanding of the scope, inspect existing conditions, and familiarize themselves with the site(s) prior to submitting a quote. No extra payment will be allowed for perceived additional work caused by unfamiliarity with site conditions and requirements.

Site visits will be held on the specified dates and times listed below only:

a. Thursday, March 19, 2026 at 9:00 AM Eastern

b. Monday, March 23, 2026 at 1:00 PM Eastern

Please Note - Site visits outside of these specific dates and times are not permitted unless additional site visit dates/times are publicized in an amendment. All questions during site visits will be sent to the Contract Specialist as indicated in the Instructions to Vendors and responses will be provided in an amendment. Information incorporated into the solicitation via amendment will become binding.

4. Technical Point of Contact:

After contract award, the Technical Point of Contact (TPOC) for this project is Park Ranger Ally Mars: (508) 248-5697 or via email at alexandra.mars@usace.army.mil.

5. Schedule:

The contract period of performance for the base year shall be from 1 April 2026, or contract award if after 1 April 2026, to March 31, 2027. In addition, the government may exercise two (2) option years with the same statement of services. Option Year one (1) has a period of performance from April 1, 2027 to March 31, 2028. Option Year two (2) has a period of performance from April 1, 2028 to October 31, 2028. Services will only need to be physically rendered from May through September each year while the park and well are in use. Work shall be performed Monday through Friday between the hours of 7:00 AM and 3:30 PM unless otherwise approved by the TPOC. Any proposed changes to an approved schedule must be submitted to the TPOC in writing and are not finalized until approved. No work shall be done on weekends or Government holidays.

Service Year Start Date End Date

Base Year 1 April 2026 or Contract Award March 31, 2027

Option Year 1 April 1, 2027 March 31, 2028

Option Year 2 April 1, 2028 October 31, 2028

All pre-work submittals shall be submitted within 14 days of contract award. The Government reserves up to 7 days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall be resubmitted to the Government in an acceptable form within 7 days of the Government's response, unless additional time is granted by the Government in writing. No field work may proceed prior to the acceptance of pre-work submittals.

6. Safety Requirements:

a. General:

All work shall be conducted in accordance with the U.S. Army Corps of Engineers (USACE) Safety and Occupational Health Requirements (EM 385-1-1, most recent edition), and all applicable Occupational Safety and Health Administration (OSHA), federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed electronically at the following link:

https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE% 2015March2024.pdf

Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.

b. Accident Prevention Plan (APP):

The Contractor shall prepare a site-specific Accident Prevention Plan. The APP must be written by a Competent Person (CP) and document the specific work processes, equipment, materials to be used, hazards and applicable control measures.

The mandatory ENG Form 6293 (Accident Prevention Plan Worksheet) must be submitted and accepted prior to beginning on site work:

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_2023Aug31.pdf

A preparatory meeting shall be conducted by the Prime Contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing the subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.

Daily safety meetings shall be held and documented. Records shall be available to the Technical Point of Contact upon request.

c. Activity Hazard Analysis (AHA):

An AHA shall be submitted and accepted for each definable feature of work (DFOW) in accordance with EM 385-1-1, Chapter 2-6. A DFOW is defined as any task, which is separate and distinct from other tasks, has separate control requirements, or is identified as different trades or disciplines. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.

For a non-mandatory formatted outline of an AHA, see ENG Form 6206 (Activity Hazard Analysis) https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_2023Aug24.pdf

d. Site Safety and Health Officer (SSHO) Requirements:

The Contractor shall employ a minimum of one person to function as a Level 3, SSHO. A Level 3 SSHO is a designated Qualified Person (QP) or Competent Person (CP) with Safety and Occupational Health (SOH) responsibility that meets the requirements of EM 385-1-1, Chapter 2-3.b and 2-4.b.

Level 3 SSHOs must have training, knowledge, and/or experience identifying hazards and implementing controls for the work being performed.

