The document is a comprehensive General Conditions Structure spreadsheet for the Colorado Springs School District 11 (District 11) Construction Manager/General Contractor (CMGC) project involving the renovation of Palmer High School. The spreadsheet meticulously details the cost allocation and responsibilities across multiple project phases, including off-site services, on-site services, travel and lodging, temporary facilities, on-site utilities and services, equipment, vertical hoisting, temporary heating, reproduction and printing, quality control, permits and special fees, insurances and bonds, and other project-related costs.
The document provides a granular breakdown of potential costs, indicating whether they are not required, part of the basic fee, general conditions cost, direct cost of work, with A/E services, owner expense, or additional services. A notable detail is the school district's bond policy, which will only cover bonds for a maximum of 3-4 subcontractors, with any additional bonding not permitted in the Guaranteed Maximum Price (GMP). The spreadsheet serves as a comprehensive financial framework for the CMGC approach, offering detailed cost categorization and allocation strategies for the Palmer High School renovation project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Attachment 2 | ||||||||
| Colorado Springs D11 | ||||||||
| CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CMGC) | ||||||||
| GENERAL CONDITIONS STRUCTURE | ||||||||
| Phase: OFF-SITE SERVICES AND STAFF | Not Required | Basic Fee | General Conditions Cost | Direct Cost of Work | With A/E Services | Owner Expense | Additional Services | |
| 1 | Corporate Executives | X | ||||||
| 2 | Principal in Charge | X | ||||||
| 3 | Project Executive | X | ||||||
| 4 | Legal (Basic Service) | X | ||||||
| 5 | Project Manager | X | ||||||
| 6 | Accounting | X | ||||||
| 7 | Added Accounting for Lender | X | ||||||
| 8 | Scheduling | X | ||||||
| 9 | Special Lender Reporting | X | ||||||
| 10 | Life-Cycle | X | ||||||
| 11 | Energy Management | X | ||||||
| 12 | Production Engineering | X | ||||||
| 13 | Purchasing | X | ||||||
| 14 | Value Engineering | X | ||||||
| 15 | Systems Development | X | ||||||
| 16 | Estimating | X | ||||||
| 17 | Cost Engineers | X | ||||||
| 18 | Project Coordinator | X | ||||||
| 19 | Project Expediter | X | ||||||
| 20 | Drafting Detailer | X | ||||||
| 21 | Drawing Checker | X | ||||||
| 22 | Safety Officer | X | ||||||
| 23 | E.E.O. Officer | X | ||||||
| 24 | Secretarial | X | ||||||
| 25 | Clerk-Typist | X | ||||||
| 26 | Fringe Benefits for Above | X | ||||||
| 27 | Vacations for Above | X | ||||||
| 28 | Bonuses for Above (If Any) | X | ||||||
| 29 | Legal (Special Services Extras) | X |
| Colorado Springs D11 | ||||||||
| CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CMGC) | ||||||||
| GENERAL CONDITIONS STRUCTURE | ||||||||
| Phase: ON-SITE SERVICES AND STAFF | Not Required | Basic Fee | General Conditions Cost | Direct Cost of Work | With A/E Services | Owner Expense | Additional Services | |
| 1 | Project Manager (If Required) | X | ||||||
| 2 | Project Superintendent | X | ||||||
| 3 | General Superintendent (If Required) | X | ||||||
| 4 | Mechanical Coordinator (If Required) | X | ||||||
| 5 | Electrical Coordinator (If Required) | X | ||||||
| 6 | Project Engineer (If Required) | X | ||||||
| 7 | Office Engineer (If Required) | X | ||||||
| 8 | Scheduling Engineer (If Required) | X | ||||||
| 9 | Field Engineer (If Required) | X | ||||||
| 10 | Draftsman/Detailer (If Required) | X | ||||||
| 11 | Drawing Checker (If Required) | X | ||||||
| 12 | Field Accountant (If Required) | X | ||||||
| 13 | Time Keeper/Checker (If Required) | X | ||||||
