S02 36C26126Q0697 Elevator - REVISED.pdf
PDF 764 KB Posted
- Attached to
- Elevator Maintenance | VAPAHCS Federal contract opportunity
- Solicitation number
- 36C26126Q0697
About this file
This is a Solicitation/Contract/Order for Commercial Products and Commercial Services (Standard Form 1449) issued by the Department of Veterans Affairs Network Contracting Office 21 for elevator maintenance and inspection services at the VA Palo Alto Health Care System.
The contract is set-aside 100 percent for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) with a solicitation number of 36C26126Q0697, issued June 12, 2026, with offers due July 2, 2026 at 10:00 AM PDT. The contract value is estimated at $22 million for a firm fixed price contract covering a base year (August 1, 2026 – July 31, 2027) plus three option years. Services include semi-annual, annual, and four-year inspection services for elevators at four VA facility locations: Palo Alto Main Campus, Menlo Park Medical Center, Mountain View Center, and Livermore Medical Center. The contractor must be ASME/NAESA qualified with at least five years of experience as a certified elevator inspector. All work must comply with ASME A17.1 and A17.2 standards, NFPA codes, and OSHA requirements. The contract prohibits subcontracting and requires monthly preventive maintenance inspections plus unscheduled maintenance repairs (not to exceed $200,000 per year). Electronic invoice submission is required through VA's Financial Services Center. Offerors must submit three volumes: technical capability documentation, past performance information, and completed pricing schedule. Award will be made to the SDVOSB offering the best value considering technical capability, past performance, and price.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C26126Q0697 - REVISED 6292026.pdf | ||
| 36C26126Q0697 0003.pdf | ||
| ELEVATOR INVENTORY 6292026.xlsx | XLSX spreadsheet | |
| 36C26126Q0697 0002.pdf | ||
| 36C26126Q0697 0001.pdf | ||
| Elevator_Inventory Attachment 1 revised.xlsx | XLSX spreadsheet | |
| Elevator PWS-6-15-2026.pdf | ||
| QASP .pdf | ||
| Wage Determination 2015-5623 - ALAMEDA.pdf | ||
| ATTACHMENT A AUTOMATIC DOOR INVENTORY.docx | DOCX document | |
| Wage Determination 2015-5641 - SANTA CLARA.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAGE 1 OF 1. REQUISITION NO.
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NO. 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
a. NAME b. TELEPHONE NO. (No Collect Calls) 8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY CODE 10. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: % FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ IFB RFP
15. DELIVER TO CODE 16. ADMINISTERED BY CODE
17a. CONTRACTOR/OFFEROR CODE FACILITY CODE 18a. PAYMENT WILL BE MADE BY CODE
TELEPHONE NO. UEI: EFT:
PHONE: FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19. 20. 21. 22. 23. 24.
ITEM NO. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA ARE ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________ 29. AWARD OF CONTRACT: REF. ___________________________________ OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DATED ________________________________. YOUR OFFER ON SOLICITATION
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION (REV. NOV 2021)
PREVIOUS EDITION IS NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
36C26126Q0697 06-12-2026
Maricela.Berrones-Gauger@va.gov 559-225-6100 6792 07-02-2026
10AM PDT
Department of Veterans Affairs
Network Contracting Office (NCO) 21
X 100
X
238290
$22 Million
N/A
See Performance Work Statement
93721
FMS-VA-2(101) Financial Services Center
PO BOX 149971
Austin TX 78714-9971
See CONTINUATION Page
Contractor to provide elevator maintenance services for the
VA Palo Alto Health Care System in accordance with the
Performance Work Statement.