The SSHO shall be present at the project site and be responsible for overseeing the implementation of the Prime Contractor's SOH program. Contractor shall designate all SSHOs on a mandatory ENG Form 6282 (Site Safety and Health Officer Designation Letter):

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_2023Aug28.pdf

e. First-Aid and CPR Personnel Requirements:

For shifts with multiple employees, provide at least two employees that are certified to administer First Aid and CPR. When employees work alone, they must be certified in First Aid and be provided an effective means of communication to call for assistance in the event of an emergency. Minimum First Aid and CPR qualifications are outlined in EM 385-1-1, Chapter 3-3.

f. Additional Personnel Requirements:

Other Competent Person (CP) or Qualified Persons (QP) may be required per EM 385-1-1 and /or other sections of this Scope of Work, based on the definable features of work for this project.

g. Accident Reporting:

All accidents and near misses shall be investigated by the Contractor and reported to the Technical Point of Contact in accordance with EM 385-1-1, Table 2-1.

The mandatory ENG Form 3394 shall be completed and submitted to the Technical Point of Contact within seven (7) days of an incident: https://www.publications.usace.army.mil/Portals/76 /Publications/EngineerForms/Eng_Form_3394_2021Aug.pdf

h. Employee Exposure Data:

The Contractor shall electronically report total employee work hours (including subcontractors) to the Technical Point of Contact by close of business on the 10th calendar day of the following month.

7. Pre-Work Conference:

Prior to the start of any site work, the Technical Point of Contact will schedule and conduct a pre-work conference. The Contractor's Project Manager and Quality Control Personnel will be physically present to attend this meeting. This conference will be held at the time and location agreeable to the Government and Contractor. No site work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government's administration and inspection of contract work or obtain other pertinent information that might be required. At the pre-work conference the Contractor shall provide the name of the project superintendent with a telephone number for project coordination.

For the duration of the contract, the Contractor will be provided keys to the Buffumville Lake Park security gate, pump house, and storage barn. Keys are to be used only for contract purposes. The keys will not be utilized to provide access for any individuals not performing contract specific work. During the contract period, the Contractor is assumed responsible for the keys. At the end of the service period, the key must be returned to the TPOC in person.

Final payment will be withheld until keys are returned to the TPOC.

The following is a general list of items for discussion during this pre-work meeting:

Authority of the Technical Point of Contact

Contractor's Safety Program (including sub-contractors)

Accident Prevention Plan (APP) and Activity Hazard Analysis (AHA)

Weekly Safety Meetings (Documented on NED Form 251)

Accident Reporting (ENG Form 3394)

Correspondence, Communication and Administrative Procedures

Invoice and payment

8. Permits:

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable federal, state, county, and municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

9. Security:

The Contractor will comply with all established security policies at the project. Due to periods of heightened security that may affect the access to the areas covered under this contract, areas may be subject to periodic closures, which in turn may reduce or inhibit the Contractor's ability to access certain areas. During periods of heightened security, the Government reserves the right, at any time, to close any property or portion of property and reschedule and/or cancel any subsequent service in an area. The Contractor shall be given at least 24-hour notice of any such closure.

10. Payment:

The Contractor shall furnish the TPOC with one (1) invoice per month or at the completion of services. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, and total amount due per line item. The invoice must also include the company letterhead, and this must match the data that is registered in the System for Award Management (SAM) registry. Payment shall be made monthly for the actual services performed at the applicable contract unit price.

NOTE: Final Payment may be held until the Contractor has returned any and all issued keys/cards to the TPOC at the completion of work. Any and all keys are required to be physically handed to the TPOC. The Contractor assumes all responsibility for loss (which may include the cost of rekeying the applicable project).

U.S. Army Corps of Engineers

Buffumville Lake

48 Old Oxford Rd.

Charlton, MA 01507

Or emailed to: alexandra.mars@usace.army.mil

II. TECHNICAL

1. Submittals:

Although the Government reviews submissions required by this performance work statement, it is emphasized that the Contractor's work must be completed using proper internal controls and review procedures. The Government reserves up to 7 days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the

Contractor shall make such revisions and shall resubmit to the Government within74 days of the Government's response, unless additional time is granted by the Government in writing.

The documents identified below must be prepared in accordance with the applicable standards, submitted to the TPOC for review and accepted by the Government.

a. Pre-Work Submittals: Submitted within 14 days of contract award. Submittals must be accepted before the commencement of any field work.