| 14 | Scheduling Engineer (If Required) | X | ||||||
| 15 | Expediter (If Required) | X | ||||||
| 16 | Secretary (If Required) | X | ||||||
| 17 | Clerk-Typist (If Required) | X | ||||||
| 18 | Rodman and Helpers (If Required) | X | ||||||
| 19 | Safety Engineer (If Required) | X | ||||||
| 20 | E.E.O. Officer (If Required) | X | ||||||
| 21 | Independent Surveyor (If Required) | X | ||||||
| 22 | Personal Computer (If Required) | X | ||||||
| 23 | Copy Machine (If Required) | X | ||||||
| 24 | Fax Machine (If Required) | X | ||||||
| 25 | Fringe Benefits | X | ||||||
| 26 | Vacations for Above Staff | X | ||||||
| 27 | Bonuses for above (If Any) | X |
| Colorado Springs D11 | ||||||||
| CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CMGC) | ||||||||
| GENERAL CONDITIONS STRUCTURE | ||||||||
| Phase: TRAVEL AND LODGING | Not Required | Basic Fee | General Conditions Cost | Direct Cost of Work | With A/E Services | Owner Expense | Additional Services | |
| 1 | Off-Site Staff Travel Cost | X | ||||||
| 2 | Off-Site Staff Transportation | X | ||||||
| 3 | On-Site Project Manager Transportation | X | ||||||
| 4 | Superintendent's Transportation | X | ||||||
| 5 | Engineer's Transportation | X | ||||||
| 6 | Project Staff Moving Expense | X | ||||||
| 7 | Project Staff Subsistence Costs | X | ||||||
| 8 | Travel/Lodging Out of State | X |
| Colorado Springs D11 | ||||||||
| CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CMGC) | ||||||||
| GENERAL CONDITIONS STRUCTURE | ||||||||
| Phase: TEMPORARY FACILITIES | Not Required | Basic Fee | General Conditions Cost | Direct Cost of Work | With A/E Services | Owner Expense | Additional Services | |
| 1 | Safety Equipment | X | ||||||
| 2 | First Aid Supplies | X | ||||||
| 3 | Handrails and Toe Boards | X | ||||||
| 4 | Opening Protection | X | ||||||
| 5 | Fire Extinguishers | X | ||||||
| 6 | Watchman Service | X | ||||||
| 7 | Office or Trailer Rental | X | ||||||
| 8 | Storage or T+A215railer Rental | X | ||||||
| 9 | Waterboy-Ice-Cups | X | ||||||
| 10 | Temporary Toilets | X | ||||||
| 11 | Change/Shower Rooms | X | ||||||
| 12 | Lunch Rooms | X | ||||||
| 13 | Temporary Stairs | X | ||||||
| 14 | Temporary Enclosures | X | ||||||
| 15 | Fireproofing Enclosure | X | ||||||
| 16 | Concrete Work Enclosure | X | ||||||
| 17 | Masonry Work Enclosure | X | ||||||
| 18 | Temporary Building Heating | X | ||||||
| 19 | Project Signs | X | ||||||
| 20 | Bulletin Boards | X | ||||||
| 21 | Temporary Fencing | X | ||||||
| 22 | Covered Walkways | X | ||||||
| 23 | Barricades | X | ||||||
| 24 | Safety Nets | X | ||||||
| 25 | Ambulance Cost | X | ||||||
| 26 | Security Guard | X | ||||||
| 27 | Architect/Engineer Temporary Office | X |
| Colorado Springs D11 | ||||||||
| CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CMGC) | ||||||||
| GENERAL CONDITIONS STRUCTURE | ||||||||
| Phase: ON-SITE UTILITIES AND SERVICES | Not Required | Basic Fee | General Conditions Cost | Direct Cost of Work | With A/E Services | Owner Expense | Additional Services | |
| 1 | Telephone Installation | X | ||||||
| 2 | Telephone Expense | X | ||||||
| 3 | Temporary Power Service (If Required) | X | ||||||
| 4 | Power Expense | X | ||||||
| 5 | Temporary Water Service | X | ||||||
| 6 | Temporary Heating Service | X | ||||||
| 7 | Temporary Cooling Service | X | ||||||
| 8 | Heating Energy Charges | X | ||||||
| 9 | Cooling Energy Charges | X | ||||||
| 10 | Temporary Wiring | X | ||||||
| 11 | Light Bulbs | X | ||||||
| 12 | Weekly Cleanup | X | ||||||
| 13 | Final Cleanup | X | ||||||
| 14 | Dump Permits and Fees | X | ||||||
| 15 | Debris Hauling/Removal | X | ||||||
| 16 | Flagman/Traffic Control | X | ||||||