Period of Performance: 08/01/2026 - 07/31/2031
Base Year: 08/01/2026 - 07/31/2027
Option Year 1: 08/01/2027 - 07/31/2028
Option Year 2: 08/01/2028 - 07/31/2029
Option Year 3: 08/01/2029 - 07/31/2030
See CONTINUATION Page
Maricela Berrones-Gauger
Contracting Officer
36C26126Q0697
Table of Contents
SECTION A
A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS
AND COMMERCIAL SERVICES
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
B.2 PRICE/COST SCHEDULE
ITEM INFORMATION
SECTION C - CONTRACT CLAUSES
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS
AND COMMERCIAL SERVICES (NOV 2023) (DEVIATION OCT 2025)
C.2 52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)
C.3 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000) ... 21
C.4 SUPPLEMENTAL INSURANCE REQUIREMENTS
C.5 52.240-91 SECURITY PROHIBITIONS AND EXCLUSIONS (NOV 2025)
(DEVIATION)
C.6 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
C.8 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED
SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023)
(DEVIATION)
C.9 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—
CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023)
(DEVIATION)
C.10 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS
(NOV 2018)
SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS
SECTION E - SOLICITATION PROVISIONS
E.1 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS AND
COMMERCIAL SERVICES (SEP 2023) (DEVIATION OCT 2025)
E.2 52.216-1 TYPE OF CONTRACT (NOV 2025) (DEVIATION)
E.3 52.233-2 SERVICE OF PROTEST (DEVIATION NOV 2025)
E.4 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB
1998)
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
1. Contract Administration: All contract administration matters will be handled by the following individuals:
a. CONTRACTOR:
b. GOVERNMENT: Contracting Officer 36C261
2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:
[X] 52.232-33, Payment by Electronic Funds Transfer—System For Award
Management, or [] 52.232-36, Payment by Third Party
3. INVOICES: Invoices shall be submitted in arrears:
a. Quarterly []
b. Semi-Annually []
c. Other []
4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.
ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:
AMENDMENT NO DATE
B.2 PRICE/COST SCHEDULE
ITEM INFORMATION
ITEM
NUMBER
DESCRIPTION OF
SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 12.00 MO __________________ __________________
Service, Maintenance, and Inspection - PAD,MPD,LVD for Palo Alto, Menlo Park, Livermore, Mountain View Contract Period: Base POP Begin: 08-01-2026 POP End: 07-31-2027 PRINCIPAL NAICS CODE: 238290 - Other Building Equipment Contractors PRODUCT/SERVICE CODE: J036 - Maintenance, Repair, and Rebuilding of Equipment - Special Industry Machinery
MANUFACTURER PART NUMBER (MPN): N/A
0002 1.00 HR __________________ __________________
Estimated Unscheduled Maintenance and Repair of all Elevators
PER PWS NTE $200K
Contract Period: Base POP Begin: 08-01-2026 POP End: 07-31-2027 PRINCIPAL NAICS CODE: 238290 - Other Building Equipment Contractors PRODUCT/SERVICE CODE: J036 - Maintenance, Repair, and Rebuilding of Equipment - Special Industry Machinery
MANUFACTURER PART NUMBER (MPN): N/A
1001 12.00 MO __________________ __________________
Service, Maintenance, and Inspection - PAD,MPD,LVD for Palo Alto, Menlo Park, Livermore, Mountain View Contract Period: Option 1 POP Begin: 08-01-2027 POP End: 07-31-2028 PRINCIPAL NAICS CODE: 238290 - Other Building Equipment Contractors PRODUCT/SERVICE CODE: J036 - Maintenance, Repair, and Rebuilding of Equipment - Special Industry Machinery
MANUFACTURER PART NUMBER (MPN): N/A
1002 1.00 HR __________________ __________________
Estimated Unscheduled Maintenance and Repair of all Elevators
PER PWS NTE $200K
Contract Period: Option 1
POP Begin: 08-01-2027 POP End: 07-31-2028 PRINCIPAL NAICS CODE: 238290 - Other Building Equipment Contractors PRODUCT/SERVICE CODE: J036 - Maintenance, Repair, and Rebuilding of Equipment - Special Industry Machinery
MANUFACTURER PART NUMBER (MPN): N/A
2001 12.00 MO __________________ __________________
Service, Maintenance, and Inspection - PAD,MPD,LVD for Palo Alto, Menlo Park, Livermore, Mountain View Contract Period: Option 2 POP Begin: 08-01-2028 POP End: 07-31-2029 PRINCIPAL NAICS CODE: 238290 - Other Building Equipment Contractors PRODUCT/SERVICE CODE: J036 - Maintenance, Repair, and Rebuilding of Equipment - Special Industry Machinery
