N6449821R4037-Amendment 0001.pdf

PDF 339 KB Posted

Attached to
Bldg 1000 Lab Server Rooms Cooling Units Federal contract opportunity
Solicitation number
N6449821R4037
Issued by
Department of the Navy Naval Sea Systems Command

About this file

This statement of work outlines the requirements for a federal contract to replace cooling equipment in server rooms. The contractor will remove existing temporary cooling units and install new computer room air conditioning units in three locations at the Naval Surface Warfare Center in Philadelphia. One site will receive three 5-ton CRAC units, another an 8-ton unit, and a third a 10-ton unit ducted to the second location. The contractor must use an authorized control system installer and integrate the new equipment into the existing building automation system. All work must be completed within 120 days of receiving the notice to proceed. The Naval Sea Systems Command is the contracting agency.

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amedment 0001 to Soliciation N6449821R4037 is hereby issued to provide responses to questions submitted.

Questions and Answ ers continue on Page 2. The SOW has been updated based on the Questions and Answ ers provided. The new due date for receipt of proposal is 23 September 2021.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 27

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 17-Sep-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6449821R4037

X 9B. DATED (SEE ITEM 11)

19-Aug-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

17-Sep-2021

CODE

NAVAL SURFACE WARFARE CENTER PHILA

CODE 0222, SHANNON LUTES

215-897-1454, SHANNON.LUTES@NAVY.MIL

5001 SOUTH BROAD STREET

PHILADELPHIA PA 19112

N64498 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6449821R4037

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 1

The responses to questions received for N6449821R4037 are as follows:

Q1. Do the units have to control humidity as well? Meaning are we required to run a water supply to the units to add humidity?

A1. The units do not need to control humidity (humidifiers are not required).

Q2. The RFP details use of PPQs for past performance. If we have CPARS available should we utilize those in lieu of the PPQ form?

A2. CPARS should not be sent in lieu of PPQs (Attachment 13). However, as stated on page 9 of the solicitation, the Government may review and consider any other sources of information for evaluating past performance. CPARS information may be reviewed by the Government, in addition to any submitted PPQs.

Q3. Also, in the RFP, page 7 of 90, there is a page limitation for past performance of 3 pages. Is that 3 pages per each project example or is it 3 pages total for all 3 projects?

A3. The page limitation is for the entirety of the Past Performance factor. However, as delineated in Section 00 21 16, paragraph 2.1 on page 5 of the solicitation, Title/Cover Page, Tables of Contents, Glossaries of abbreviations and acronyms, PPQs, CPARS, and attachments do not count towards the page limitation.

Q4. Is there a piping route for the new units? It is hard to determine any lengths without sketches/drawings or knowing where the pipes will be ran.

A4. Pipe routing drawings were not provided. Intent is to locate condensers inline on roof along penthouse south wall adjacent existing 15-ton condenser (with mfg. recommended spacing).

Q5. In the photos it references a 15 ton unit – this unit is not mentioned anywhere in the RFP – Please advise what this is and what needs to be done with this unit.

A5. Nothing is required to be done with the existing 15 ton unit. The pictures of the existing 15 ton unit were shown for reference to provide an example of a condenser mounted on the roof and acceptable line-set supports & penetration through wall.

Q6. It appears we are to install 2 new panels – (PP1C & PP3P) – Please confirm? Also can anyone verify length from PPE LAB panel to panels PP1C & PP3P

A6. NAVFAC has installed panels, PP1C and PP3P, to facilitate other projects on the fourth floor. This is where the contractor will take their power for the new units from these panels. See section 23.23

Q7. For the controls is there an existing panel and system we are tying into inside Bldg 1000?

There are existing panels for other equipment. Each room will have a new enclosure installed for the units. One enclosure will have two power panels in room 473A. One for the 8-ton unit and the other for the 10-ton unit. Room 477A will have an enclosure with three power panels. One power panel for each of the 5-ton units. The power panels can be connected to an existing communication panel.

Q8. I have not found anyone that has attended the site visit – was there a sign in sheet?

A8. 5 contractors attended the site visit:

Diversified Refrigeration,Inc.

Surety Mechanical DAGDA Corporation Xtreme Mechanical Peterson Service

Q9. How many temporary units are there that need removed and turned over?

A9. 2x 5-ton portable units (1x in each server room)

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 20-Sep-2021 03:30 PM to 23-Sep-2021 03:30 PM.

