RFB936000-01 Addendum 1.pdf

PDF 5 MB Posted

Attached to
IPBS Fire Alarm Replacement
Solicitation number
RFB936000-01
Issued by
Muscatine County, Iowa

About this file

This document is Addendum 1 for Request for Bid (RFB) 936000-01 issued by the Iowa Department of Administrative Services (DAS) for the Iowa PBS (Public Broadcasting Service) Fire Alarm Replacement project located at 6450 Corporate Drive in Johnston, Iowa. The addendum modifies the original bid documents, changing the bid due date to March 7, 2024 at 2 PM, and providing updates to specifications and drawings. The project involves replacing the fire alarm system with two primary alternates: Alternate 01 involves reusing existing speaker strobe and notification devices, while Alternate 02 involves installing new speaker strobe and notification devices. The project includes unit prices for adding or reducing addressable smoke and duct smoke detectors, with a target substantial completion date of September 5, 2024.

The bid package covers all labor, materials, equipment, and services required to complete the fire alarm system replacement, including demolition of existing systems and installation of new components. Bidders must submit their proposals through the IMPACS Electronic Procurement System and provide a bid security of 5% of the total bid amount. The project will require on-site supervision, daily logs, and coordination with Iowa PBS staff, who will handle the relocation of furniture and equipment during the construction process. Work hours are restricted to 7:00 AM to 5:00 PM Monday through Thursday, with no noise-producing work permitted during filming times, typically on Fridays. Background checks will be required for personnel needing badges, and all construction workers must adhere to strict site rules, including no smoking, drugs, or alcohol on the premises.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum 1 for RFB936000-01

Project Name: DOE IPBS JOH 6450 Fire Alarm Replacement

RFB #: 936000-01

DAS Project #: 9360.00

Date: 02/21/2024

BID DUE DATE CHANGED TO MARCH 7, 2024 @ 2PM

Questions/Substitution requests can be submitted to construction.procurement@iowa.gov until

February 27, 2024 @ 12 PM.

1. See attached Pre-bid Meeting Minutes from the Pre-Bid Walkthrough on February 13, 2024 @

2:30 pm and Attendee List.

2. SPECIFICATIONS

A. Section 00 4116 – Bid Form

a. MODIFY descriptions for Alternate 01 and Alternate 02.

B. Section 01 1200 – Contract Summary

a. MODIFY descriptions for Alternate 01 and Alternate 02.

C. Section 284600 – Digital, Addressable Fire Alarm System

a. CLARIFY system type shall be Horn strobe for Basis of Design and Speaker

Strobe for Alternate #1 and #2.

3. DRAWINGS

A. Drawing E000 – Electrical Geneal Notes & Symbols

a. MODIFY descriptions for Alternate #1 and #2.

b. ADD Speaker strobe symbol to Legend.

c. Refer to attached full size sheet E000.

B. Drawing ED101 – Fire Alarm Demolition - West

a. MODIFY existing horn strobe devices to speaker strobe to match existing conditions.

b. MODIFY keynotes to match existing conditions and new alternates.

c. Refer to attached full size sheet ED101.

C. Drawing ED102 – Fire Alarm Demolition - East

a. MODIFY existing horn strobe devices to speaker strobe to match existing conditions.

b. MODIFY keynotes to match existing conditions and new alternates.

c. Refer to attached full size sheet ED102.

D. Drawing ED103 – Fire Alarm Demo & New - Mezzanine

a. MODIFY existing horn strobe devices to speaker strobe to match existing conditions.

b. MODIFY keynotes to match existing conditions and new alternates.

c. Refer to attached full size sheet ED103.

mailto:construction.procurement@iowa.gov

E. Drawing E101 – Fire Detection & Alarm Plans - West

a. MODIFY general noes and keynotes to match existing conditions and new alternates.

b. Refer to attached full size sheet E101.

F. Drawing E102 – Fire Detection & Alarm Plans - West

a. MODIFY general noes and keynotes to match existing conditions and new alternates.

b. Refer to attached full size sheet E102.

G. Drawing E103 – Fire Detection & Alarm Plans – West Alternate #1 & #2

a. ADD sheet to show locations for a speaker strobe system. Device locations to be used for both alternates.

b. Refer to attached full size sheet E103.

H. Drawing E104 – Fire Detection & Alarm Plans – West Alternate #1 & #2

a. ADD sheet to show locations for a speaker strobe system. Device locations to be used for both alternates.

b. Refer to attached full size sheet E104.

State of Iowa - Department of Administrative Services 109 SE 13th St.

Des Moines, Iowa 50319 P: (515) 281-7260

Project: 9360.00 DOE IPBS JOH 6450 Fire Alarm Replacement

6450 Corporate Drive Johnston, Iowa 50131

RFB Pre-Bid Minutes: Meeting #1

Meeting Date Feb 13, 2024 Meeting Time 2:30 PM - 3:30 PM Central Time (US & Canada)

Meeting Location IPBS

Overview Meeting to allow prospective bidders to visit the site, when possible, and learn more about the project.

Notes

Attachments Attendee List.pdf, IPBS Zone Map.pdf

Scheduled Attendees

Name Company Phone Number Email Attendance

Mike Downey Iowa PBS michael.downey@iowapbs.org Present

Jamie Dye Iowa PBS P: (515) 725-9829 james.dye@iowapbs.org Present

Michelle Wendel Iowa PBS P: (515) 725-9828 michelle.wendel@iowapbs.org Present

Eric Heynen KCL Engineering P: (515) 724-7938 eheynen@kclengineering.com Present

Adam Douglas McGough Construction adam.douglas@mcgough.com Present

Leilani Hammel McGough Construction P: (515) 344-8980 leilani.hammel@mcgough.com Present

Brandon Adams State of Iowa - Department of Administrative Services brandon.adams@iowa.gov Present

Jennifer Kleene State of Iowa - Department of Administrative Services

P: (515) 725-0454 jennifer.kleene@iowa.gov For Distribution Only

Introduction

No. Mtg Origin Title Assignment Due Date Priority Status

1.1 1 Introductions Open

Description DAS - Owner's Representative

• Brandon Adams

McGough Construction - CM

• Adam Douglas

• Leilani Hammel

Iowa PBS

• Michelle Wendel

• Jamie Dye

• Mike Downey

KCL

State of Iowa - Department of Administrative Services Page 1 of 4 Printed On: Feb 20, 2024 02:00 PM CST https://storage.procore.com/v4/d/us-east-1/pro-core.com/companies/42578/01HPMSJ0ZJTG267SMAA7AAF6F4?sig=df11b2a356d8f8436ed3434ac11b3940a0c27e519c39b5edd134710db0c6b9c3 https://storage.procore.com/v4/d/us-east-1/pro-core.com/companies/42578/01HP2PVTDVCGY5E3J4KMZZFKH7?sig=9513c4956d15c400264b75e42f89d48c084eac37ccbf8fa7e661abddb3efc085

• Eric Heynen

Official Documented Meeting Minutes See attached Attendee List.

Project Overview

2.1 1 Project Description Open

Description

• Base bid: Fire Alarm Replacement - All work on the contract documents complete, include plans and specifications.

• Alternates:

o Alternate 01: Replacement of Existing Conductors - Provide a complete replacement of the existing conductors.

o Alternate 02: Reuse Existing Notification - Reuse existing notification devices. Existing devices will remain intact and be reconnected to the new system.

• Unit prices:

o Unit 01: Smoke Detection - Provide price to add/reduce an addressable smoke detector o Unit 02: Duct Smoke Detection - Provide price to add/reduce an addressable duct smoke detector.

