This document is a revised bid sheet for the City of Covington's Floyd Street Gas Pipeline Replacement project. The project scope involves the installation of approximately 9,000 feet of 2-inch polyethylene gas main, fourteen tie-ins to existing 2 and 4-inch steel gas mains, and associated service tie-overs along Floyd Street in Covington, Georgia. The bid sheet lists 16 line items for materials, labor, and equipment required for the project, including pipe, valves, service installations, site restoration, and other ancillary items. A mandatory pre-bid meeting will be held on August 9, 2024, and sealed proposals are due by August 22, 2024, at 10:00 AM local time, to be publicly opened and read aloud.

The bid sheet provides unit prices and total amounts for each line item. The total estimated cost for the project is $458,950. This includes items such as $50,000 for squeegee/pad material, $85,000 for hard surface haul-off, $12,500 for curb inlet filters, and $300,000 for asphalt/concrete replacement. The project is funded by the City of Covington and is located within Newton County, Georgia.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM TYPE DESCRIPTION QTY. UNIT UNIT PRICE TOTAL AMOUNT

1. M,L&E 2" SDR 11 PE 2406/2708 Polyethylene Line Pipe 9,000 L.F. $0.00

2. M,L&E Tie in per Detail A 14 Ea $0.00

3. M,L&E Fabrication and Installation of 4" Header per Detail B (includes tie-in to existing 4" main and 4" valve w/ valve box)

1 Ea $0.00

4. M,L&E 2" Polyball Ball Valve w/ valve box 21 Ea $0.00

5. M,L&E Insert short side service (includes self tapping tee, EFV, anodeless riser and meter valve)

39 Ea $0.00

6. M,L&E Insert longside service (includes self tapping tee, EFV, anodeless riser and meter valve)

32 Ea $0.00

7. L & E Mobilzation/Demobilization between Phase 1 and 2 1 Ea $0.00

8. M,L&E Squeegie/Pad Material 10,000 L.F. $5.00 $50,000.00 five dollars & no/100

9. L&E Hard Surface Haul-off 1,000 Tons $85.00 $85,000.00 eighty-five dollars & no/100

10. M,L&E Type C Silt Fence 100 L.F. $3.00 $300.00 three dollars & no/100

11. M,L&E Curb Inlet Filters 50 Ea. $250.00 $12,500.00 ten dollars & no/100

12. M,L&E Sod replacement 2,000 Sq. Ft. $2.00 $4,000.00 two dollars & no/100

13. M,L&E Tree Protection and Buffer Delineation Orange Fencing 50 L.F. $3.00 $150.00 three dollars & no/100

14. L & E Per foot of Extra Depth where required 500 L.F. $10.00 $5,000.00 ten dollars & no/100

15. L & E Solid Rock Excavation 10 C.Y. $200.00 $2,000.00 two hundred dollars & no/100

16. M,L&E Asphalt/concrete replacement 20,000 Sq. Ft. $15.00 $300,000.00 fifteen dollars & no/100

Total Cost (Items 1-16) $458,950.00

CITY OF COVINGTON

FLOYD STREET GAS MAIN REPLACEMENT (REVISED 8/19/2024)

Sheet1