Q and A No. 5-7.pdf
PDF 66 KB Posted
- Attached to
- Containerized Housing Units Federal contract opportunity
- Solicitation number
- Not on record
About this file
This document contains questions and answers regarding Solicitation # FA301620Q00320001 for Containerized Housing Units at Joint Base San Antonio Lackland in Texas. The solicitation requires the delivery and installation of 10 containerized housing units, with each unit approximately 60-70 feet from the main power distribution panel. Additional requirements include supplying approximately 205 tons of type II sub-base gravel, with the ability to order 10% more. While the base has an on-site contractor, they can only maintain existing infrastructure, so the government prefers to have all work covered under one contract. The response deadline was extended to April 20, 2020 due to additional requirements outlined in the Statement of Objectives dated April 6, 2020.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Q and A No. 17-22.pdf | ||
| Q and A No. 12-16.pdf | ||
| Q and A No. 8-11.pdf | ||
| Q and A No. 4 (updated).pdf | ||
| Q and A No. 1-3.pdf | ||
| Q and A No. 4.pdf | ||
| Attachment 1 - Statement of Objectives - Addendum 1 (6 April 2020).pdf | ||
| Questions And Answers Sheet.docx | DOCX document | |
| Attachment 2 - Layout Specification 6 April 2020.pdf | ||
| Solicitation Amendment FA301620Q00320001.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
502 CONS/JBKAE Solicitation # FA301620Q00320001 JBSA Lackland, TX Containerized Housing Units
QUESTIONS & ANSWERS
Cut-off date for contractor questions is: 12:00 PM CST, 13 April 2020.
Questions
Question 5: Section 2.2 – What is the distance between the 2 CHU’s and the main power distribution panel?
Government Response: Answered in question 3. approximately 60’-70’ for each…120’-140’ total.
Question 6: Section 2.3.8 – How much additional gravel do you estimate?
Government Response: From our CE expert… 16 cubic yards per container X 2700lbs per ton= 20.5 tons per container X 10 CHUs=~205 Tons of type II sub-base. It might be safe to order 10% more.
Question 7: Suggestion – Have you considered using your local MATOC contractor for the electrical and gravel portion of this project? Might be a significant cost-savings if you went this route.
Government Response: We have a contractor on site, but the can only maintain existing infrastructure.
We prefer to have everything ion one contract.