SECTION 01 00 00 - GENERAL REQUIREMENTS

The following have been modified:

STATEMENT OF WORK

BLDG 1000 Repair HVAC 4th Floor Lab Server Rooms

STATEMENT OF WORK

Division 01 – General Requirements

Section 01 11 00 – Summary of Work

1.1 SYNOPSIS: The Contractor shall provide all labor, material, tools, equipment, supplies, testing, and supervision to complete all work described in this Statement of Work (SOW) for Lab Server Rooms, which are located on the 4th floor of Bldg 1000 at the Philadelphia Naval Business Center (PNBC), Philadelphia, PA 19112. The Contractor shall remove the existing temporary cooling units and install three (3) 5-ton Computer Room Air Conditioning (CRAC) units in room 477A, one (1) 8-ton CRAC unit in room 473A, and one (1) 10-ton CRAC unit in room 473 that will be ducted into room 473A. The Contractor shall return the temporary portable A/C units to the Government for future use. After completion of all work, the area shall be properly cleaned and the system shall be balanced and tested.

All work associated with termination of communication cabling into the main Automated Logic Corporation (ALC) Building Automation System (BAS) Direct Digital Control (DDC) system, new system design and development of the associated shop drawings, and programming of the controllers tied into the Automated Logic BAS DDC system should be completed by personnel with training as detailed in SOW Section 1.13.12.

1.2 SITE LOCATION: The work is located on Government-owned property at the Philadelphia Naval Business

Center (PNBC), also known as the Philadelphia Navy Yard. The work is located on the fourth floor in rooms 473, 473A and 477A of Bldg 1000, Naval Surface Warfare Center Philadelphia Division (NSWCPD), having street address of 5101 South 18th Street, Philadelphia, PA 19112. Bldg 1000 is four stories; approximately 376,000 gross square feet; and, contains a mixed use of personnel, warehouse, and laboratory spaces. See SOW Attachment 1 for overall site location within PNBC.

1.3 GOVERNMENT TECHNICAL POINT OF CONTACT (TPOC): The TPOC is a representative of the

NSWCPD, Contracting Officer and provides technical and administrative assistance related to the subject contract and work. All scheduling and coordination shall be through the NSWCPD TPOC, who is Jacob Scholz (215-897-7028).

Section 01 14 00 – Work Restrictions

1.4 GOVERNMENT FURNISHED UTILITIES: The Government shall furnish the following utility services for use as may be required for the work to be performed under the contract: electricity and potable water.

Government-furnished electricity may be used by the contractor unless contractor’s use adversely impacts a building’s electrical distribution system and equipment. Information concerning the location of existing outlets may be obtained from the NSWCPD TPOC. The Contractor shall provide and maintain the necessary service lines from existing Government outlets to the site of the work. For the utilities specified above, they shall be furnished at no cost to the Contractor. In the event that the Government is unable to provide the required types of utilities, the Contractor shall arrange for the required utilities.

1.5 PERMITS: The Contractor shall obtain all appointments, licenses, and permits required for the prosecution of the work. The Contractor shall comply with all applicable or relevant and appropriate federal, state, and local laws. Evidence of such permits and licenses shall be provided to the Contracting Officer or his/her representative before work commences.

1.6 INSTALLATION ACCESS, SECURITY, AND CONTRACTOR BADGES AND IDENTIFICATION

1.6.1 No employee or representative of the Contractor shall be admitted to the work site unless the employee has satisfactorily completed an installation-pass application (business/Contractor-employee) and has furnished satisfactory proof that the employee is a citizen of the United States.

The Government Security Office shall approve each installation-pass application before the employee or representative shall be authorized admittance to the work site by NSWCPD.

1.6.2 Contractor and subcontractor personnel shall carry photographic identification (ID) on their person at all times on-site for review by Government Security or Access Control Personnel upon request.

For each day on NSWCPD property, the contractor shall complete the current version of the NSWCPD COVID-19 Screening and Self-Assessment Questionnaire (SOW Attachment 2) for each employee. If there are any “Yes” answers, the contractor shall contact the TPOC or the Contractor Officer.