ENG Form 6293 (Accident Prevention Plan)

ENG Form 6206 (Activity Hazard Analysis)

ENG Form 6282 (Site Safety and Health Officer Designation Letter)

First Aid and CPR Certificates

SDS sheets

All Certification(s) and License(s) as required by 310 CMR 22.00: The Massachusetts Drinking Water Regulations Statement

b. Other Submittals:

Written sampling plan & Mass DEP approval

Written start-up procedure & acceptance (No later than May 1st)

All final lab results & acceptances (After each test)

2. Clean Up:

The Contractor shall practice good housekeeping to maintain a safe job site. The Contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials. Upon completing work in an area, the Contractor shall remove any tools, equipment, and materials that are not the property of the Government. Upon completion of work, the Contractor shall clean up the job site to the satisfaction of the Government.

3. Government Resources:

The Contractor is responsible for providing all materials to complete the project. Unless specified in the contract, the Government will not provide any equipment, telephone services or other resources.

4. Damage to Government and Private Property:

The Contractor shall be responsible for restoring any Government facilities or structures damaged as a result of the firm's operation. The Contractor shall also be responsible for any damage to private property or injury to any person as a result of the firm's operations. The Contractor shall notify the Technical Point of Contact immediately of damage to Government and private property and injury to any person resulting from the firm's operation.

5. Omissions:

This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.

6. Quality Assurance:

The Contractor is responsible for the quality control of the contract work. The Government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.

7. Other Contracts:

The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other Contractors and Government employees. The Contractor shall not commit or permit any act, which will interfere with the performance of work by another Contractor, or by Government employees.

8. Environmental Protection:

Containers for excess and/or waste materials, rubbish, etc. shall be provided by the Contractor at the site, and the site will be inspected/ cleaned on a daily basis. No burning is permissible.

Water, air, and land resources shall not be adversely impacted during the course of the work.

The Contractor will take necessary steps to ensure all federal, state, and local environmental regulatory requirements are met.

9. Receiving and Storing Materials:

The Contractor is responsible for protecting any stored material until it is placed in service. The Contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive material or supplies for the Contractor and will not be responsible for damage to Contractor equipment or material.

10. Existing Conditions:

Buffumville Lake Park is a seasonal recreation area. The park opens on the third Saturday of May and closes on the second Sunday of September each year. Hours of operation for the park are 8:00 AM to 8:00 PM, seven days a week, including Federal holidays. The park's water is sourced by Public Water Supply (PWS) 2054052. Amenities include a swim beach, picnic tables and grills, a restroom facility, picnic shelter, and three (3) RV host sites.

a. PWS 2054052

i. Seasonal transient well system.

ii. 6" bedrock well drilled to a depth of 675' with a 2-horsepower submersible pump set at 600'.

iii. Approved by Mass DEP for a withdrawal rate of 3,000 gallons per day.

iv. Aboveground well components are located in the pump house. See the attached map and as-built drawings for reference. Components include a calibrated water meter, variable frequency pump control drive, pressure tank, and filter housing unit.

v. See included attachments for the 2026 Certificate of Registration, 2025 Drinking Water Quality Report, and Compliance Monitoring Schedule (2026-2028).

11. Service Locations:

Three (3) different sampling points exist within Buffumville Lake Park.

a. Sample Point 1

i. Located inside the pump house which requires keyed entry.

ii. Handwheel hose bib serves as the sampling point tap, found between the pressure tank and filter housing along the piping.

iii. Sample Point 1 represents the entry point to the distribution system.

b. Sample Point 2

i. Located along the exterior of the restroom facility.

ii. Two (2) water fountains are located on the face of the building closest to the beach. The Contractor shall select either of these fountains and remain consistent with that choice for the remainder of the contract.

iii. Sample Point 2 represents a consumer endpoint of the distribution system.

c. Sample Point 3

i. Located along the exterior of the storage barn.

ii. Frost-proof yard hydrant, mounted to a 4" by 4" wood post in Host Site 1.

iii. Sample Point 3 represents a consumer endpoint of the distribution system.

III. EXECUTION:

The Contractor shall be the primary communicator between the Government and Mass DEP. In the event Mass DEP communicates concerns or work which falls outside of the contract's scope, the Contractor shall not go forward with actions until they have communicated with the TPOC. Execution of services shall occur in accordance with the Performance Work Statement, 310 CMR 22.00: The Massachusetts Drinking Water Regulations, and all local, state, and federal requirements.