MANUFACTURER PART NUMBER (MPN): N/A
2002 1.00 HR __________________ __________________
Estimated Unscheduled Maintenance and Repair of all Elevators
PER PWS NTE $200K
Contract Period: Option 2 POP Begin: 08-01-2028 POP End: 07-31-2029 PRINCIPAL NAICS CODE: 238290 - Other Building Equipment Contractors PRODUCT/SERVICE CODE: J036 - Maintenance, Repair, and Rebuilding of Equipment - Special Industry Machinery
MANUFACTURER PART NUMBER (MPN): N/A
3001 12.00 MO __________________ __________________
Service, Maintenance, and Inspection - PAD,MPD,LVD for Palo Alto, Menlo Park, Livermore, Mountain View Contract Period: Option 3 POP Begin: 08-01-2029 POP End: 07-31-2030 PRINCIPAL NAICS CODE: 238290 - Other Building Equipment Contractors PRODUCT/SERVICE CODE: J036 - Maintenance, Repair, and Rebuilding of Equipment - Special Industry Machinery
MANUFACTURER PART NUMBER (MPN): N/A
3002 1.00 HR __________________ __________________
Estimated Unscheduled Maintenance and Repair of all Elevators
PER PWS NTE $200K
Contract Period: Option 3 POP Begin: 08-01-2029 POP End: 07-31-2030 PRINCIPAL NAICS CODE: 238290 - Other Building Equipment Contractors PRODUCT/SERVICE CODE: J036 - Maintenance, Repair, and Rebuilding of Equipment - Special Industry Machinery
MANUFACTURER PART NUMBER (MPN): N/A
GRAND TOTAL __________________
B.2 PERFORMANCE WORK STATEMENT
Elevator Inspections
VA Palo Alto Health Care System
Section 1: General Information
1.1 General: This is a non-personal services contract to provide semi-annual, annual, and 4 year inspection services to the Elevators for the VA Palo Alto Health Care System (VAPAHCS).
The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.
1.2 Period of Performance:
A. Period of performance shall be base year plus four option years.
a. Base Year: August 1, 2026 to July 31, 2027
b. Option Year 1: August 1, 2027 to July 31, 2028
c. Option Year 2: August 1, 2028 to July 31, 2029
d. Option Year 3: August 1, 2029 to July 31, 2030
1.3 Place of Performance: Services are required at the following locations. The points of contact (POC) for each location are listed. All work must be coordinated with the COR.
Palo Alto Main Campus
3801 Miranda Ave.
Palo Alto, CA 94304
POC: Hector Aquino
Machuca
(650) 709-5630
Menlo Park Medical Center
795 Willow Rd.
Menlo Park, CA 94025
POC: Ronald Nielson
(650) 465-5121
Mountain View Center
1776 Old Middlefield Way
Mountain View, CA 94043
POC: Ronald Nielson
(650) 465-5121
Livermore Medical Center
4951 Arroyo Rd.
Livermore, CA 94550
POC: Don Jasch
(650) 285-9610
1.4 Hours of Operation: All inspections shall be performed during business hours of 8:00 AM to
4:30 PM Monday through Friday, except Federal Holidays. Contractor may work outside normal business hours by arrangement with the COR if such services are provided without additional charge to the government.
1.4.1 Observed Federal Holidays
• New Year’s Day
• Labor Day
• Martin Luther King Jr.’s Birthday
• Columbus Day
• President’s Day
• Veteran’s Day
• Memorial Day
• Thanksgiving Day
• Juneteenth Day
• Christmas Day
• Independence Day
1.5 Type of Contract: The government will award a Firm Fixed Price contract.
1.6 Invoicing: All invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.
VA’s Electronic Invoice Presentment and Payment System – The FSC uses a third-party contractor, Tungsten, to transition vendors from paper to electronic invoice submission.
Please go to this website: http://www.tungsten-network.com/US/en/veterans-affairs/ to begin submitting electronic invoices, free of charge.
More information on the VA Financial Services Center is available at http://www.fsc.va.gov/einvoice.asp.
Vendor e-Invoice Set-Up Information:
Please contact Tungsten at the phone number or email address listed below to begin submitting your electronic invoices to the VA Financial Services Center for payment processing, free of charge. If you have question about the e-invoicing program or
Tungsten, please contact the FSC at the phone number or email address listed below:
• Tungsten e-Invoice Setup Information: 1-877-489-6135
• Tungsten e-Invoice email: VA.Registration@Tungsten-Network.com
• FSC e-Invoice Contact Information: 1-877-353-9791
• FSC e-invoice email: vafsccshd@va.gov
1.6.1 Payments: Government will only paid for services rendered. Government will not pay on any uncompleted or undelivered work, services, or goods.