| 17 | Street/Walk Cleaning (If Required) | X | ||||||
| 18 | Dust Controls | X | ||||||
| 19 | Temporary Roads (If Required) | X | ||||||
| 20 | Roadway Maintenance (If Required) | X | ||||||
| 21 | Temporary Water Expense (If Required) | X | ||||||
| 22 | Temporary Sewer Expense | X | ||||||
| 23 | Two-Way Radio Equipment | X | ||||||
| 24 | Trash Chute and Hoppers | X | ||||||
| 25 | Architect/Engineer Telephone Charges | X |
| Colorado Springs D11 | ||||||||
| CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CMGC) | ||||||||
| GENERAL CONDITIONS STRUCTURE | ||||||||
| Phase: ON-SITE EQUIPMENT | Not Required | Basic Fee | General Conditions Cost | Direct Cost of Work | With A/E Services | Owner Expense | Additional Services | |
| 1 | Automobile and Fuel | X | ||||||
| 2 | Pickup Truck and Fuel | X | ||||||
| 3 | Flatbed Truck and Fuel | X | ||||||
| 4 | Water Truck and Fuel | X | ||||||
| 5 | Air Compressor and Fuel | X | ||||||
| 6 | Dewatering Equipment and Fuel | X | ||||||
| 7 | Generator and Fuel | X | ||||||
| 8 | Debris Removal/Hauling Equipment | X | ||||||
| 9 | Snow Removal Equipment | X | ||||||
| 10 | Tire and Maintenance Cost for Above | X | ||||||
| 11 | Welder and Fuel | X | ||||||
| 12 | Welding Equipment and Fuel | X | ||||||
| 13 | Cutter Torches and Fuel | X | ||||||
| 14 | Office Rentals or Cost | X | ||||||
| 15 | Storage Rentals or Cost | X | ||||||
| 16 | Small Tools Purchase | X | ||||||
| 17 | Small Equipment Rental | X | ||||||
| 18 | Office Furniture Rental | X | ||||||
| 19 | Fax Machine and Supplies (If Required) | X | ||||||
| 20 | Copy Machine and Supplies (If Required) | X | ||||||
| 21 | Office Equipment and Supplies (If Required) | X |
| Colorado Springs D11 | ||||||||
| CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CMGC) | ||||||||
| GENERAL CONDITIONS STRUCTURE | ||||||||
| Phase: VERTICAL HOISTING | Not Required | Basic Fee | General Conditions Cost | Direct Cost of Work | With A/E Services | Owner Expense | Additional Services | |
| 1 | Hoist and Tower Rental | X | ||||||
| 2 | Small Material Hoist Rental | X | ||||||
| 3 | Hoist Landings and Fronts | X | ||||||
| 4 | Hoist Operators | X | ||||||
| 5 | Hoist Safety Inspections | X | ||||||
| 6 | Hoist Materials Skips | X | ||||||
| 7 | Hoist Material Hoppers | X | ||||||
| 8 | Erect and Dismantle Hoists | X | ||||||
| 9 | Fuel Repairs and Maintenance | X | ||||||
| 10 | Hoist Communications | X | ||||||
| 11 | Crane Rental | X | ||||||
| 12 | Crane Operators | X | ||||||
| 13 | Crane Safety Inspections | X | ||||||
| 14 | Erect and Dismantle Crane | X | ||||||
| 15 | Fuel, Repairs, Maintenance | X | ||||||
| 16 | Crane Raising/Jumping Cost | X | ||||||
| 17 | Temporary Elevator Rental | X | ||||||
| 18 | Elevator Operations Cost | X | ||||||
| 19 | Elevator Repairs and Maintenance | X | ||||||
| 20 | Cage Rider at Elevator | X | ||||||
| 21 | Safety Inspections | X | ||||||
| 22 | Forklift Rental | X | ||||||
| 23 | Forklift Operators | X | ||||||
| 24 | Forklift Safety Inspections | X | ||||||
| 25 | Fuel, Repairs, Maintenance | X | ||||||
| 26 | Elevator Service Costs | X | ||||||
| 27 | Crane/Hoist Inspections | X | ||||||
| 28 | Erections/Removal of Above | X |
| Colorado Springs D11 | ||||||||
| CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CMGC) | ||||||||
| GENERAL CONDITIONS STRUCTURE | ||||||||
| Phase: TEMPORARY HEATING (If Required) | Not Required | Basic Fee | General Conditions Cost | Direct Cost of Work | With A/E Services | Owner Expense | Additional Services | |
| 1 | Remove Snow and Ice | X | ||||||
| 2 | Partitions and Enclosures | X | ||||||
| 3 | Piping Cost in Building | X | ||||||
| 4 | Fuel Cost for Heating | X | ||||||