1. Seasonal Start-up Procedures

a. The Contractor shall submit to Mass DEP a written sampling plan that identifies the sampling sites listed in this performance work statement and a sample collection schedule.

b. The Contractor shall submit a written start-up procedure to the Mass DEP no later than May 1st. After the start-up procedures are accepted, the procedures as agreed upon shall be fully executed.

c. A formal receipt or written acknowledgement from Mass DEP must be submitted by the Contractor for both the sampling plan and start-up procedures.

2. Routine Water Testing

a. The Contractor shall perform routine tests at the intervals agreed upon by the Mass DEP in their written sampling plan.

b. One Routine Water Test requires sampling from Sample Point 1, Sample Point 2, and Sample Point 3.

c. The Contractor is responsible for submitting lab results for Routine Water Testing to the TPOC no later than 48 hours after lab results are completed.

3. Additional Testing as Required

a. In the event that a Routine Water Test exceeds the Maximum Contaminant Levels (MCL) for any compound or bacteria, the Contractor shall then perform additional testing as required by repeat monitoring requirements and analytical requirements in 310 CMR 22.05(2).

b. The Contractor may perform up to two (2) instances of Additional Testing as Required. The Government shall only pay for services rendered.

c. One Additional Testing as Required is defined as the first initial test exceeding MCL. All consecutive tests exceeding MCL are considered the same instance of Additional Testing as Required until proof of acceptable levels, as defined by Mass DEP, are achieved.

d. The Contractor is responsible for submitting lab results for all Additional Testing as Required to the TPOC no later than 48 hours after lab results are completed.

4. Corrective Action Treatment

a. In the event that any test exceeds MCL or at the request of Mass DEP, then the Contractor shall provide treatment to the PWS to bring the water quality below MCL thresholds or satisfy Mass DEP's request.

b. The Contractor may perform up to four (4) instances of Corrective Action Treatment. The Government shall only pay for services rendered.

5. Seasonal Shutdown Procedures

a. The Contractor shall complete and submit seasonal shutdown paperwork.

b. The Contractor is not responsible for winterizing the PWS and water system.

*** END OF NARRATIVE ***

Requirements Potable Water Testing Services, Buffumville Lake, Charlton, MA

Contract Clauses

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.

2017-01

52.204-13 System for Award Management- Maintenance.

2026-02

52.212-4 Terms and Conditions-Commercial Products and Commercial Services.

2026-02

52.219-6 Notice of Total Small Business Set-Aside. 2026-02

52.222-36 Equal Opportunity for Workers with Disabilities.

2026-02

52.222-41 Service Contract Labor Standards. 2026-02

52.222-50 Combating Trafficking in Persons. 2026-02

52.222-62 Paid Sick Leave Under Executive Order 13706.

2026-02

52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving.

2024-05

52.232-33 Payment by Electronic Funds Transfer- System for Award Management.

2018-10

52.232-40 Providing Accelerated Payments to Small Business Subcontractors.

2023-03

52.233-3 Protest after Award. 2026-02

52.233-4 Applicable Law for Breach of Contract Claim.

2026-02

DFARS Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

252.203-7000 Requirements Relating to Compensation of Former DoD Officials.

2011-09

252.203-7002 Requirement to Inform Employees of Whistleblower Rights.

2022-12

252.204-7004 Antiterrorism Awareness Training for Contractors.

2023-01

252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting. (DEVIATION 2024-O0013

REVISION 1)

2024-05 Deviation 2024- O0013

2024-05

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services.

2023-01

252.204-7020 NIST SP 800-171 DoD Assessment Requirements.

2023-11

252.223-7008 Prohibition of Hexavalent Chromium. 2023-01

252.225-7001 Buy American and Balance of Payments Program.

2024-02

252.225-7012 Preference for Certain Domestic Commodities.

2022-04

252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime.

2023-01

252.225-7060 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region.

2023-06

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports.

2018-12

252.232-7010 Levies on Contract Payments. 2006-12

252.247-7023 Transportation of Supplies by Sea. 2024-10

FAR Clauses Incorporated by Full Text

Date

Alternate Deviation

Variation Effective Date

52.219-28 Postaward Small Business Program Rerepresentation.

2026-02

Postaward Small Business Program Rerepresentation (Feb 2026)

(a) . As used in this clause-Definitions

Long-term contract means a contract of more than five years in duration, including options.

However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern-

(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in its field of operation, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.

(2) , as used in this definition, means business concerns, one of whom directly or Affiliates indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.