Section 2: Definitions & Acronyms http://www.tungsten-network.com/US/en/veterans-affairs/ http://www.fsc.va.gov/einvoice.asp mailto:VA.Registration@Tungsten-Network.com mailto:vafsccshd@va.gov
2.1 Definitions:
Contractor. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.
Subcontractor. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
Work Day. The number of hours per day the Contractor provides services in accordance with the contract.
Work Week. Monday through Friday, unless specified otherwise.
2.2 Acronyms:
COR Contracting Officer Representative
NFPA National Fire Protection Association
OEM Original Equipment Manufacturer
OSHA Occupational Safety and Health Administration
POC Point of Contact
PM Preventative Maintenance
PMI Preventative Maintenance Inspection
VA Veterans Affairs
VAPAHCS Veterans Affairs Palo Alto Health Care System
Section 3: Government Furnished Property, Equipment, and Services
A. This PWS does not have any government furnish equipment. Contractor shall not use any government own equipment, material, supplies, or tools. Contractor shall furnish all requirements. The government reserves option to terminate the contract in the event that contractor uses government equipment or supplies without written approval from the
Contracting Officer and COR.
B. Elevator Maintenance Company shall provide elevator technician and weights as required for all inspections.
Section 4: Contractor Furnished Items and Services
The Contractor shall provide all equipment, supplies, management, supervision, personnel, and transportation necessary to assure that all services are in accordance with the contract and all applicable laws and regulations. The contractor shall ensure all work meets performance standards specified in this Performance Work Statement (PWS) and referenced documents to include all notes, explanatory material, and appendixes.
4.1 Contractors Qualifications:
A. Contractor shall be an ASME/NAESA qualified elevator inspector with at least five years of experience as a certified elevator inspector. Contractor shall submit in technical package all certifications and licenses. The Government reserves the right to request and review licenses and certification during the contract period.
B. This contract does not permit subcontracts.
4.2 Qualify Personnel:
A. Contractor’s employees shall be an ASME/NAESA qualified elevator inspector with at least five years of experience as a certified elevator inspector. The Government reserves the right to request and review licenses and certification during the contract period.
Section 5: Specific Tasks
5.1 Inspections:
A. Contractor shall provide all labor, equipment, and tools to perform five year, annual, and semi-annual inspections of the vertical transportation system at locations describe in section 1.3.
B. Contractor shall inspect all elevator listed in attachment A.
C. Contractor shall perform at lease one 4 year inspection per elevator during the life of the contract which will include .
D. Annual inspections are due in beginning and before the end of that year contract.
E. Semi inspections are due in February.
F. Contractor shall provide to the COR a schedule of the semi-annual, annual, and 4 year inspections 15 days form awarded date.
G. Contractor shall submit a request to proceed with inspection 30 day in advance. Date can change due to the availability of the elevator company. COR will confirm any changes to the schedule.
H. Contractor shall be made available no later than 2 business days from notification for additional onsite consultation and to clarify questions that may have arisen as a result of inspection at no additional charge to the government.
I. Contractor shall be available by phone, fax, or email for consultation during normal business hours at no addition cost to the government.
J. Contractor shall provide a writing analysis of each elevator: life cycle, life expectancy of equipment, recommendation of equipment replacement, recommendations of communication and network upgrades and other factors that VAPAHCS requires.
Contractor and COR shall agree on factors at no additional cost to the government.
K. Unscheduled maintenance listed on the price schedule shall be utilized when an inspection, equipment malfunction, or operational failure identifies a repair requirement that is outside of the scope of routine preventive maintenance performed under this contract. Unscheduled maintenance would be repairs that cannot be addressed through scheduled maintenance activities.
L. Work performed under unscheduled maintenance shall be authorized on a case by case basis by the COR prior to performance. The contractor shall provide a description of the repair requirement, recommend corrective actions, and estimated cost and repair time for Government review and approval. Unscheduled maintenance is intended to provide a mechanism for addressing non-routine repair requirements identified during performance of the contract and is not intended to cover routine maintenance or preventive maintenance included under the contract.
M. Contractor shall conduct inspection in accordance with ASME A17.1 and A17.2 most current edition.
N. Contractor shall provide one print book and an electronic downloadable copy of ASME
A17.1 and A17.2 most current edition for each base and option year.