*Full Descriptions can be found in 01 1200 Contract Summary.*

2.2 1 Project Schedule Open

Description

• Contract(s) Issued: 3/1/24

• Submittals: March 2024

• Construction: June 18, 2024-Sept 5, 2024

• Closeout: September 2024

A pull-plan session will be held with the successful bid package contractors to finalize the construction schedule.

State Holidays: New Year's Day, Martin Luther King Day, Memorial Day, 4th of July, Labor Day, Veterans Day, Thanksgiving and day after Thanksgiving, Christmas Day

2.3 1 Site Rules Open

Description

• Onsite supervision by Prime Contractor is required at all times when work by that contractor or their subcontractors/suppliers is taking place.

• Contractors shall provide daily logs for each day they are on site.

• Construction progress meeting will be established once construction starts.

• It is of the utmost importance to show respect and courtesy to all staff at all times.

• Clean all debris, materials, and bring all finishes back to existing conditions in the area they were working in prior to moving to the next area.

• No smoking, vaping or smokeless tobacco use onsite.

• Temporary facilities - Not needed.

• Background checks will be needed for anyone who needs a badge, likely just foremen.

Meeting #1 - RFB Pre-Bid Project: 9360.00 DOE IPBS JOH 6450 Fire Alarm Replacement

State of Iowa - Department of Administrative Services Page 2 of 4 Printed On: Feb 20, 2024 02:00 PM CST

• Work hours: 7:00am - 5:00pm Monday through Thursday. No noise producing work is permitted during filming times, typically Fridays.

• View Specification 01 1200 - Contract Summary for more information.

RFB Overview

3.1 1 Bid Submission Open

Description

• Bids are due Thursday, February 29 at 2pm.

• The Bid shall be submitted to the Issuing Officer through the IMPACS Electronic Procurement System.

o Link and information is in the project manual o Contractors will need to register prior to bidding o Bidders will need to register regardless of whether it has already done business with the State of Iowa.

o Bidders should complete the registration process and ensure the ability to log in as soon as possible to ensure Bids can be submitted on the due date.

o Please make sure the electronic documents submitted contain any required signatures. Digital signatures will be accepted.

• Bid Opening will be held via conference call on Thursday, February 29 at 3pm.

• Contractor shall reference section 00 0116 for the bid submittal checklist o Bid Proposal Information o Non Discrimination Clause Information o Contractor Targeted Small Business Enterprise Pre-Bid Contract Information o Bid Security – 5% of total Bid amount

• Apparent low bidder will be required to submit subcontractor/supplier list 48hrs after the bid opening

Bid due date will be changed to March 7 @ 2pm with bid opening March 7 @ 3pm.

3.2 1 Bid Schedule Open

Description

• Questions/Substitutions Due in Writing to Construction.Procurement@iowa.gov: February 20 by 12pm.

• Addendum will be issued during the week of 2/19.

• Bids Due: Feb. 29, 2024 @ 2pm.

• Tentative NOI Issued: March 01, 2024

3.3 1 Administrative Details Open

Description

• Contractors will sign a modified ConsensusDocs 802. Example in the project manual.

• Project-specific Certificate of Insurance must be provided prior to contract execution. Follow example in the project manual and limits in the 802.

• Project-specific P&P bonds must be provided prior to contract execution.

• Successful contractor must turn in their list of subcontractors and suppliers within 48 hours of the bid.

• DAS will provide tax exempt certificates upon request.

• Procore will be used for all project management, at no cost to the trade contractor.

State of Iowa - Department of Administrative Services Page 3 of 4 Printed On: Feb 20, 2024 02:00 PM CST mailto:Construction.Procurement@iowa.gov:

o Submittals, Invoicing, RFIs, ASIs, PRs, RFQs o Contracts, Change Orders and Certificates of Substantial and Final Completion will also use Docusign

• Contractor Schedule of Values shall be broken out as specified in the project manual.

o SOV must contain a closeout line item for at least 1% of the total contract value.

o This line item can only be invoiced once the certificate of final completion has been signed by all parties.

• The contractor will be responsible for submitting plans to the Fire Marshal for review and approval.

3.4 1 Pre-Bid Site Visits Open

Description Review IPBS Zone Map.

Official Documented Meeting Minutes

• Pink zones need to be back working by the end of each day and green zones are going to be dependent on IPBS' schedule but can remain down until the end of the week and just need to be back up and running over the weekend.

o The building is not required to have smoke detection but is important that the highlighted areas have them working as noted.

o The white areas are more occupied space/office space. There will still be pull stations and other notifiers that will be working.

Questions

4.1 1 Questions Open

Description Submit all questions in writing to construction.procurement@iowa.gov.

Official Documented Meeting Minutes

• Discussion items:

o If any drywall or ceiling are disturbed, it is the contractor's responsibility to bring that back to existing conditions.

o The ceiling tile are 20" x 60" so contractors need to be careful to not damage the tiles.

o There are several mag holds throughout the building that will need to be tied into the system to override the mag hold if the fire alarm goes off.

o More smoke detection is required in the lobby to be up to code, there is a hard lid ceiling with a couple access panels.

These meeting minutes are believed to be an accurate reflection of those items discussed and the conclusions that were reached during the referenced meeting.

Please contact State of Iowa - Department of Administrative Services if there are any discrepancies or questions with the content of these minutes.

State of Iowa - Department of Administrative Services Page 4 of 4 Printed On: Feb 20, 2024 02:00 PM CST mailto:construction.procurement@iowa.gov

PROJECT 9360.00 BID FORM 00 4116 - 1

SECTION 00 4116

BID FORM

The Bid Form must be submitted online through the State�s IMPACS Electronic Procurement System.

RFB #936000-01

BID FORM for CONSTRUCTION CONTRACT for

Iowa PBS 6450 Corporate Drive, Johnston, IA 50131

Project 9360.00

Iowa Department of Administrative Services Hoover State Office Building, Level 3 1305 East Walnut Street Des Moines, Iowa 50319-0105

The following information is to be completed and submitted with your bid.

1. Bid Form - Completed and Signed (to be uploaded with bid submission)

2. Non Discrimination Clause Information

3. Contractor Targeted Small Business Enterprise Pre-Bid Contract Information

4. Bid Security � 5% of total Bid amount (to be uploaded with bid submission)

Authorized Representative:

The undersigned Bidder, in response to your Request for Bid for construction of the above project, having examined the Drawings, Specifications, and other Bidding Documents dated February, 01, 2024 and Addenda issued and acknowledged below as received and being familiar with all the conditions surrounding the construction of the proposed project including the availability of materials and labor, hereby proposes to furnish all labor, materials, equipment and supplies to perform all work to construct the project in strict accordance with the proposed Contract Documents, within the time and at the prices stated below. Prices are to cover all expenses incurred in performing the work required under the proposed Contract Documents, of which this bid is a part.

Bidder acknowledges receipt of the following Addenda which are a part of the Bidding Documents and for which any effect on cost of the Work is included in the bid amounts indicated:

Number ________ ________ ________ ________ ________

Dated ________ ________ ________ ________ ________

Note that the State of Iowa is exempt from State and Local sales and use taxes (including local option and school option) for this project. Taxes on construction materials shall NOT be included in the bid amounts.

PROJECT 9360.00 BID FORM 00 4116 - 2

Amounts shall be indicated in both words and figures. In case of discrepancy, the amount indicated in words shall govern.

BID PACKAGES:

BP 01

Description: All material, labor and equipment associated with all work shown on the contract documents complete including the plans and specifications.

Bidder proposes and agrees to perform all work as described in the Construction Documents for the sum of:

Dollars

ALTERNATES:

ALT 01

Description: (DEDUCT) Reuse existing speaker strobe and strobe notification devices. Existing devices are on a Siemens system and are Edwards Est Product. Existing conductors are noted to be 14/4 for the speaker strobes.

