RFP Addendum 03 (DTMB-0414) 511.24221.JLM.pdf

PDF 107 KB Posted

Attached to
511/24221. JLM; Fort Custer - ARC Flash Study
Solicitation number
RFP 171 240000002399 4
Issued by
Michigan

About this file

This is an RFP Addendum issued by the Michigan Department of Technology, Management and Budget (DTMB), State Facilities Administration Design and Construction Division for an Arc Flash Study at Fort Custer Training Center. The addendum, numbered 03 and issued on July 2, 2024, provides clarification regarding transformer specifications at the project site. Project Director Josiah L. Meyers issued this addendum in response to a proposer inquiry about the type of primary fuses used on pad-mount transformers shown in the electrical drawings. The proposal due date remains unchanged at Thursday, July 11, 2024, and all addenda are distributed to proposers through the SIGMA Vendor VSS system.

The addendum confirms that the majority of pad-mount transformers at the Fort Custer Training Center site utilize Bay-O-Net style primary fuses. This clarification addresses technical specifications necessary for proposers to develop accurate scope and pricing for the arc flash study work. No changes to pricing terms, contract amounts, or other proposal requirements were issued in this addendum.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 RFP (Rev 2/22)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration Design and Construction Division

REQUEST FOR PROPOSAL

ADDENDUM NO. 03

This form identifies an Addendum to a Request for Proposal for Professional Services, and incorporates interpretations or clarifications, modifications, and other information into the Request for Proposals.

Addenda will be numbered by the Project Director and distributed through SIGMA Vendor VSS as an attachment.

TO:

ALL PROPOSERS

DATE ISSUED

July 2, 2024

PROJECT NAME

Arc Flash Study Fort Custer Training Center

FILE NUMBER

511/24221.JLM

PROJECT DIRECTOR

Josiah L. Meyers

PROPOSAL DUE DATE:

Thursday, July 11, 2024

ADDENDUM ITEMS: (attach additional sheets and drawings if required)

Please note the following RFI response:

Q1) Given that most if not all the transformers are pad-mount type, are the fuses shown on E-1 typically bayonet type fuses?

A1) Yes, most are Bay-O-Net style primary fuses.

The proposal due date remains unchanged

APPROVED BY:

PROJECT DIRECTOR : Josiah L. Meyers DATE: July 2, 2024 http://www.buy4michigan.com/