| 5 | Power Cost for Heating | X | ||||||
| 6 | Steam Purchase Cost | X | ||||||
| 7 | Furnace Rental | X | ||||||
| 8 | Heater Rental | X | ||||||
| 9 | Boiler Rental | X | ||||||
| 10 | Operator (Temporary System) | X | ||||||
| 11 | Operator (Permanent System) | X | ||||||
| 12 | Operation Fire Watch | X | ||||||
| 13 | Cleaning Costs | X | ||||||
| 14 | Maintenance Cost | X | ||||||
| 15 | Warranty Cost | X | ||||||
| 16 | Filter Change | X | ||||||
| 17 | Temporary Office Heating | X | ||||||
| 18 | Lunch Room Heating | X | ||||||
| 19 | Change/Shower Room Heating | X | ||||||
| 20 | Temporary Enclosures | X | ||||||
| 21 | Temporary Partitions | X | ||||||
| 22 | Temporary Exterior Enclosure | X | ||||||
| 23 | Enclosure Moving/Maintenance | X |
| Colorado Springs D11 | ||||||||
| CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CMGC) | ||||||||
| GENERAL CONDITIONS STRUCTURE | ||||||||
| Phase: REPRODUCTION AND PRINTING | Not Required | Basic Fee | General Conditions Cost | Direct Cost of Work | With A/E Services | Owner Expense | Additional Services | |
| 1 | Cost Study Documents | X | ||||||
| 2 | Systems Study Documents | X | ||||||
| 3 | Bid Package Documents | X | ||||||
| 4 | Bidding Instructions | X | ||||||
| 5 | Construction Documents | X | ||||||
| 6 | Postage and Express Costs | X | ||||||
| 7 | As-Built Documents (Drafting) | X | ||||||
| 8 | As-Built Documents (Printing) | X | ||||||
| 9 | Accounting Forms | X | ||||||
| 10 | Field Reporting Forms | X | ||||||
| 11 | Contract Agreements | X | ||||||
| 12 | Schedule Report Forms | X | ||||||
| 13 | Estimating Forms | X | ||||||
| 14 | Cost Reporting Forms | X | ||||||
| 16 | Presentation Charts and Graphics | X | ||||||
| 17 | Data Processing (in House) | X | ||||||
| 18 | Reference Materials | X | ||||||
| 19 | Duplication Expense (Miscellaneous) | X | ||||||
| 20 | Shop Drawing Printing | X | ||||||
| 21 | Date Processing (Outside Services) | X | ||||||
| 22 | Maintenance Manuals | X | ||||||
| 23 | Operation Manuals | X | ||||||
| 24 | Special Forms | X | ||||||
| 25 | As-Built Record (Field) | X | ||||||
| 26 | As-Built Master Drafting | X |
| Colorado Springs D11 | ||||||||
| CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CMGC) | ||||||||
| GENERAL CONDITIONS STRUCTURE | ||||||||
| Phase: QUALITY CONTROL | Not Required | Basic Fee | General Conditions Cost | Direct Cost of Work | With A/E Services | Owner Expense | Additional Services | |
| 1 | Chief Inspector | X | ||||||
| 2 | Field Inspector | X | ||||||
| 3 | Inspectors Office | X | ||||||
| 4 | Inspectors Transportation | X | ||||||
| 5 | Inspectors Equipment | X | ||||||
| 6 | Special Inspection Consultants | X | ||||||
| 7 | Special Testing Consultants | X | ||||||
| 8 | Concrete Testing | X | ||||||
| 9 | Masonry Testing | X | ||||||
| 10 | Compaction Testing | X | ||||||
| 11 | Welding Testing | X | ||||||
| 12 | Welding Inspections | X | ||||||
| 13 | Fireproofing Inspections | X | ||||||
| 14 | Soils Investigations | X | ||||||
| 15 | Special Testing Services | X | ||||||
| 16 | Supplies and Materials (Field Office) | X | ||||||
| 17 | Project Photographs | X | ||||||
| 18 | Warranty Inspections Coordination | X | ||||||
| 19 | Air and Water Balancing | X | ||||||
| 20 | Operator On-Site Training | X | ||||||
| 21 | Operation & Maintenance Manual Coordination | X | ||||||
| 22 | Prepare Operations Manuals | X | ||||||
| 23 | Prepare Maintenance Manuals | X |
| Colorado Springs D11 | ||||||||
| CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CMGC) | ||||||||
| GENERAL CONDITIONS STRUCTURE | ||||||||
| Phase: PERMITS AND SPECIAL FEES | Not Required | Basic Fee | General Conditions Cost | Direct Cost of Work | With A/E Services | Owner Expense | Additional Services | |
| 1 | Storage Yard Rental | X | ||||||
| 2 | Parking Lot Rentals | X | ||||||
| 3 | Parking Fees | X | ||||||
| 4 | Curb and Gutter Permits | X | ||||||
| 5 | Sign Permits | X | ||||||
| 6 | Staking Fees | X | ||||||
| 7 | Sidewalk Permits | X | ||||||
| 8 | Landscape Permits | X | ||||||
| 9 | Street/Curb Design Charge | X | ||||||
| 10 | Building Permits | X | ||||||
| 11 | Plan Check Fees | X | ||||||
| 12 | Water Connection Fee | X | ||||||
| 13 | Sanitary Fee | X | ||||||
| 14 | Storm Connection Fee | X | ||||||
| 15 | Gas Service Charge | X | ||||||
| 16 | Power Service Charge | X | ||||||
| 17 | Steam Service Charge | X | ||||||
| 18 | Chiller Water Service Charge | X | ||||||
| 19 | Special Tap Fees | X | ||||||
| 20 | Contractors Licenses | X | ||||||
| 21 | Royalties | X | ||||||
| 22 | Zoning Fees/Consultants | X | ||||||
| 23 | Use Fees | X | ||||||
| 24 | Construction Equipment Licenses | X | ||||||
| 25 | Construction Equipment Permits | X | ||||||
| 26 | Street Bonds/Permits | X | ||||||
| 27 | AGC/ABC Project Fees | X |
| Colorado Springs D11 | |||||||||
| CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CMGC) | |||||||||
| GENERAL CONDITIONS STRUCTURE | |||||||||
| Phase: INSURANCES AND BONDS | Not Required | Basic Fee | General Conditions Cost | Direct Cost of Work | With A/E Services | Owner Expense | Additional Services | ||
| 1 | Builders Risk Insurance | X | |||||||
| 2 | Errors and Omissions | X | |||||||
| 3 | General Liability | X | |||||||
| 4 | Product Liability | X | |||||||
| 5 | Excess Liability Coverage | X | |||||||
| 6 | Workmen's Compensation | X | |||||||
| 7 | FICA Insurance | X | |||||||
| 8 | Federal Employment | X | |||||||
| 9 | State Unemployment | X | |||||||
| 10 | Payment Bond | X | |||||||
| 11 | Performance Bond | X | |||||||
| 12 | Street/Property Bonds | X | |||||||
| 13 | State/Local Bonds | X | |||||||
| 14 | Contractors Bonds | X | |||||||
| 15 | Warrantee Bond Costs | X | |||||||
| 16 | Subcontractor Bonds: | ||||||||
| Note: The school district will only allow a maximum of 3-4 subcontractors to be bonded for which the district will pay for the bonds. Any bonding of subcontractors in excess of 4 cannot be included in the GMP. | X | ||||||||
| 17 | Off-Site Staff Insurance | X | |||||||
| 18 | Off-Site Staff Taxes | X |
| Colorado Springs D11 | ||||||||
| CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CMGC) | ||||||||
| GENERAL CONDITIONS STRUCTURE | ||||||||
| Phase: OTHER COSTS | Not Required | Basic Fee | General Conditions Cost | Direct Cost of Work | With A/E Services | Owner Expense | Additional Services | |
| 1 | Project Taxes (On Construction Work) | X | ||||||
| 2 | Construction Equipment | X | ||||||
| 3 | Construction Services | X | ||||||
| 4 | Construction Materials | X | ||||||
| 5 | Cost of Design and Engineering | X | ||||||
| 6 | A/E Cost for Bid Packages | X | ||||||
| 7 | A/E Fast Track Cost Extras | X | ||||||
| 8 | Preliminary Soils Investigations | X | ||||||
| 9 | Title/Development Cost | X | ||||||
| 10 | Land Costs | X | ||||||
| 11 | Financing/Interest Cost | X | ||||||
| 12 | Interim Financing Costs | X | ||||||
| 13 | Owner Change Contingency | X | ||||||
| 14 | Building Operation after Move-In | X | ||||||
| 15 | Building Maintenance after Move-In | X | ||||||
| 16 | Moving Coordination | X | ||||||
| 17 | Moving Costs | X | ||||||
| 18 | Corrective Work Extra | X | ||||||
| 19 | Costs of Emergency Work | X | ||||||
| 20 | CMGC Overhead Cost | X | ||||||
| 21 | CMGC Profit Margin | X | ||||||
| 22 | GMP Financial Responsibility | X | ||||||
| 23 | Late Payment Interest | X | ||||||
| 24 | Environmental Impact Studies | X |