1.6.3 Citizenship Requirements: Work under this contract is restricted to U.S. citizens. No employee or representative of the Contractor shall be admitted to the work site unless he/she furnishes satisfactory proof that he/she is a citizen of the United States. In accordance with current NSWCPD security protocol, contractor employees who hold dual citizenship shall not be granted security clearance to our facilities. Documents acceptable for Proof of Citizenship include:

1.6.3.1 Birth registration card.

1.6.3.2 Certificate of live birth, birth certificate.

1.6.3.3 Certificate of Naturalization.

1.6.3.4 Certificate of registration.

1.6.3.5 DD-214 (Shall Cite Birthplace).

1.6.3.6 DD Form 4 (Contract for Enlistment and Shall Cite Birthplace).

1.6.3.7 DD 1966 (Application for Enlistment).

1.6.3.8 Military discharge papers (shall cite birthplace).

1.6.3.9 Delayed birth certificate.

1.6.3.10 Hawaii certificate of foreign birth.

1.6.3.11 Hospital birth certificate.

1.6.3.12 Marriage license certificate.

1.6.3.13 Merchant marine certificate.

1.6.3.14 Military officer ID card.

1.6.3.15 Notification of birth registration.

1.6.3.16 State of Hawaii ID card.

1.6.3.17 USA passport.

1.6.3.18 Verbal inquiry with State of Hawaii Vital Statistics Office.

1.6.4 Application for Contractor Identification Badges: The Contractor's employees or representatives who shall be working inside NSWCPD facilities or secure perimeters shall obtain a Contractor's ID badge which can be valid for up to 12 months.

For all Contractor employees or representatives that do not have a CONFIDENTIAL or higher security clearance, the Contractor shall provide a completed SECNAV 5512/1 (DoN Local Population ID Card/Base Access Registration Form) for each employee or representative to the NSWCPD TPOC for CNRMA (Command Navy Region Mid-Atlantic) vetting, review and approval.

Once approved, the Contractor's employees shall report to Security (Building 29) with two forms of identification for issuance of the ID badge. The Contractor shall obtain the required employee ID badges from the Government. The ID badge shall be returned within 5 calendar days to Security (Building 29) when an employee leaves the Contractor's service, when the job is complete, or the ID badge has expired. The Government is not responsible for any cost or lost time associated with obtaining or the use of daily or Contractor ID badges.

One-Day Visitor Badges: The Contractor's employees or representatives can obtain a daily Visitor's badge from the Security desk inside NSWCPD facilities; however, a Government escort shall be required at all times, and the visitor badge shall only be valid for the facility where the badge was issued. The use of daily visitor's ID badge is not recommended, as a Government escort shall be scheduled in advance and escort's availability is limited and granted on a case-by-case basis (i.e., availability is not guaranteed). The Contractor's personnel would have to obtain daily passes, be subject to daily mandatory vehicle inspection, and would have limited access to the installation if using a Visitor badge. The Government is not responsible for any cost or lost time associated with escort availability in conjunction with the use of Visitor’s badges for the Contractor’s employees or representatives.

1.6.5 General Access Requirements and Restrictions: The following access requirements and restrictions apply to work at any NSWCPD facility or secured perimeter:

1.6.5.1 No employee or representative of the Contractor shall be admitted to the site of the work unless they have satisfactorily completed the Application for Contractor Identification Badge process and have furnished satisfactory proof that they are a citizen of the United States. The Government Security Office shall approve each base application form before the employee or representative shall be authorized admittance to the site of work by the Government.

1.6.5.2 The Contractor is responsible to collect and account for all identification badges issued to its personnel at the expiration of the contract, expiration of the badge or when no longer required. Collected badges shall be returned by the Contractor to the NSWCPD Security Office (Building 29).

1.6.5.3 Comply with all security regulations and policy currently in force by the Government Security Office having jurisdiction and as communicated directly by Government Security personnel or as conveyed by the NSWCPD TPOC.

1.6.5.4 Employees or representatives of the Contractor, while working at NSWCPD, shall display the Government issued badge over the front of their outer clothing at all times.

1.6.5.5 Roll up/garage doors shall only be permitted to be opened by Government personnel or Access Control Personnel (ACP). The ACP or Government personnel shall guard the door during the entire time the door is un-secured. The doors shall be secured immediately following its use, unless otherwise permitted by the Command Security Director.

1.6.5.6 Fence gates shall only be permitted to be opened by Government personnel or Access Control Personnel (ACP). The ACP or Government personnel shall guard the gate during the entire time the gate is un-secured. The gate shall be secured immediately following its use, unless otherwise permitted by the Command Security Director.

1.6.5.7 Commercial vehicles (with company logo) that are required to enter the fence line perimeter or enter the building at any NSWCPD facility shall be inspected by the Government Mobile Vehicle Inspection Team (MVIT) currently situated adjacent to Bldg 753 along Langley Avenue prior to entering the property. No personally-owned vehicles (POVs) are permitted within the fence line perimeter of any NSWCPD facility.

Coordinate vehicle inspections with the NSWCPD TPOC.

1.6.5.8 No Contractor or personally-owned cameras are allowed inside NSWCPD facilities. If photographs are required for design or work records, submit a written request to the NSWCPD TPOC or Contracting Officer to have photographs taken by a Government Official using a Government camera. Photographs taken by the Government shall be reviewed by Security before release to the Contractor.

1.6.5.9 If a security alarm is required to be temporarily disabled for a work activity, the Contractor shall submit a completed Request to Mask Security Alarm form to the NSWCPD TPOC at least three business days in advance of the required date. The NSWCPD TPOC shall coordinate with the NSWCPD Security Office to obtain approval for the request.

1.7 IDENTIFICATION OF CONTRACTOR VEHICLES: The Contractor shall obtain parking passes for company vehicles, if required, from the Contracting Officer. The company name shall be displayed on each of the Contractor's vehicles in a manner and size that is clearly visible. All vehicles shall display a valid state license plate and safety inspection sticker, if applicable, and shall be maintained in good repair. See SOW Section 1.6.5.7 above about inspection of contractor commercial vehicles by the Government MVIT.

1.8 OPERATIONAL SECURITY (OPSEC): The Contractor shall protect critical information associated with this contract to prevent unauthorized disclosure. The NSWC Philadelphia Division's (NSWCPD) Critical Information List, (CIL) will be provided on site, if warranted. Performance under this contract requires the contractor to adhere to OPSEC requirements. The Contractor may not impose OPSEC requirements on its subcontractors unless NSWCPD approves the OPSEC requirements. During the period of this contract, the Contractor may be exposed to, use, or produce, NSWCPD Critical Information (CI) and/or observables and indicators which may lead to discovery of CI. NSWC PD's CI will not be distributed to unauthorized third parties, including foreign governments, or companies under Foreign Ownership, Control, or Influence

(FOCI).

CUI correspondence transmitted internally on the contractor's unclassified networks or information systems, and externally, shall be protected per NIST SP-800-171, Protecting Controlled Unclassified Information (CUI) in Non-federal Systems and Organizations. Assembled large components/systems being transported to and from testing areas, other production or government facilities (whether or not on public roadways) shall be in an enclosed van trailer or covered flatbed trailer. Component/System outside storage, staging, and test areas shall be shielded/obscured from public view wherever physically possible.

NSWCPD's CI shall not be publicized in corporate wide newsletters, trade magazines, displays, intranet pages or public facing websites. Media requests related to this project shall be directed to the PCO, and the COR who will forward the required to the NSWCPD Public Release Authority for review.

Any attempt by unauthorized third parties to solicit, obtain, photograph, or record, or; incidents of loss/compromise of government Classified or CI, Business Sensitive, Company Proprietary information related to this or other program must be immediately reported to the contractor's Facility Security Officer and Cognizant Security Office and/or the Naval Criminal Investigative Service, and the NSWC PD Security Division (Code 105.1). Questions concerning these requirements shall be directed to the PCO, and the COR who will forward the request to the NSWCPD Security Division (Code 105.1).

Section 01 30 00 – Administrative Requirements

1.9 SUPERVISION AND CONTRACTOR PERSONNEL: The Contractor shall have at least one qualified supervisor, i.e., Project Superintendent, capable of reading, writing, and conversing fluently in the English language on the work site full-time during all working hours. The Project Superintendent shall have a minimum of 5 years experience with projects of similar size and scope. The Project Superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project and shall be onsite anytime work is being performed. The Project Superintendent shall attend (either remotely or in-person) all meetings associated with this project. The Contractor shall provide qualified personnel, mechanics, and subcontractors to perform all work. A minimum of two Contractor personnel are required to perform the functions of Project Superintendent, Site Safety and Health Officer (SSHO), and Contractor Quality Control System Manager (CQCSM); the latter two personnel responsibilities are described in the Subsections below:

1.9.1 Site Safety and Health Officer (SSHO): The contractor shall provide a Safety oversight team that includes a minimum of one (1) Competent Person at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO shall visit the work site daily, unless specified differently in the contract, to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor. The SSHO’s training, experience, and qualifications shall meet EM 385-1-1 paragraph 01.A.17 and all associated sub-paragraphs. The SSHO may serve as the Superintendent on this project.

1.9.2 Contractor Quality Control System Manager (CQCSM): Provide a CQCSM for the work site to manage and implement the Contractor Quality Control (CQC) program. The CQCSM shall be responsible for overall management of the Contractor Quality Control program and has the authority to act and give direction in all CQC matters for the Contractor. The CQCSM shall have been regularly engaged in work and repair projects of similar type, size, and complexity that has included the major trades executing the work of this contract. The CQCSM shall be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification, safety compliance, and sustainability. The CQCSM may serve as the SSHO on this project; however, the CQCSM cannot perform the duties of Project Superintendent.

Section 01 32 16.00 20 – Small Project Construction Project Schedules

1.10 PROJECT SCHEDULE: Prior to the start of work, the Contractor shall prepare and submit, a work schedule to the NSWCPD TPOC. The schedule shall, at a minimum, show contract-award date, Notice-To- Proceed (NTP) date, work activities, submittals, material/equipment delivery, utility outages, on-site work, testing, closeout activities, and Contract Completion Date (CCD). The schedule shall be time scaled and generated using scheduling software. The schedule shall be kept current, i.e., updated and submitted regularly, during this contract, reflecting actual activity progress and plan for completing the remaining work.

1.11 EXECUTION OF WORK: The Contractor’s and subcontractor(’s) work shall be performed during normal duty hours from 0700 to 1600, Monday through Friday, as directed by the NSWCPD TPOC. No work shall be performed after normal duty hours or on Government holidays unless authorized by the NSWCPD TPOC in advance. All access shall be closely coordinated with the NSWCPD TPOC.

Section 01 33 10 – Submittal Procedures

1.12 SUBMITTALS: The Contractor shall submit the pre-work submittals of SOW Section 1.13 below within ten (10) calendar days after award. The Contracting Officer or NSWCPD TPOC may request submittals in addition to those specified when deemed necessary to describe adequately the work covered in the respective sections. Each submittal shall be legible, well-organized, complete, and in sufficient detail to allow ready determination of compliance with contract requirements. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only “FIO.”

1.12.1 Submittal Procedures: Both “G” and “FIO” submittals shall be transmitted to NSWCPD using a formal Transmittal format. Provide submittals in electronic format, with the exception of material samples. Compile the electronic submittal file as a single, complete document, to include the ENG FORM 4025-R Transmittal Form available for download at:

https://www.publications.usace.army.mil/USACE-Publications/Engineer-Forms/. Note that all instances of the “US Army Corp of Engineers” on the transmittal form shall be interpreted as “Naval Surface Warfare Center Philadelphia Division.” Name the electronic submittal file according to its contents and its revision level (e.g., rev00, rev01, etc.) or submittal date. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Provide hard copies of submittals when requested by the Contracting Officer or NSWCPD TPOC. Submittals requiring Government approval shall be scheduled and made prior to the acquisition of the material or equipment covered thereby.

1.13 PRE-WORK SUBMITTALS: All Submittals shall be approved by the NSWCPD TPOC prior to the start of work.

1.13.1 Pre-work submittals marked with a “G” require Government approval prior to the Contractor's mobilization to the work-site location.

1.13.2 Contractor’s Daily Production Report: See SOW Attachment 3. The Requirements are listed in

Section 1.27 below.

1.13.3 Project Schedule - G: Prior to the start of work, the Contractor shall prepare and submit a work schedule to the NSWCPD TPOC per SOW Section 1.10 above.

1.13.4 Requirements for Contractor Lift Operations: See SOW Attachment 4. This shall be completed as required per Section 1.15.

1.13.5 Machinery and Mobile Equipment Checklist: See SOW Attachment 5. This shall be completed as required per Section 1.15 and Section 1.19.2.14.

1.13.6 Activity Hazard Analysis (AHA) - G: in accordance with EM 385-1-1. See SOW Attachment 6 for blank form and sample. See SOW Section 1.19.3 for additional information. The AHA shall cover all aspects of the work.

1.13.7 Accident Prevention Plan (APP) - G: The Contractor shall submit a site-specific APP to the NSWCPD TPOC. The site-specific APP shall outline the job-specific hazards associated with the project scope and reflect the Contractor’s overall safety and health program. At a minimum, the plan shall meet the requirements of the abbreviated Accident Prevention Plan identified in the U. S. Army Corps of Engineers Safety and Health Requirements Engineering Manual, EM-385-1-1, Appendix A.

1.13.8 All Required Security Forms for Contractor ID, Vetting, and Badging – Prior to the start of work, the Contractor shall identify its personnel who will perform the work on-site and submit corresponding ID, vetting, and badging forms and supporting information. See Section 1.6 above, especially regarding SECNAV Form DD5512.