Bidder proposes and agrees to perform all work as described in the Construction Documents for the sum of:

Dollars

ALT 02

Description: (ADD) Install new speaker strobe and strobe notification devise with new system. Existing devices to be removed. Existing conductors are noted to be 14/4 for the speaker strobes.

Bidder proposes and agrees to perform all work as described in the Construction Documents for the sum of:

Dollars

UNIT PRICES:

UNIT 01

Description: (ADD/DEDUCT) Provide price to add/reduce an addressable smoke detector. Assume 30 feet of conductors, wall penetration, and mounting hardware per device.

PROJECT 9360.00 BID FORM 00 4116 - 3

Dollars

UNIT 02

Description: (ADD/DEDUCT) Provide price to add/reduce an addressable duct smoke detector. Assume 50 feet of conductors, test tube, mounting hardware, and shut down relay to mechanical unit per device.

Dollars

Bidder hereby certifies that:

1. This bid is genuine and is not made in the interest of or on behalf of any undisclosed person, firm or corporation;

2. Bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid; Bidder has not solicited or induced any person, firm or corporation to refrain from bidding;

and Bidder has not sought by collusion to obtain any advantage over any other bidder or over the Owner.

3. Bidder hereby certifies that the Bidder is registered with the Iowa Labor Commissioner as a Contractor as required by Chapter 91C, Code of Iowa.

4. Bidder agrees to comply with all Federal and State Affirmative Action/Equal Employment Opportunity requirements concerning fair employment and will not discriminate between or among them by reason of race, color, religion, sex, national origin or physical handicap.

5. All construction under this Contract shall conform to the requirements of the Iowa State Building Code.

6. Bidder agrees that this bid shall remain valid and shall not be withdrawn for a period of thirty (30) calendar days after the date for receipt of bids.

7. Bidder agrees that if written notice of acceptance of this bid is mailed, emailed, or delivered to the undersigned within thirty (30) days after the date in which bids are due, or at any time thereafter before it is withdrawn, the undersigned will sign and return the Contract Agreement, prepared in accord with the Bidding Documents and this bid as accepted; and will also provide proof of insurance coverage and required surety bonds.

8. Bidder understands that the Owner reserves the right to reject any and all bids, and to waive irregularities or informalities and enter into a contract for the work, as the Owner deems to be in the best interest of the State.

9. Bidder understands that the Owner reserves the right to accept any, or no, Alternate Bid, if requested, and that the Alternate Bids may be considered in any order or combination, and the low Bidder shall be determined on the basis of the sum of the base bid and any Alternate(s) accepted.

Subcontractors:

The Trade Contractor must identify all Subcontractors and Suppliers within 48 hours of the published date and time for which bids must be submitted, in accordance with Iowa Code Section 8A311, as amended by House File 646 in 2011. Subcontractors and suppliers may not be changed without the approval of the Owner. Requests for changing a Subcontractor or supplier must identify the reason for the proposed change, the name of the new Subcontractor or supplier, and the change in the subcontractor or supplier price as a result of the change. Any reduction in subcontractor or supplier price as a result of the change, if the change is approved by the Owner, shall be deducted from the Trade Contract Price via a deductive Change Order. Any such changes, if approved by the Owner, which result in an increase in the Trade

PROJECT 9360.00 BID FORM 00 4116 - 4

Contract Price shall be borne by the Trade Contractor.

Enforcement of Reciprocal Resident Bidder Preference, per Iowa Code 73A.21.

All bidders shall either check the box next to �Resident Bidder� or check the box next to

�Nonresident Bidder� and by doing so and signing thereafter certifies and attests to the same. All information requested must be provided. Seek out the advice of an attorney if you have questions.

�Resident Bidder� means a person or entity authorized to transact business in of the State of Iowa and having a place of business for transacting business within the State of Iowa at which it is conducting and has conducted business for at least three years prior to the date of the first advertisement for the public improvement. Note, however, that if a nonresident bidder�s state or foreign country has a more stringent definition of a resident bidder, the more stringent definition is applicable as to bidders from that state or foreign country.

Resident Bidder

Name of Resident Bidder: ___________________________

By: _____________________________________ Authorized Agent and Signatory of Resident Bidder

OR:

Nonresident Bidder

Name of Nonresident Bidder: ___________________________

Name of State or Foreign Country of Nonresident Bidder: ___________________________

Particularly identify and describe any preference, labor preference, or any other type of preferential treatment, in effect in the nonresident bidder�s state or foreign country at the time of this bid:

NOTICE: Nonresident Bidders domiciled in a state or country with a resident labor force preference shall make and keep, for a period of not less than three years, accurate records of all workers employed on the public improvement. The records shall include each worker�s name, address, telephone number when available, social security number, trade classification, and the starting ending time of employment.

By: ________________________________________ Authorized Agent and Signatory of Nonresident Bidder

Bid Form shall be signed by an officer of the company with authority to bind in a contract.

Notice of acceptance of this bid, or request for additional information by the Department of Administrative Services, may be addressed to the undersigned at the address set forth below:

Legal Name of Firm: ____________________________________________________________

Date: _________________________________________________

Signature of Bidder: ____________________________________________________

PROJECT 9360.00 BID FORM 00 4116 - 5

Title: ______________________________________________________

Typed Name of Signatory: _____________________________________________________

Email: _______________________________________

Business Address:

Telephone Number: ____________________ Fax Number: ____________________

Federal Tax Identification Number: ____________________

Iowa Contractor Registration Number: _________________________

Bidder Safety Manager Name:_______________________________

For an out-of-state Bidder, Bidder certifies that the Resident Preference given by the State or

Foreign Country of Bidder�s residence, _________________________, is _______ %.

END OF SECTION

PROJECT 9360.00 CONTRACT SUMMARY 01 1200 - 1

SECTION 01 1200

CONTRACT SUMMARY

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Project Information B. Project Summary C. Bid Scope Summary D. Work Hour Restrictions E. Access to Site F. Coordination with Occupants G. Rules for Construction Workers H. Bid Package Instructions

1.02 PROJECT INFORMATION

A. Facility Name/Location: Iowa PBS, 6450 Corporate Dr, Johnston, IA 50131 B. DAS Project #: 9360.00 C. Owner: State of Iowa, Department of Administrative Services, Hoover State Office Building, Level 3, 1305 East Walnut Street, Des Moines, IA 50319 D. Owner�s Representative: Brandon Adams, Iowa Department of Administrative Services, 109 SE

13th Street, Des Moines, IA 50319 E. Construction Manager: Adam Douglas, McGough Construction, 217 E. 2nd St, Suite 120, Des

Moines, IA 50309

1.03 PROJECT SUMMARY

A. The project includes replacing the fire alarm system at Iowa PBS.

B. Target date to provide substantial completion is September 05, 2024.

1.04 BID SCOPE SUMMARY

A. Scope Applicable to All Bid Packages:

1. The Contractor�s Work includes all labor, supervision, materials, equipment, services, supplies, tools, facilities, transportation, hoisting, storage, receiving, licenses, inspections, certifications, overhead, profit, or other items required or reasonably inferable to properly and timely perform and complete all work and services to be performed by the Contractor pursuant to this Agreement. Unless specifically stated otherwise, incidental work required to accomplish the work of this Bid Package shall be included the bid. This would include, but not be limited to, temporary facilities, protection of the work, security of equipment, materials, and work in progress, etc. Contractor�s Work shall be performed in accordance with the Drawings, Specification Divisions 00 and 01, and Specification sections applicable to each Contractor�s scope.