5.2 Site Investigation and Conditions Affecting the Work
A. The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to (1) conditions bearing upon transportation, disposal, handling, and storage of materials; (2) the availability of labor, water, eclectic power, and roads; (3) uncertainties of weather, river stages, tides, or similar physical conditions at the site; (4) the conformation and condition of the ground; and (5) the character of equipment and facilities needed preliminary to and during work performance. The Contractor also acknowledges that it has satisfied itself as to the character, quality , and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the , including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relive the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.
B. The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this contract.
C. Contractor has the responsibility to make the determination and request a site walk.
Failure to perform a site walk shall not relieve the contractor to complete the contract on time and within budget
5.3 Contract Modifications
A. Throughout the performance of this contract, the addition or removal of elevators may be necessary. Please note that the government will not negotiate on modifications related to the addition or removal of elevators. Any such changes must be strictly managed through the Contracting Officer's authorization to ensure they fall within the contract scope and that pricing is fair and reasonable. The Contracting Officer will issue a written modification to the contract to capture these changes.
5.4 Safety:
A. At a minimum contractor, subcontract, and personnel shall wear at all times hard hat, safety glasses, reflective vest, and safety shoes.
B. No shorts or tank tops shall be permitted.
C. Contractor shall adhere to OSHA 10 CFR 1910.
D. Contractor shall be responsible to use appropriate PPE when required by the OSHA and
VAPAHCS.
E. Safety plan shall be submit to the COR within 15 days of awarded contract.
F. Contractor shall submit Safety Data Sheet for all chemical used at the VAPAHCS.
Chemicals must be approved by COR or Safety Services. Safety Data Sheet shall be kept at work site at all times.
G. Contractor shall comply with Environment Protection Agency standards. No dumping of water or chemical in the storm drains. Contaminates shall be removed from VAPAHCS property and shall be disposed of per all Federal, State, and Local EPA regulation and standards at no additional cost to the government.
a. Any penalties incurred due to unlawful disposal of hazardous material or EPA, State, or Local regulation and standards shall be the responsibility of the
Contractor.
5.5 Performance Standards:
A. Contractor shall adhere to the performance standards listed below. Contractor shall adhere to all references in the performance standard to include all notes, explanatory material, and appendixes. The most current edition will be used on all references listed below.
a. ASME A17.1: Safety Code for Elevator and Escalator
b. ASME A17.2: Inspectors’ Manual for Elevator and Escalator
c. NFPA 25: Standard for the Inspection, Testing, and Maintenance of Water-
Based Fire Protection Systems
d. NFPA 70: National Electrical Code
e. NFPA 99: Standard for Health Care Facility
f. OSHA Standard 29 CFR 1910
5.6 Documentation Requirements
A. The Contractor shall provide reports to the COR and Compliance Office.
B. Each report shall include a separate document for each elevator inspected. The report shall state the following
a. Location of inspection
b. Identifying device number
c. The type of device
d. All ASME deficiencies
e. Reference section and the number or letter designation of deficiencies
f. Heading and space to indicate scheduled date of repair
g. Actual date of repair
h. Date of inspection
i. Recommendations and comments
C. All recommended upgrades shall be listed and identified as recommended upgrades on the same document.
D. Contractor shall also include ASME checklist for inspection of electric elevators which shall be completed for every elevator inspected.
E. Contractor shall also include ASME checklist for inspection of hydraulic elevators which shall be completed for every elevator inspected.
F. Contractor shall provide a certificate for every elevator and device inspection. At a minimum shall have the following information on the certificate:
a. Building
b. Device number
c. Type of duty
d. City
e. Capacity
f. Speed
g. Date of inspection
h. Elevator mechanic and/or elevator maintenance company
i. Elevator inspector’s signature
j. Inspector qualified elevator inspector’s number
G. Invoices for approved work shall indicate, individual part(s) used, cost of individual part(s), and total part(s) cost.
H. Service Report(s) shall have the at a minimum the following:
a. Company name, address, telephone, and fax number.
b. VA contract number, name and number of the VA Contracting Officer.
c. Date and Time of work.
d. Copies of contractor’s valid licenses, professional and training certificates.
e. Location, type, name, and model of devices tested.
f. Description of work items.
g. Test data.
h. Remarks on conditions of devices and systems.
i. List of all deficiencies, if any, with time frame for repairs or replacement, and cost.
j. Recommended corrective actions, if any.
I. Submit One (1) hard copy of the completed written report and one downloadable electronic version of the report in Microsoft (i.e. excel, word..) format to the Engineering
Compliance Office within seven (7) calendar days of completion of inspection and testing.
