About this file

This is a bid form for the Robbins-Key AML Reclamation Project, a contract opportunity in Alabama. The project encompasses comprehensive reclamation and erosion control work across approximately 9 acres, with principal items of work organized into lump sum and variable quantity categories. Lump sum items include mobilization, stormwater erosion control management, and clearing. Variable quantity items span multiple work categories including dam backfill and compaction (680 cubic yards), various erosion control materials such as silt fence (6,430 linear feet), wattles (1,000 linear feet), and erosion control blankets, limestone in multiple grades totaling 595 tons, riprap (1,315 tons combined), corrugated polyethylene pipe (235 linear feet), pond outlet control structures and skimmers, and seeding and mulching work covering 9 acres for permanent seeding and 23 acres for temporary seeding, with 36 additional tons of temporary mulching required.

Bidders are required to submit unit prices for each principal item of work and calculate extended prices by multiplying the unit price by the specified quantity. The bid form requires vendors to provide complete pricing for all line items and submit a total contract bid price, with notation that failure to provide detailed pricing as outlined may result in bid rejection. The form specifies that the total contract bid price must be entered in the Unit Price field in Alabama Buys, the state's procurement system. Contractors must sign and date the completed bid proposal form, which consists of two pages detailing the full scope of materials and services required for the reclamation project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Robbins-Key AML Reclamation Project Principal Items of Work

Description of Work "Lump Sum" Items Unit(s) Qty. Unit Price Extended Price Mobilization LS 1 @ $ = $ Stormwater Erosion Control Management LS 1 @ $ = $ Clearing Acres 9 @ $ = $ Unclassified Excavation Cu. Yd. 16,600 @ $ = $

"Variable Quantity" Items Unit(s) Qty. Unit Price Extended Price Dam Backfill & Compaction Cu. Yd. 680 @ $ = $ Silt Fence, Type A Lin. Ft. 6,430 @ $ = $ Wattles (20" Dia.) Lin. Ft. 1,000 @ $ = $ Terraces Lin. Ft. 1,150 @ $ = $ Terrace Erosion Control Blanket Lin. Ft. 1,150 @ $ = $ Contour Erosion Control Blanket Lin. Ft. 2,390 @ $ = $ Turf Reinforcement Blanket Lin. Ft. 1,900 @ $ = $ Non-woven Filter Fabric Sq. Yd. 2,050 @ $ = $ ALDOT No. 24 Limestone Tons 70 @ $ = $ ALDOT No. 57 Limestone Tons 280 @ $ = $ ALDOT No. 8910 Limestone Tons 100 @ $ = $ ALDOT No. 825-B Limestone Tons 145 @ $ = $ Riprap, Class I Limestone Tons 1,115 @ $ = $ Riprap, Class II Limestone Tons 200 @ $ = $ Concrete Grout Cu. Yd. 50 @ $ = $ Pipe, 18" Dia. Corr. PE (N-12) WT/IB Lin. Ft. 235 @ $ = $ Anti-seep Collar (18" Dia. Pipe) Each 2 @ $ = $ Pond Outlet Control Structure Each 1 @ $ = $ Pond Skimmer (2" Dia.) Each 1 @ $ = $ Detention Pond Baffles Lin. Ft. 300 @ $ = $ Erosion Control Power (PAM) Pounds 90 @ $ = $ Erosion Control Floc Blocks Each 10 @ $ = $ Dolomitic Lime Tons 60 @ $ = $ Commercial Fertilizer (13-13-13) Tons 4 @ $ = $ Seeding Acres 9 @ $ = $ Temporary Seeding Acres 23 @ $ = $ Mulching Tons 29 @ $ = $

* Note: Vendor must list the pricing for each principal items of work and their total contract bid price below. The total bid price must also be listed on the Unit Price, Line 1 of the Request for Bid. Failure to provide and attach copies of the principal items of work pricing as outlined above may result in the rejection of your bid.

Subtotal, Lump Sum Items

Bid Proposal Form Page 1 of 2

Robbins-Key AML Reclamation Project Principal Items of Work

Description of Work "Variable Quantity" Items Unit(s) Qty. Unit Price Extended Price Temporary Mulching Tons 36 @ $ = $

Contractor

By: Date:

Subtotal, Variable Quantity Items

Total Contract Bid Price (For evaluation of bids only)

** THE TOTAL CONTRACT BID PRICE MUST BE ENTERED IN THE UNIT PRICE IN ALABAMA

BUYS

Bid Proposal Form Page 2 of 2

Principal Items of Work Form

File details come from the government source that posted it. Updated .