(b) If the Contractor represented that it was a small business concern, a small disadvantaged business concern, or a joint venture that was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts-

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code(s) assigned to this contract. The small business size standard corresponding to this NAICS code(s) can be found at https://www.sba.gov /document/support--table-size-standards.

(d) The small business size standard for a Contractor providing an end item that it does not manufacture, process, or produce itself, for a contract other than a construction or service contract, is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition-

(1) Was set aside for small business and has a value above the simplified acquisition threshold;

(2) Used the HUBZone price evaluation preference regardless of dollar value, unless the Contractor waived the price evaluation preference; or

(3) Was an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation(s) required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting officer in writing within the timeframes specified in paragraph (b) of this clause, that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:

(1) The Contractor represents that it is, is not a small business concern under 541380 NAICS Code assigned to contract number.W912WJ26PXXXX

(2) [Complete only if the Contractor represented itself as a small business concern in .] The Contractor represents that it is, is not, a small paragraph (g)(1) of this clause disadvantaged business concern as defined in .13 CFR 124.1001

(3) . Women-owned small business (WOSB) joint venture eligible under the WOSB Program The Contractor represents that it is, is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [ The Contractor shall enter the name and unique ____ entity identifier of each party to the joint venture: __.]

(4) . Economically disadvantaged women-owned small business (EDWOSB) joint venture The Contractor represents that it is, is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [ The Contractor shall enter the name and unique ____ entity identifier of each party to the joint venture: __ .]

(5) Service-disabled veteran-owned small business (SDVOSB) joint venture eligible under . The Contractor represents that it is, is not an SDVOSB joint venture the SDVOSB Program eligible under the SDVOSB Program that complies with the requirements of 13 CFR

128.402. [ The Contractor shall enter the name and unique entity identifier of each party ____ to the joint venture: __.]

(6) [ HUBZone joint venture eligible under the HUBZone Program. Complete only if the ] The offeror represents, as part of its offer, offeror is a HUBZone small business concern.

that It is, is not a HUBZone joint venture that complies with the requirements of 13 CFR 126.616(a) through (c). [ The Contractor shall enter the name and unique entity identifier ____ of each party to the joint venture: .] Each HUBZone small business concern participating in the HUBZone joint venture must be certified as a HUBZone concern. [ Contractor to sign ____ and date and insert authorized signer's name and title.]

(End of clause)

52.222-42 Statement of Equivalent Rates for Federal Hires.

2014-05

Statement of Equivalent Rates for Federal Hires (May 2014)

In compliance with the Service Contract Labor Standards statute and the regulations of the Secretary of Labor ( 29 CFR Part 4), this clause identifies the classes of service employees expected to be employed under the contract and states the wages and fringe benefits payable to each if they were employed by the contracting agency subject to the provisions of 5 U.S.C.5341 or 5 332.

This Statement is for Information Only: It is not a Wage Determination

Employee Class Monetary Wage-Fringe Benefits (End of clause)

DFARS Clauses Incorporated by Full Text

Date

Alternate Deviation

Variation Effective Date

252.232-7006 Wide Area WorkFlow Payment Instructions.

2023-01

WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)

(a) Definitions. As used in this clause-

"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.

"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.

"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall-

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web- Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items-

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

(Contracting Officer: Insert either "Invoice 2in1" or the applicable invoice and receiving report document type(s) for fixed price line items for services.)

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial financing, submit a commercial financing request.

(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC ____ Issue By DoDAAC ____ Admin DoDAAC ____ Inspect By DoDAAC ____ Ship To Code ____ Ship From Code ____ Mark For Code ____ Service Approver (DoDAAC) ____ Service Acceptor (DoDAAC) ____ Accept at Other DoDAAC ____ LPO DoDAAC ____

DCAA Auditor DoDAAC ____ Other DoDAAC(s) ____ (*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert "See Schedule" or "Not applicable.")

(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

(Contracting Officer: Insert applicable information or "Not applicable.")

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

Addendum to Contract Clauses

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.204-9 Personal Identity Verification of Contractor Personnel.

2011-01

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations.

2026-02

52.222-3 Convict Labor. 2026-02

52.223-23 Sustainable Products. 2026-02

52.240-91 Security Prohibitions and Exclusions. 2026-02

52.244-6 Subcontracts for Commercial Products and Commercial Services.

2026-02

DFARS Clauses Incorporated by Reference

Date

Alternate Deviation

Variation Effective Date

252.237-7010 Prohibition on Interrogation of Detainees by Contractor Personnel.

2023-01

252.243-7001 Pricing of Contract Modifications. 1991-12

252.244-7999 Subcontracts for Commercial Products or Commercial Services.

(DEVIATION 2026-O0015)

2026-02 Deviation 2026- O0015

2026-01

FAR Clauses Incorporated by Full Text

Number Title Effective Alternate Variation

Date Deviation Effective Date

52.217-9 Option to Extend the Term of the Contract.

2000-03

Option to Extend the Term of the Contract (Mar 2000)

The Government may extend the term of this contract by written notice to the Contractor (a) within ; provided that the Government gives the Contractor a preliminary 15 calendar days written notice of its intent to extend at least before the contract expires. 30 calendar days The preliminary notice does not commit the Government to an extension.

If the Government exercises this option, the extended contract shall be considered to (b) include this option clause.

The total duration of this contract, including the exercise of any options under this clause, (c) shall not exceed .3 years

(End of clause)

52.252-2 Clauses Incorporated by Reference.

1998-02

Clauses Incorporated By Reference (Feb 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address (es):

https://www.acquisition.gov/

(End of clause)

52.252-6 Authorized Deviations in Clauses.

2020-11

Authorized Deviations in Clauses (Nov 2020)

The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR (a) Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.

The use in this solicitation or contract of any (48 CFR ) clause with an (b) DFARS Chapter 2 authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

List of Contract Documents, Exhibits, or Attachments

ATTACHMENTS:

PLEASE SEE ATTACHMENTS INCLUDED SEPARATELY FOR ADDITIONAL INFORMATION.

SECURITY REQUIREMENTS:

General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor ("Contractor") and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (eg., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as "RAMs"), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures -this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clauses of this contract, should FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

WAGE DETERMINATIONS:

The Wage Determination for this project can be found at:

https://sam.gov/wage-determination/2015-4103/33

Wage Determination No.: 2015-4103

Revision No.: 33

Revised Date: 03 December 2025

*** END OF NARRATIVE ***

W912WJ26QA072

https://sam.gov/wage-determination/2015-4103/33

Solicitation Provisions

FAR Provisions Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.204-7 System for Award Management- Registration.

2026-02

52.212-1 Instructions to Offerors-Commercial Products and Commercial Services.

2026-02

DFARS Provisions Incorporated by Reference

Date

Alternate Deviation

Variation Effective Date

252.203-7005 Representation Relating to Compensation of Former DoD Officials.

2022-09

252.204-7008 Compliance with Safeguarding Covered Defense Information Controls.

2016-10

252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements.

2023-11

252.204-7024 Notice on the Use of the Supplier Performance Risk System.

2023-03

252.225-7055 Representation Regarding Business Operations with the Maduro Regime.

2022-05

252.225-7059 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region-Representation.

2023-06

DFARS Provisions Incorporated by Full Text

Date

Alternate Deviation

Variation Effective Date

252.204-7016 Covered Defense Telecommunications Equipment or Services-Representation.

2019-12

COVERED DEFENSE TELECOMMUNICATIONS EQUIPMENT OR SERVICES-

REPRESENTATION (DEC 2019)

(a) Definitions. As used in this provision, "covered defense telecommunications equipment or services" has the meaning provided in the clause 252.204-7018, Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services.

(b) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for "covered defense telecommunications equipment or services".

(c) Representation. The Offeror represents that it [ ] does, [ ] does not provide covered defense telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument.

(End of provision)

252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services-Representation.

2021-05

PROHIBITION ON THE ACQUISITION OF COVERED DEFENSE

TELECOMMUNICATIONS EQUIPMENT OR SERVICES-REPRESENTATION (MAY 2021)

The Offeror is not required to complete the representation in this provision if the Offeror has represented in the provision at 252.204-7016, Covered Defense Telecommunications Equipment or Services-Representation, that it "does not provide covered defense telecommunications equipment or services as a part of its offered products or services to the

Government in the performance of any contract, subcontract, or other contractual instrument."

(a) Definitions. "Covered defense telecommunications equipment or services," "covered mission," "critical technology," and "substantial or essential component," as used in this provision, have the meanings given in the 252.204-7018 clause, Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services, of this solicitation.

(b)…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .