Floyd_Street_Pipeline_Replacement_Bid_Sheet.xlsx
XLSX spreadsheet 16 KB Posted
- Attached to
- Floyd Street Gas Pipeline Replacement
- Solicitation number
- PE-70750-NONST-2025-000000031
- Issued by
- Newton County, Georgia
About this file
This document is a bid sheet for the City of Covington's Floyd Street Gas Main Replacement project. The work consists of installing approximately 9,000 feet of 2-inch polyethylene gas main, fourteen tie-ins to existing 2 and 4-inch steel gas mains, and associated service tie-overs along Floyd Street in Covington, Georgia. A mandatory pre-bid meeting will be held on August 9, 2024, at 10:00 A.M. at Covington City Hall, and sealed proposals will be due by August 22, 2024, at 10:00 A.M.
The bid sheet includes unit pricing for various line items, such as polyethylene pipe, tie-ins, fabrication and installation of a 4-inch header, ball valves, service installations, mobilization, haul-off, erosion control measures, sod replacement, tree protection, and extra depth or solid rock excavation. The total estimated cost for the project is $453,950.00. The contract is for the City of Covington, which is located in Newton County, Georgia.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| CITY OF COVINGTON |
| FLOYD STREET GAS MAIN REPLACEMENT |
| ITEM | TYPE | DESCRIPTION | QTY. | UNIT | UNIT PRICE | TOTAL AMOUNT |
| 1. | M,L&E | 2" SDR 11 PE 2406/2708 Polyethylene Line Pipe | 9,000 | L.F. | $0.00 |
2. M,L&E Tie in per Detail A 14 Ea $0.00
3. M,L&E Fabrication and Installation of 4" Header per Detail B (includes tie-in to existing 4" main and 4" valve w/ valve box) 1 Ea $0.00
4. M,L&E 2" Polyball Ball Valve w/ valve box 21 Ea $0.00
5. M,L&E Insert short side service (includes self tapping tee, EFV, anodeless riser and meter valve) 39 Ea $0.00
6. M,L&E Insert longside service (includes self tapping tee, EFV, anodeless riser and meter valve) 32 Ea $0.00
7. L & E Mobilzation/Demobilization between Phase 1 and 2 1 Ea $0.00
| 8. | M,L&E | Squeegie/Pad Material | 10,000 | L.F. | $5.00 | $50,000.00 |
| five dollars & no/100 |
| 9. | L&E | Hard Surface Haul-off | 20,000 | Sq. Ft. | $4.00 | $80,000.00 |
| four dollars & no/100 |
| 10. | M,L&E | Type C Silt Fence | 100 | L.F. | $3.00 | $300.00 |
| three dollars & no/100 |
| 11. | M,L&E | Curb Inlet Filters | 50 | Ea. | $250.00 | $12,500.00 |
| ten dollars & no/100 |
| 12. | M,L&E | Sod replacement | 2,000 | Sq. Ft. | $2.00 | $4,000.00 |
| two dollars & no/100 |
| 13. | M,L&E | Tree Protection and Buffer Delineation Orange Fencing | 50 | L.F. | $3.00 | $150.00 |
| three dollars & no/100 |
| 14. | L & E | Per foot of Extra Depth where required | 500 | L.F. | $10.00 | $5,000.00 |
| ten dollars & no/100 |
| 15. | L & E | Solid Rock Excavation | 10 | C.Y. | $200.00 | $2,000.00 |
| two hundred dollars & no/100 |
| 16. | M,L&E | Asphalt/concrete replacement | 20,000 | Sq. Ft. | $15.00 | $300,000.00 |
| fifteen dollars & no/100 |
Total Cost (Items 1-16) $453,950.00