2. Contractor is responsible for all labor and equipment to unload, account for all material delivered, stock, and delivery for this scope of work. Storage and delivery of materials and equipment at the Site shall be permitted only to the extent approved in advance by the Construction Manager, and if anything so stored obstructs the progress of any portion of the work, it shall be promptly removed or relocated by the Contractor without reimbursement.

3. On site supervision by Prime Contractor at all times work by that contractor or their subcontractors/suppliers is taking place.

4. Provide all temporary facilities required for this scope of work including trailer, trailer power, telephone, secured storage, temporary power for work, temporary and task

PROJECT 9360.00 CONTRACT SUMMARY 01 1200 - 2

lighting for work, etc. as determined necessary by Contractor. Coordinate location of trailers, material storage and utility lines with Construction Manager. Limited space is available, and permission to bring any such facility or excess materials on to the site shall be approved by the Construction Manager.

5. Contractor shall provide all equipment and tools for Contractor�s own cleanup. Clean up shall be done at end of every shift or more frequently if required for the Contractor to perform their work, for other Contractors to perform their work, as required by the Owner�s operations, and at the discretion of the Construction Manager.

6. All turf, landscaping, and subgrade disturbances caused by equipment traffic or other activities related to the Contractor�s scope shall be repaired or restored to proper conditions by the Contractor.

7. Protect adjacent existing building elements from damage from Scope of work. Repair existing building elements damaged during Contractor�s Scope of work.

8. Contractor shall maintain an accurate set of As-Built Drawings throughout the duration of the project and submit to the Construction Manager at the completion of the project.

Contractor to show accurate wire paths and device addresses.

1.05 WORK HOUR RESTRICTIONS

A. Work hours are from 7:00 AM to 5:00 PM, Monday through Thursday unless arrangements are made in advance.

B. No noise producing work is permitted during filming times, typically Fridays.

C. Iowa PBS will notify contractors/project teams of any unpeated filming at least 24 hours before it occurs. Contractor shall stay in communication with Owner and Construction Manager on work activities since the building is occupied and in use.

1.06 CONTRACTOR USE OF SITE AND PREMISES

A. Construction Operations: Limited to areas noted on Drawings.

B. Provide access to and from site as required by law and Owner:

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permission of Owner and permit if required.

C. Facility will be occupied at all times during duration of work. Contractor personnel shall conduct themselves in an agreeable manner at all times. Failure to do so may result in removal from the work site.

1.07 OWNER OCCUPANCY

A. Owner intends to occupy the building throughout the course of construction.

B. Cooperate with Owner to minimize conflict and to facilitate Owner�s operations.

C. Schedule the Work to accommodate Owner occupancy.

1.08 RULES FOR CONSTRUCTION WORKERS

A. The staff of the State of Iowa has a responsibility to protect the public by providing a secure environment. All work site rules must be followed to the letter, at all times.

B. All construction workers must have a background check completed prior to entering the campus to perform work.

C. Hot Work Permit Processes and Fire Watch, when necessary, will be adhered to for this project.

D. All State properties are tobacco free. No smoking will be permitted or tolerated on campus unless in designated areas.

E. You are permitted access only to the work site and no other area of the institution.

F. No drugs, alcohol, or firearms are allowed on the work site.

PROJECT 9360.00 CONTRACT SUMMARY 01 1200 - 3

G. Do not leave money, drugs, alcohol, or firearms in your personal vehicle.

H. Company and personal vehicles are to be parked and locked in designated or authorized area of the work.

I. Secure all tools at the end of the day.

J. Maintain control of all tools, supplies, and debris at all times during the work.

K. Never leave keys in any vehicle. If a security officer finds keys in a vehicle, they are under orders to turn them in to a security supervisor.

L. Do not give anything to residents or take anything from residents; if they offer, inform your supervisor.

M. Secure all tools at the end of each day. Never leave tools unattended. All tools shall be checked in at the beginning of the day and checked out at the end of the day. If security officers find loose tools, they are under orders to turn them in to their supervisor.

N. All delivery vehicles must go directly to the job site. Extra time should be anticipated for all deliveries. Provide 24-hour notice to the facility of deliveries.

O. During an emergency, follow the instructions of the security staff.

P. Contractor shall wear clothing of a different color, pattern, fashion, etc. as to distinguish themselves from inmates.

1.09 BID PACKAGE INSTRUCTIONS

A. Bid Package #01 � Fire Alarm Replacement: Trade Contractor shall include all of the following, but not limited to, as part of the contract:

1. All work on the contract documents complete; material and labor including all freight, unloading and installation for a complete scope.

2. Includes specifications: All of Divisions 00, 01, 26, and 28.

B. Alternate #01 � Reuse Existing Speaker Strobe System Trade Contractor shall include all of the following, but not limited to, as part of the contract:

1. Reuse existing speaker strobe and strobe notification devices. Existing devices are on a

Siemens system and are Edwards Est product. Reconnect existing devices to the new system. Existing conductors are noted to be 14/4 for the speaker strobes. Conductors can be reused if feasible with new system configuration. Remove or tag abandoned cables per NEC 760. Refer to sheets ED103, E103, and E104 for more information.

2. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project.

3. Include as part of each alternate, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation whether or not indicated as part of alternate.

4. Execute accepted alternates under the same conditions as other work of the Contract.

C. Alternate #02 � Replacement of Notification Devices: Trade Contractor shall include all of the following, but not limited to, as part of the contract:

1. Install new speaker strobe and strobe notification devices with new system. Existing devices to be removed. Existing conductors are noted to be 14/4 for the speaker strobes.

Conductors can be reused if feasible with new system configuration. Remove or tag abandoned cables per NEW 760. Refer to sheets ED103, E103, and E104 for more information.

2. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project.

3. Include as part of each alternate, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation whether or not indicated as part of alternate.

4. Execute accepted alternates under the same conditions as other work of the Contract.

PROJECT 9360.00 CONTRACT SUMMARY 01 1200 - 4

D. Unit Price #01 � Smoke Detection: Trade Contractor shall include all of the following, but not limited to, as part of the contract:

1. Provide price to add/reduce an addressable smoke detector. Assume 30 feet of conductors, wall penetration, and mounting hardware per device.

2. Unit prices include all necessary material, plus cost for delivery, installation, insurance, overhead, and profit.

3. Owner reserves the right to reject Contractor�s measurements of work in place that involves use of established unit prices and to have this work measured, at the Owner�s expense, by an independent surveyor acceptable to the Contractor.

E. Unit Price #02 � Duct Smoke Detection: Trade Contractor shall include all of the following, but not limited to, as part of the contract:

1. Provide price to add/reduce an addressable duct smoke detector. Assume 50 feet of conductors, test tube, mounting hardware, and shut down relay to mechanical unit per device

2. Unit prices include all necessary material, plus cost for delivery, installation, insurance, overhead, and profit.

3. Owner reserves the right to reject Contractor�s measurements of work in place that involves use of established unit prices and to have this work measured, at the Owner�s expense, by an independent surveyor acceptable to the Contractor.

F. Work Performed by Owner: Iowa PBS will perform the following work items:

1. Relocate all moveable furniture, fixtures and equipment (FF&E), including window treatments; and personal materials from each sequenced work area prior to demolition and construction activities and after new construction is completed.

PART 2 - PRODUCTS � NOT USED

PART 3 - EXECUTION � NOT USED

END OF SECTION

I hereby certify that this engineering document was prepared by me or under my direct personal supervision and that i am a duly licensed Professional Engineer under the laws of the State of Iowa

(signature)

License Number :

Pages or sheets covered by this seal:

(date)

My license renewal date is December 31, E N

G N

E E

R I

AOFESSION

S E

D

PR

AI O W

L

IC

E N

L

ERIC HEYNEN, P.E.

ERIC

HEYNEN

E. Sheets

P24706P24706

SHEET LIST

G001 LIFE SAFETY AND CODE SUMMARY

E000 ELECTRICAL GENERAL NOTES & SYMBOLS

ED101 FIRE ALARM DEMOLITION - WEST

ED102 FIRE ALARM DEMOLITION - EAST

ED103 FIRE ALARM DEMO AND NEW - MEZZANINE

E101 FIRE DETECTION & ALARM PLANS - WEST

E102 FIRE DETECTION & ALARM PLANS - EAST

E103 FIRE DETECTION & ALARM PLANS - WEST ALTERNATE #1 & #2

E104 FIRE DETECTION & ALARM PLANS - EAST ALTERNATE #1 & #2

OWNER

IOWA DEPARTMENT OF ADMINISTRATIVE SERVICES

109 SE 13TH STREET

DES MOINES, IA 50319

OWNER PROJECT NUMBER: 9360.00

CONSTRUCTION MANAGER

ADAM DOUGLAS - PROJECT EXECUTIVE

MCGOUGH

217 E 2ND STREET, SUITE 120

DES MOINES, IOWA 50309

ENGINEER

ERIC HEYNEN, PE

KCL ENGINEERING

eheynen@kclengineering.com 515-300-8092

ENGINEER PROJECT NUMBER: 23249

2/20/2024 1:04:29 PM

CONSTRUCTION DOCUMENTS

2/1/2024

STATE OF IOWA DEPARTMENT OF ADMINISTRATIVE SERVICES

9360.00 IOWA PBS FIRE ALARM REPLACEMENT

VICINITY MAP:

6450 CORPORATE DRIVE

JOHNSTON, IOWA 50131

M E

R L

E H

A Y

R O

A D

NW 62ND AVE

6450 CORPORATE DR

CONDUIT SLEEVE

EQUIPMENT IDENTIFICATION TAG. REFER TO EQUIPMENT CONNECTION SCHEDULE

GENERAL SYMBOLS

KEYNOTE#

XXX

X

JUNCTION BOX, CEILING OR FLOOR MOUNTED.

JUNCTION BOX, WALL MOUNTED, ELEVATION AS NOTED.

J

J

POWER SYMBOLS

DUPLEX RECEPTACLE, TAMPER-RESISTANT, WALL MOUNT +18", OR AS NOTED

EQUIPMENT CONNECTION, WALL MOUNT +18", OR AS NOTED, REFER TO ELECTRICAL

EQUIPMENT CONNECTION SCHEDULE FOR CONNECTION TYPE

PANELBOARD - SURFACE MOUNTED

**NOTE: ALL SYMBOLS MAY NOT APPLY TO THIS PROJECT**

1. PROVIDE ELECTRICAL INSTALLATION IN ACCORDANCE WITH ALL STATE CODES.

2. THE CURRENT ADOPTED EDITION OF THE ELECTRICAL CODE IS THE STANDARD FOR THE

ELECTRICAL INSTALLATION. VERIFY WITH STATE OFFICIALS WHEN PERMITS ARE OBTAINED.

NOTIFY DESIGN TEAM OF ANY DISCREPANCIES BETWEEN THE PROJECT MANUAL OR

DRAWINGS AND THE GOVERNING CODE.

3. INSTALLATION SHALL FOLLOW REQUIREMENTS OF THE ADAAG –AMERICANS WITH

DISABILITIES ACT.

4. REFER TO PROJECT MANUAL AND PROJECT CODE REVIEW SHEET FOR LIST OF APPLICABLE

CODES.

CODE NOTES - ELECTRICAL

1. PROVIDE NEW FULLY FUNCTIONAL AND CODE COMPLIANT FIRE ALARM SYSTEM.

2. THE STATE FIRE MARSHAL HAS APPROVED THE USE OF DETECTION ON A ROOM-BY-ROOM

BASIS. DETECTION IS SHOWN IN SPACES THAT THE OWNER WOULD LIKE DETECTION WITHIN

THE SPACE. BIDS AND DESIGN SHALL INCLUDE COVERAGE OF ALL THE SPACES SHOWN IN

THE CURRENT DESIGN.

GENERAL PROJECT INTENT

DEMOLITION AND RENOVATION NOTES - ELECTRICAL

1. ELECTRICAL DEMOLITION DRAWINGS SHOWING EXISTING CONDITIONS HAVE BEEN PREPARED

BASED ON FIELD OBSERVATION AND ORIGINAL DRAWINGS. FIELD VERIFY EXISTING

CONDITIONS BEFORE WORK BEGINS. ADDITIONAL COMPONENTS MAY EXIST WHICH ARE NOT

SHOWN. BECOME FAMILIAR WITH EXISTING ELECTRICAL SYSTEM WHICH WILL BE AFFECTED

BY THE DEMOLITION WORK.

2. PROVIDE EQUIPMENT, LABOR, AND MATERIALS TO REMOVE ELECTRICAL FACILITIES AND

CLEAR THE AREA TO RECEIVE THE NEW WORK PROVIDED UNDER THIS CONTRACT.

3. IN OCCUPIED AREAS BEYOND THE DEMOLITION SCOPE, KEEP EXISTING SYSTEMS NOT

AFFECTED BY PROJECT SCOPE OPERATIONAL THROUGH THE DURATION OF THE PROJECT.

OBTAIN PERMISSION FROM OWNER'S REPRESENTATIVE TO SHUT OFF SERVICES OR SYSTEMS

WHICH MAY AFFECT OTHER AREAS BEYOND THE LIMITS OF THE DEMOLITION AREA. INFORM

OWNER’S REPRESENTATIVE OF THE REASON FOR AND DURATION OF THE SHUTDOWN AND

ENSURE THAT THE SHUTDOWN IS MADE WITH AS LITTLE INCONVENIENCE TO OTHER AREAS

AS POSSIBLE.

4. INSTALL NEW CONDUCTORS FOR NEW DEVICES UNLESS SPECIFICALLY NOTED OTHERWISE.

RETAIN EXISTING CONDUITS IN GOOD CONDITION WHERE APPROVED BY ENGINEER OR AS

INDICATED.

5. KEEP EXISTING SYSTEMS OPERATIONAL DURING ALL PHASES OF CONSTRUCTION. DO NOT

CUT EXISTING TELECOMMUNICATION WIRING, CABLES OR CONDUIT. CONTRACTORS WHO CUT

IN-SERVICE CABLES ARE RESPONSIBLE FOR ALL DOWNTIME AND COSTS TO REPAIR.

6. INSTALL BLANK COVER PLATES OVER OPENING AT REMOVED DEVICE LOCATIONS. THIS

INCLUDES BUT IS NOT LIMITED TO, CLOCKS, RECEPTACLES, SWITCHES, JUNCTION BOXES,

ETC.

7. PROVIDE CUTTING AND PATCHING OF EXISTING MATERIALS AS REQUIRED FOR THE PROPER

COMPLETION OF THE DEMOLITION WORK AND THE INSTALLATION OF THE NEW WORK.

8. MAINTAIN FULL FUNCTIONAL AND AESTHETIC INTEGRITY OF DEVICES IDENTIFIED TO BE

REMOVED AND RELOCATED, AND HANDLE WITH APPROPRIATE CARE TO ALLOW FOR

REINSTALLATION. REPLACE DEVICES DAMAGED DURING DEMOLITION WITH NEW AT

CONTRACTOR’S EXPENSE.

9. EQUIPMENT AND SYSTEM THAT ARE REMOVED REMAIN THE PROPERTY OF THE OWNER

UNLESS OTHERWISE NOTED. DISPOSE OF ALL MATERIALS NOT SALVAGED BY THE OWNER.

10. REMOVE AND REINSTALL CEILING TILES REQUIRED FOR THE WORK BEING DONE UNDER THIS

CONTRACT. REPLACE CEILING TILES DAMAGED DURING CONSTRUCTION TO MATCH EXISTING.

1. BECOME FAMILIAR WITH EXISTING CONDITIONS PRIOR TO BID.

2. INCREASE CONDUCTOR SIZES ON 20A 120V-1 PHASE CIRCUITS EXCEEDING 100 FEET TO

CENTER OF LOAD TO ACCOUNT FOR VOLTAGE DROP.

3. PROVIDE A DEDICATED GREEN INSULATED GROUND CONDUCTOR TO ALL DEVICES. DO

NOT USE CONDUIT SYSTEM AS THE ONLY EQUIPMENT GROUNDING METHOD.

4. CONTRACTOR IS RESPONSIBLE FOR OPENINGS IN WALLS, FLOORS, AND CEILINGS THAT

ARE REQUIRED TO COMPLETE THEIR SCOPE OF WORK. SEAL PENETRATIONS IN

ACCORDANCE WITH THE RATING OF THE AFFECTED ASSEMBLY. REFER TO OCCUPANCY

PLAN FOR RATED WALLS, FLOORS, AND CEILINGS.

INSTALLATION NOTES - ELECTRICAL

ELECTRICAL ABBREVIATIONS

A DEVICE MOUNTED +8" ABOVE

COUNTER TOP (VERIFY LOCATION)

AFF ABOVE FINISHED FLOOR

ATS AUTOMATIC TRANSFER SWITCH

C CEILING

CB CIRCUIT BREAKER

CT CURRENT TRANSFORMER

E EXISTING ITEM TO REMAIN

EC ELECTRICAL CONTRACTOR

EM EMERGENCY LIGHT FIXTURE

ER NEW LOCATION OF EXISTING ITEM

F ROUGH IN FOR FUTURE DEVICE

FAAP FIRE ALARM ANNUNCIATOR PANEL

FACP FIRE ALARM CONTROL PANEL

FSD FIRE SMOKE DAMPER

G GROUND FAULT CIRCUIT INTERRUPTER

GND GROUND

KVA KILO-VOLT-AMPERES

KW KILOWATTS

MC MECHANICAL CONTRACTOR

MCB MAIN CIRCUIT BREAKER

MDP MAIN DISTRIBUTION PANEL

MLO MAIN LUGS ONLY

N NEW DEVICE IN EXISTING LOCATION

NIC NOT IN CONTRACT

NM NONMETALLIC

NTS NOT TO SCALE

OC ON CENTER

OFCI OWNER FURNISHED

CONTRACTOR INSTALLED

OFOI OWNER FURNISHED,

OWNER INSTALLED

R EXISTING ITEM TO BE REMOVED

RR EXISTING ITEM TO BE REMOVED AND

RELOCATED

RN EXISTING ITEM TO BE REMOVED AND

REPLACED WITH NEW

SCCR SHORT CIRCUIT CURRENT RATING

T TAMPER PROOF DEVICE

TCC TEMPERATURE CONTROL CONTRACTOR

TV TELEVISION

TYP TYPICAL

UPS UNINTERRUPTIBLE POWER SUPPLY

V VOLTS

VA VOLT-AMPERES

W WEATHERPROOF DEVICE

WR WEATHER RESISTANT DEVICE

+24" INDICATES MOUNTING HEIGHT CENTER

LINE OF DEVICE TO FINISHED FLOOR

MANUAL FIRE ALARM PULL STATION

FIRE DETECTION AND ALARM SYMBOLS

SMOKE DETECTOR

SMOKE DETECTOR WITH 520Hz SOUNDER BASE

DUCT SMOKE DETECTOR

CARBON MONOXIDE DETECTOR

HEAT DETECTOR

WALL MOUNTED COMBINATION HORN WITH STROBE

CEILING MOUNTED STROBE

SPEAKER

ADDRESSABLE INPUT MODULE; FS - SPRINKLER WATER FLOW SWITCH,

TS - TAMPER SWITCH, PIV - POST INDICATOR VALVE

MAGNETIC DOOR HOLD

FIRE ALARM CONTROL PANEL + EMERGENCY COMMUNICATIONS PANEL

COMBINATION FIRE/SMOKE DAMPER

S

S

AIM

ADDRESSABLE OUTPUT MODULE; SD - FAN SHUT DOWN RELAY, AM - AUDIO MUTEAOM

S

SB

H HORN

S

FSD

S

F

FAA

FACP

XX

XX

COMBINATION CARBON MONOXIDE / SMOKE DETECTORS

FIRE ALARM ANNUNCIATOR PANEL

WALL MOUNTED STROBE

CEILING MOUNTED COMBINATION HORN WITH STROBE

C

WALL MOUNTED WEATHERPROOF COMBINATION HORN WITH STROBE

W

WALL MOUNTED COMBINATION SPEAKER WITH STROBE

CEILING MOUNTED COMBINATION SPEAKER WITH STROBE

C

COMMUNICATIONS - TELECOM SYSTEMS:

O

FO

I

COPPER HORIZONTAL CABLING, EXTENDED PHONE LINES

ROUGH-IN, PATHWAYS AND SLEEVES

SAFETY - FIRE DETECTION AND ALARM:

ROUGH-IN, PATHWAYS AND SLEEVES

INITIATING FIELD DEVICES (SMOKE, MANUAL PULL, MONITOR MODULES)

NOTIFICATION APPLIANCES (HORNS, STROBES, SPEAKERS)

MISCELLANEOUS DEVICES (RELAYS, TEST STATION, ANNUNCIATOR)

TECHNOLOGY RESPONSIBILITY MATRIX

PROVISION RESPONSIBILITIES DEFINED

OFOI

OFCI

CFCI

CFOI

OWNER FURNISHED & OWNER INSTALLED

OWNER FURNISHED & CONTRACTOR INSTALLED

CONTRACTOR FURNISHED & CONTRACTOR INSTALLED

CONTRACTOR FURNISHED & OWNER INSTALLED

GENERAL NOTE:

A. MATRIX IS NOT INTENDED TO BE EXHAUSTIVE TO COVER ALL MATERIALS NECESSARY FOR

SCOPE AND SHOULD ONLY BE USED TO QUICKLY IDENTIFY SYSTEMS AND RELATED

INFRASTRUCTURE INSIDE AND OUTSIDE THE BID OF THIS PROJECT. ANY ITEMS FURNISHED

OR INSTALLED BY THE BIDDING CONTRACTOR SHALL COVER ALL REQUIRED APPURTENANCES

NECESSARY FOR A COMPLETE SYSTEM. THIS SHALL INCLUDE BUT NOT BE LIMITED TO,

EQUIPMENT, ACCESSORIES, TERMINATIONS, TERMINATION COMPONENTS, ALL FINAL

CORDAGE CONNECTIVITY, SOFTWARE, PROGRAMMING, AND THE LABOR TO INSTALL.

O

FC

I

C

FC

I

C

FO

I

1. EXISTING FIRE DETECTION AND ALARM SYSTEM MUST REMAIN OPERATIONAL UNTIL

NEW FIRE ALARM PANEL IS FUNCTIONAL. COORDINATE EXISTING ZONES IN USE AND

PHASE REPLACEMENT OF SYSTEM TO MINIMIZE DOWNTIME.

2. METHODICALLY, AND IN CLOSE COORDINATION WITH THE OWNER, ROUTE NEW FIELD

WIRING TO ANTICIPATED DEVICE LOCATIONS. TAKE NO MORE THAN ONE EXISTING

SIGNAL LINE CIRCUIT OFFLINE AT ANY ONE TIME TO ENSURE A GRACEFUL MIGRATION

OCCURS FROM THE EXISTING SYSTEM TO THE NEW.