5.7 Security Requirements
A. The Certification and Accreditation requirements do not apply and a Security
Accreditation Package is not required for this work.
B. Contractors, contractor personnel, subcontractors, and subcontractor personnel shall be subject to the same Federal laws, regulations, standards, VA directives and handbooks as VA personnel regarding information security under VA Handbook 6500.6, Contract
Security, Appendix C.
SECTION C - CONTRACT CLAUSES
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL
PRODUCTS AND COMMERCIAL SERVICES (NOV 2023) (DEVIATION OCT
2025)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The
Government must exercise its post-acceptance rights—
(1) Within a reasonable time after the defect was discovered or should have been discovered;
and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims
Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the
Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation (FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the
Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the
Contracting Officer of the cessation of such occurrence.
(g) Invoice.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by
Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.—
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt
Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-
5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting
Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the
Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if—
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in FAR 32.608-2 in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the
Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The
Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the
Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.
(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain
Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.
(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services.
(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with
Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;
(3) The clause at 52.212-5.
(4) Addenda to this solicitation or contract, including any license agreements for computer software.
(5) Solicitation provisions if this is a solicitation.
(6) Other paragraphs of this clause.
(7) The Standard Form 1449.
(8) Other documents, exhibits, and attachments
(9) The specification.
(t) [Reserved]
(u) Unauthorized Obligations.
(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service
(TOS), or similar legal instrument or agreement, that includes any clause requiring the
Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:
(i) Any such clause is unenforceable against the Government.
(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.
(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.
(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.
(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of Clause)
ADDENDUM to FAR 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL
PRODUCTS AND COMMERCIAL SERVICES
Clauses that are incorporated by reference (by Citation Number, Title, and Date), have the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.
The following clauses are incorporated into 52.212-4 as an addendum to this contract:
C.2 52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)
The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor within 30 days of contract expiring.
(End of Clause)
C.3 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR
2000)
(a) The Government may extend the term of this contract by written notice to the Contractor within 30 days of contract expiring; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 30 days before the contract expires. The preliminary notice does not commit the Government to an extension.
(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.
(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed four (4) years.
(End of Clause)
C.4 SUPPLEMENTAL INSURANCE REQUIREMENTS
In accordance with FAR 28.307-2 and FAR 52.228-5, the following minimum coverage shall apply to this contract:
(a) Workers' compensation and employers liability: Contractors are required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 is required, except in States with exclusive or monopolistic funds that do not permit workers' compensation to be written by private carriers.
(b) General Liability: $500,000.00 per occurrences.
(c) Automobile liability: $200,000.00 per person; $500,000.00 per occurrence and $20,000.00 property damage.
(d) The successful bidder must present to the Contracting Officer, prior to award, evidence of general liability insurance without any exclusionary clauses for asbestos that would void the general liability coverage.
(End of Clause)
C.5 52.240-91 SECURITY PROHIBITIONS AND EXCLUSIONS (NOV 2025)
(DEVIATION)
(a) Definitions. As used in this clause—
American Security Drone Act-covered foreign entity means an entity included on a list that the
Federal Acquisition Security Council (FASC) develops and maintains and publishes in the
System for Award Management (SAM) at https://www.sam.gov (section 1822 of Pub. L. 118-31, 41 U.S.C. 3901 note prec.).
Backhaul means intermediate links between the core network, or backbone network, and the small subnetworks at the edge of the network (e.g., connecting cell phones/towers to the core telephone network). Backhaul can be wireless (e.g., microwave) or wired (e.g., fiber optic, coaxial cable, Ethernet).
Covered application means the social networking service TikTok or any successor application or service developed or provided by ByteDance Limited or an entity owned by ByteDance
Limited.
Covered article, as defined in 41 U.S.C. 4713(k), means:
(1) Information technology, as defined in 40 U.S.C. 11101, including cloud computing services of all types;
(2) Telecommunications equipment or telecommunications service, as those terms are defined in section 3 of the Communications Act of 1934 (47 U.S.C. 153);
(3) The processing of information on a Federal or non-Federal information system, subject to the requirements of the Controlled Unclassified Information program (see 32 CFR part 2002); or
(4) Hardware, systems, devices, software, or services that include embedded or incidental information technology.
Covered foreign country means The People’s Republic of China.
Covered telecommunications equipment or services means—
(1) Telecommunications equipment produced by Huawei Technologies Company or ZTE
Corporation (or any subsidiary or affiliate of such entities);
(2) For the purpose of public safety, security of Government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities);
(3) Telecommunications or video surveillance services provided by such entities or using such equipment; or
(4) Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of National Intelligence https://www.sam.gov or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country.
Critical technology means—
(1) Defense articles or defense services included on the United States Munitions List set forth in the International Traffic in Arms Regulations under subchapter M of chapter I of title 22, Code of Federal Regulations;
(2) Items included on the Commerce Control List set forth in Supplement No. 1 to part 774 of the Export Administration Regulations under subchapter C of chapter VII of title 15, Code of
Federal Regulations, and controlled—
(i) Pursuant to multilateral regimes, including for reasons relating to national security, chemical and biological weapons proliferation, nuclear nonproliferation, or missile technology; or
(ii) For reasons relating to regional stability or surreptitious listening;
(3) Specially designed and prepared nuclear equipment, parts and components, materials, software, and technology covered by part 810 of title 10, Code of Federal Regulations (relating to assistance to foreign atomic energy activities);
(4) Nuclear facilities, equipment, and material covered by part 110 of title 10, Code of Federal
Regulations (relating to export and import of nuclear equipment and material);
(5) Select agents and toxins covered by part 331 of title 7, Code of Federal Regulations, part
121 of title 9 of such Code, or part 73 of title 42 of such Code; or
(6) Emerging and foundational technologies controlled pursuant to section 1758 of the Export
Control Reform Act of 2018 (50 U.S.C. 4817).
FASC-prohibited unmanned aircraft system means an unmanned aircraft system manufactured or assembled by an American Security Drone Act—covered foreign entity.
FASCSA order means any of the following orders issued under the Federal Acquisition Supply
Chain Security Act (FASCSA) requiring removing covered articles from executive agency information systems or excluding one or more named sources or named covered articles from executive agency procurement actions, as described in 41 CFR 201-1.303(d) and (e):
(1) The Secretary of Homeland Security may issue FASCSA orders that apply to civilian agencies, to the extent not covered by paragraph (2) or (3) of this definition. This type of
FASCSA order may be referred to as a Department of Homeland Security (DHS) FASCSA order.
(2) The Secretary of Defense may issue FASCSA orders that apply to the Department of
Defense (DoD) and national security systems other than sensitive compartmented information systems. This type of FASCSA order may be referred to as a DoD FASCSA order.
(3) The Director of National Intelligence (DNI) may issue FASCSA orders that apply to the intelligence community and sensitive compartmented information systems, to the extent not covered by paragraph (2) of this definition. This type of FASCSA order may be referred to as a
DNI FASCSA order.
Information technology, as defined in 40 U.S.C. 11101(6)—
(1) Means any equipment or interconnected system or subsystem of equipment, used in the automatic acquisition, storage, analysis, evaluation, manipulation, management, movement, control, display, switching, interchange, transmission, or reception of data or information by the executive agency, if the equipment is used by the executive agency directly or is used by a contractor under a contract with the executive agency that requires the use—
(i) Of that equipment; or
(ii) Of that equipment to a significant extent in the performance of a service or the furnishing of a product;
(2) Includes computers, ancillary equipment (including imaging peripherals, input, output, and storage devices necessary for security and surveillance), peripheral equipment designed to be controlled by the central processing unit of a computer, software, firmware and similar procedures, services (including support services), and related resources; but
(3) Does not include any equipment acquired by a Federal contractor incidental to a Federal contract.
Intelligence community, as defined by 50 U.S.C. 3003(4), means the following—
(1) The Office of the Director of National Intelligence;
(2) The Central Intelligence Agency;
(3) The National Security Agency;
(4) The Defense Intelligence Agency;
(5) The National Geospatial-Intelligence Agency;
(6) The National Reconnaissance Office;
(7) Other offices within the Department of Defense for the collection of specialized national intelligence through reconnaissance programs;
(8) The intelligence elements of the Army, the Navy, the Air Force, the Marine Corps, the
Coast Guard, the Federal Bureau of Investigation, the Drug Enforcement Administration, and the Department of Energy;
(9) The Bureau of Intelligence and Research of the Department of State;
(10) The Office of Intelligence and Analysis of the Department of the Treasury;
(11) The Office of Intelligence and Analysis of the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .