This document is an Addendum to a state and local contract opportunity issued by the City of Covington, Georgia for the Floyd Street Gas Pipeline Replacement project. The addendum revises the bid sheet, specifying that the city will pay $75/ton to the site plus $10/ton to the contractor for a total of $85/ton for line item 9. Bidders are instructed to use this revised bid sheet for their bid submission and to note Addendum 1 in their submittal.
The underlying state and local contract opportunity involves the installation of approximately 9,000 feet of 2-inch polyethylene gas main, fourteen tie-ins to existing 2 and 4 steel gas mains, and associated service tie-overs along Floyd Street in Covington, Georgia. The sealed proposals are due to the City of Covington by August 22, 2024 at 10:00 A.M. local time, and a mandatory pre-bid meeting will be held on August 9, 2024 at 10:00 A.M. at the Covington City Hall complex.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum # 1
Issuance Date: August 20, 2024
Description: This addendum is in regards to revised bid sheet (See attached)
Revised Bid Sheet for Floyd Street Gas Pipeline Replacement
1. Based on this, line item 9 of the attached bid sheet has been revised. The cost the city will pay will include $75/ton to the site plus $10/ton to the contractor for a total of $85/ton. Please use this bid sheet for submittal of your bid and note Addendum 1 in your submittal.