3. BIDDING CONTRACTOR IS ENCOURAGED TO RE-USE EXISTING PATHWAYS AND BOXES

WHERE IT IS APPROPRIATE. PROVIDE NEW PENETRATIONS AND SLEEVES WHERE

NECESSARY FOR DEVICE INSTALLATION. REFER TO PLAN SHEETS FOR NEW DEVICE

LOCATIONS AND WHERE EXISTING LOCATIONS CAN BE REUSED.

4. INTERFACE NEW DEVICES WITH NEW AND/OR EXISTING MECHANICAL EQUIPMENT FOR

FAN SHUT DOWN, SMOKE DAMPER AND COMBINATION FIRE/SMOKE DAMPER

PURPOSES.

5. NEW FIRE ALARM DEVICES FOR NOTIFICATION OR DETECTION SHALL BE INSTALLED IN

THE MIDDLE OF CEILING TILES. EXISTING TILE SIZE IS APPROXIMATELY 20" X 60".

INSTALL APPROPRIATE BRACKETS SO DEVICES ARE SUPPORTED FROM THE GRID OR

STRUCTURE ABOVE. TILES CANNOT BE USED FOR SUPPORT.

6. FIRE ALARM ITEMS AND DEVICES ARE SHOWN IN SUGGESTED LOCATIONS. FINAL

LAYOUTS, LOCATIONS, AND QUANTITIES SHALL BE IN ACCORDANCE WITH APPLICABLE

CODES, MANUFACTURER’S RECOMMENDATIONS, AND EQUIPMENT LISTINGS.

COORDINATE LOCATIONS WITH LIGHTING AND AIR HANDLING SYSTEMS.

7. ALL FIRE ALARM CIRCUITRY IN EXPOSED CEILING SPACES SHALL BE IN ¾” CONDUIT PER

SPECIFICATIONS. EXPOSED CABLING SHALL NOT BE ACCEPTED.

8. ALL CONCEALED, ACCESSIBLE CEILING TILE LOCATIONS SHALL BE ALLOWED TO HAVE

OPEN AIR CABLING INSTALLED. PROVIDE J-HOOKS, BRIDLE RINGS AND ASSOCIATED

CABLE SUPPORTS TO KEEP INFRASTRUCTURE MANAGED AND OFF OF THE CEILING TILE.

9. ELECTRICAL CONTRACTOR SHALL PROVIDE FIRESTOPPING AT ALL PENETRATIONS PER

SPECIFICATION.

10. DEVICES SHALL BE WHITE UNLESS OTHERWISE NOTED.

FIRE DETECTION & ALARM NOTES

1. REUSE EXISTING SPEAKER STROBE AND STROBE NOTIFICATION DEVICES. EXISTING

DEVICES ARE ON A SIEMENS SYSTEM AND ARE EDWARDS EST PRODUCT. RECONNECTED

EXISTING DEVICES TO THE NEW SYSTEM. EXISTING CONDUCTORS ARE NOTED TO BE 14/4

FOR THE SPEAKER STROBES. CONDUCTORS CAN BE REUSED IF FEASIBLE WITH NEW

SYSTEM CONFIGURATION. REMOVE OR TAG ABANDONED CABLES PER NEC 760. REFER

TO SHEETS ED103, E103, AND E104 FOR MORE INFORMATION.

2. INSTALL NEW SPEAKER STROBE AND STROBE NOTIFICATION DEVICES WITH NEW

SYSTEM. EXISTING DEVICES TO BE REMOVED. EXISTING CONDUCTORS ARE NOTED TO BE

14/4 FOR THE SPEAKER STROBES. CONDUCTORS CAN BE REUSED IF FEASIBLE WITH NEW

SYSTEM CONFIGURATION. REMOVE OR TAG ABANDONED CABLES PER NEC 760.REFER TO

SHEETS ED103, E103, AND E104 FOR MORE INFORMATION.

ALTERNATES

MAGNETIC LOCKML

ACCESS CONTROL SYMBOLS

Drawing #:

Date:

Project No:

© 2022 KCL Engineering L.L.C. These documents have been prepared specifically for this project. they are not suitable for use on other projects or in other locations without the expressed written approval and participation of KCL Engineering L.L.C. A limited license is granted to the owner/contractor to reproduce these documents or portions thereof, but only for use in connection with this project. Unauthorized reproduction is prohibited.

P lo t D a te

T im e

Drawing Name:

info@kclengineering.com

300 4th Street West Des Moines, Iowa 50265 515.724.7938

/2

/2

:0 :3

P

M

E000

CONSTRUCTION

DOCUMENTS

2/1/2024

9360.00

S T

A T

E O

F I

O W

A

D A

S

IP

B S

F

IR

E A

L A

R M

R E

P L

A C

E M

E N

T C

O R

P O

R A

T E

D R

IV

E

J O

H N

S T

O N

IO

W A

ELECTRICAL GENERAL

NOTES & SYMBOLS

# Revision Date

1 ADDENDUM #1 02/20/2024

F A

A

S S

F

F

C

C

S

S

S

S

F

S S S

S

S S

SS

SS

S S S

S

S SS

S

S

S S

S

SS

S

S

S

S

S

S

S

S

S

S

S

S

S

S

F

S

FAA

S

ML

M L

ML

ML

ML

ML

1. DEMOLITION DRAWINGS PRESENT LAYOUT OF EXISTING

CONDITIONS AND MAJOR ITEMS. THEY ARE NOT TO BE

CONSTRUED AS COMPLETE IN REPRESENTATION OF

ACCESSORIES AND INCIDENTALS TO BE REMOVED, REPLACED,

OR REWORKED. NOR SHOULD ACCESSIBILITY BE INFERRED.

THE CONTRACTOR IS RESPONSIBLE TO FAMILIARIZE

THEMSELVES WITH THE BUILDING AND EXISTING CONDITIONS,

PRIOR TO THE SUBMITTING OF A BID FOR THIS PROJECT.

2. REMOVE ELECTRICAL FACILITIES AND CLEAR THE AREA TO

RECEIVE THE NEW WORK TO BE PROVIDED UNDER THIS

CONTRACT.

3. THIS ELECTRICAL DEMOLITION DRAWING SHOWING EXISTING

CONDITIONS HAS BEEN PREPARED BASED ON FIELD

OBSERVATION. ADDITIONAL COMPONENTS MAY EXIST WHICH

DO NOT SHOW, AND SUCH ITEMS SHALL BE REMOVED TO

MATCH SIMILAR ITEMS WHICH DO SHOW. CONTRACTOR SHALL

VISIT THE SITE AND BECOME FAMILIAR WITH EXISTING

CONDITIONS.

4. ABBREVIATIONS:

E - EXISTING ITEM TO REMAIN

ER - NEW LOCATION OF EXISTING ITEM

N - NEW ITEM IN EXISTING LOCATION

R - EXISTING ITEM TO BE REMOVED, PATCH AND/OR

COVER

RN - REPLACE EXISTING WITH NEW

RR - EXISTING ITEM TO BE REMOVED AND RELOCATED

ELECTRICAL DEMOLITION NOTES

ADMINISTRATION

COMMUNICATIONS

OFFICE

OFFICE

OFFICE1114

OFFICE

OFFICE

BOARDROOM

PRODUCTION

EDUCATION

VIDEO TAPE LIBRARY

NETWORK VIDEO CENTER

TECH EQUIP. CENTER

NETWORK CONTROL

CENTER

AVID 5

FINAL CUT 4

EDIT SERVER

AVID 6

AVID 1

AVID 2

LUNCH ROOM

VENDING

1155A

VEST.

TECHNICAL SHOP

STUDIO 2

CC "B"

AUDIO PROD.

VIDEO CONTROL 1

AUDIO CONTROL 1

CONFERENCE ROOM

FINAL CUT 1

FINAL CUT 2

FINAL CUT 3

OFFICE

SOUTH CONF. ROOM

1126A

MEETING ROOM

GRAPHICS & DESIGN

MENS

WOMEN

CONF. ROOM

VEST.

1138A

FINAL CUT 5

AVID 4

AVID 3

CC "A"

CORRIDOR

MAIN LOBBY

VEST.

CORRIDOR

RN

RN

RN RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN RN RN

RN

RN

RN

RN

R

RN

RN RN

RNRN

RNRN

RN RN RN

RN

RN

R

RN

RN RN

RN

RN

RN RN

RN

RN

RN RN

RN

RN

RN

RN RN

RN

RN

RN

RNRN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RNRN

RN

RN

RN

RN

RN

RN

RN

RN

RN

MOTION GRAPHICS

DARK RM.

M A

T C

H L

IN

E

M A

T C

H L

IN

E

RN

RN

RN

E E

E

E

RN

RN

INSTALL NEW SMOKE DETECTOR IN SATELITE BUILDING.

REUSE EXISTING CONDUIT AND CONDUCTORS TO BUILDING.

REMOVE EXISTING HEAT DETECTOR IN TOWER.

REUSE EXISTING CONDUIT AND CONDUCTORS TO BUILDING.

RN

RN

3 3

3 3

E

E

E

E

Drawing #:

Date:

Project No:

© 2022 KCL Engineering L.L.C. These documents have been prepared specifically for this project. they are not suitable for use on other projects or in other locations without the expressed written approval and participation of KCL Engineering L.L.C. A limited license is granted to the owner/contractor to reproduce these documents or portions thereof, but only for use in connection with this project. Unauthorized reproduction is prohibited.

P lo t D a te

T im e

Drawing Name:

info@kclengineering.com

300 4th Street West Des Moines, Iowa 50265 515.724.7938

/2

/2

:0 :3

P

M

ED101

CONSTRUCTION

DOCUMENTS

2/1/2024

9360.00

S T

A T

E O

F I

O W

A

D A

S

IP

B S

F

IR

E A

L A

R M

R E

P L

A C

E M

E N

T C

O R

P O

R A

T E

D R

IV

E

J O

H N

S T

O N

IO

W A

FIRE ALARM

DEMOLITION - WEST

1/8" = 1'-0"

FIRE ALARM DEMO FLOOR PLAN - WEST

KEYNOTES

1 REMOVE EXISTING DEVICE IN ROOM. PREPARE WIRNG FOR

REUSE AND EXTENSION TO NEW DEVICE LOCATIONS IN

ROOM. INSTALL BLANK COVER PLATE OVER EXISTING

DEVICE LOCATION.

2 BASE BID TO REMOVE NOTIFICATION DEVICES AND

REPLACE WITH NEW. ALTERNATE #1 INCLUDES REUSING

EXISTING SPEAKER STROBE NOTIFICATION DEVICES CAN BE

REUSED AS A PART OF ALTERNATE #1. EXISTING DEVICES

APPEAR TO BE EDWARDS EST SPEAKER STROBE

PRODUCTS WITH 14/4 WIRING. SEE DESCRIPTION OF

ALTERNATE ON SHEET E000 FOR MORE INFORMATION.

3 BASE BID TO REMOVE NOTIFICATION DEVICES AND

REPLACE WITH NEW. ALTERNATE #1 INCLUDES REUSING

EXISTING NOTIFICATION DEVICES. EXISTING DEVICES

APPEAR TO BE EDWARDS EST. SEE DESCRIPTION OF

ALTERNATE ON SHEET E000 FOR MORE INFORMATION.

# Revision Date

1 ADDENDUM #1 02/20/2024

C P

FAA

S S

SS

S

S

S S

S

S

S

S

S

S

S

S

S

S

S

S

S S S S

S

F

F

S S

SS

S

S S

S

S

SS

SS

S

S

S

S

SSS

S

F

F

AIM

FS

AIM

TS

S

SS

N A

C

M L

M L

M L

ML

M L

ML

ML

1. DEMOLITION DRAWINGS PRESENT LAYOUT OF EXISTING

CONDITIONS AND MAJOR ITEMS. THEY ARE NOT TO BE

CONSTRUED AS COMPLETE IN REPRESENTATION OF

ACCESSORIES AND INCIDENTALS TO BE REMOVED, REPLACED,

OR REWORKED. NOR SHOULD ACCESSIBILITY BE INFERRED.

THE CONTRACTOR IS RESPONSIBLE TO FAMILIARIZE

THEMSELVES WITH THE BUILDING AND EXISTING CONDITIONS,

PRIOR TO THE SUBMITTING OF A BID FOR THIS PROJECT.

2. REMOVE ELECTRICAL FACILITIES AND CLEAR THE AREA TO

RECEIVE THE NEW WORK TO BE PROVIDED UNDER THIS

CONTRACT.

3. THIS ELECTRICAL DEMOLITION DRAWING SHOWING EXISTING

CONDITIONS HAS BEEN PREPARED BASED ON FIELD

OBSERVATION. ADDITIONAL COMPONENTS MAY EXIST WHICH

DO NOT SHOW, AND SUCH ITEMS SHALL BE REMOVED TO

MATCH SIMILAR ITEMS WHICH DO SHOW. CONTRACTOR SHALL

VISIT THE SITE AND BECOME FAMILIAR WITH EXISTING

CONDITIONS.

4. ABBREVIATIONS:

E - EXISTING ITEM TO REMAIN

ER - NEW LOCATION OF EXISTING ITEM

N - NEW ITEM IN EXISTING LOCATION

R - EXISTING ITEM TO BE REMOVED, PATCH AND/OR

COVER

RN - REPLACE EXISTING WITH NEW

RR - EXISTING ITEM TO BE REMOVED AND RELOCATED

ELECTRICAL DEMOLITION NOTES

STORAGE ROOM

WOMENS

MENS

ELEC. RM.

MECH RM.

CORRIDOR

EFP

1169A

FIBER

GENERAL SERVICES

1170A

COMP. ROOM

TECHNICAL STORAGE

PRODUCTION SHOP

DESIGN

STUDIO 1

GREEN ROOM

OFFICE

OFFICE

OFFICE

COAT CLOSET

MENS

WOMEN

MAYTAG LOBBY

VEST

STUDIO 3

MAYTAG AUDITORIUM

SERVING

VIDEO ROOM

AUDIO ROOM

VEST.

DRESSING

DRESSING

DRESS.1196

MENS

WOMEN

DRESS.

RECEIVING

JAN

CORRIDOR

ENGINEERING

CLOSET

UPS RM.

RN

RN

R

RN

RN RN

RNRN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN RN RN RN

RN

RN

RN RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RN

RNRN

RNRN

RN

RN

RN

RN

RN

RNRNRN

RN

RN RN

RNRN

RN

RN RN

RN

RN

RN

RN

M A

T C

H L

IN

E

M A

T C

H L

IN

E

RN

RN

RN

E

E

RN

RN

E

E

RNRN

R

REMOVE EXISTING FIRE

ALARM FDC BELL AND

PREPARE AREA FOR

NEW HORN/STROBE

E

E

EEE

E

E

Drawing #:

Date:

Project No:

© 2022 KCL Engineering L.L.C. These documents have been prepared specifically for this project. they are not suitable for use on other projects or in other locations without the expressed written approval and participation of KCL Engineering L.L.C.