1.13.9 List of proposed Subcontractors – FIO: Provide the NSWCPD TPOC a list of all proposed subcontractors including address, telephone number, point of personal contact, qualifications, and certifications for the completion of project tasks in this SOW.

1.13.10 The contractor shall provide licenses for all HVAC and Electric personnel who shall be working on this project.

1.13.11 List of proposed Products - G: Provide the NSWCPD TPOC a list of proposed Product cut sheets, manufacturer specification sheets, manufacturers installation guidelines, equipment cut sheets, fan curves, etc., and as applicable Safety Data Sheets (SDS) for all materials to be used in the performance of this project. All equipment shall be approved by the government TPOC prior to the start of work. Note that this overall, comprehensive list of proposed products is G; however, some individual items on this list of proposed products may be considered FIO by the NSWCPD TPOC.

1.13.12 Contractor Personnel Qualifications and Certification(s):

1.13.12.1 HVACR Technician - Prior to the start of work, provide Proof of Certification for the lead technician onsite that conforms with the Code of Federal Regulations Title 40, Chapter I, Subchapter C, Part 82, Subpart F. Certification is required for technicians performing repair, maintenance, service, and disposal of appliances containing ozone depleting refrigerant under Section 608 of the Clean Air Act. The Contractor shall provide City of Philadelphia HVAC technician certification.

1.13.12.2 Building Automation System Engineers - The Contractor should utilize engineering personnel trained by ALC or a third-party training service authorized to provide training on behalf of ALC with a minimum of 5 years of experience that routinely develop plans and specifications for BAS, develop and troubleshoot programs for the operation of the BAS, and develop graphical user interfaces for operators.

1.13.12.3 Building Automation System Field Technicians - The Contractor should utilize field technicians trained by ALC or a third-party training service authorized to provide training on behalf of ALC with a minimum of 2 years’ experience each that routinely perform installation, termination, and field programming work on building automation systems.

Provide a foreman, lead or supervisory field technician at all times work is performed with a minimum of 5 years of experience that routinely performs installation, termination, and field programming work on building automation systems.

1.13.12.4 Building Automation System Engineers and Field Technicians - Design engineers and field technicians should be trained in the courses listed below provided by Automated Logic Corporation (ALC) or an approved third-party authorized to provide the training on ALC’s behalf.

Networking I and II Design Engineer I and II (design engineers only) Eikon I and II Field Technician

I and II (field technicians only) Networking I and II BACnet

Integration II Viewbuilder I and II Modbus Integration II

1.14 ADDITIONAL SUBMITTALS: Contractor shall make other submittals as required in this Statement of

Work, in addition to the pre-work submittals of Section 1.13 above. In general, the additional submittals include material samples, material information or cuts sheets, Safety Data Sheets (SDS), contractor qualifications, technical manuals, test plans, etc. All submittals other than pre-work submittals shall be submitted by the Contractor a minimum of fourteen (14) calendar days before the start of the particular task or definable feature of work (DFOW) to which the submittal is associated to provide sufficient Government review-and-approval time. One additional submittal is listed below:

1.14.1 Warranty Information – G: Contractor shall submit warranty information guaranteeing all products and workmanship to be free of defects for a minimum of one year after acceptance. Electric motors shall be free of defects in material and workmanship for a minimum of two years after acceptance.

1.15 CONTRACTOR REQUIREMENTS FOR LIFT OPERATIONS: Contractor shall comply with the requirements of Naval Facilities Command (NAVFAC) P-307, Weight Handling Program Management, and SOW Attachment 4, “Requirements for Contractor Lift Operations” for all work performed with cranes or other machines used to lift equipment or materials. Related to lift and weight-handling operations, contractor shall submit Machinery and Mobile Equipment Check List (SOW Attachment 5) if required.

Section 01 35 26 – Governmental Safety Requirements

1.16 DIRECTIVES: The Contractor and its employees shall comply with all referenced regulations, directives, and instructions. Applicable Department of Defense (DOD), Secretary of the Navy (SECNAV), Chief of Naval Operations (OPNAV), and other directives, instructions, and regulations are available from the Contracting Officer.

1.17 FIRE PROTECTION: The Contractor and its employees shall know where fire alarms are located and how to turn them on. The Contractor shall handle and store all combustible supplies, materials, waste, and trash in a manner that prevents fire or hazards to persons, facilities, and materials. Contractor employees operating critical equipment shall be trained to properly respond during a fire alarm or fire in accordance with activity instructions.

1.18 ENVIRONMENTAL PROTECTION: The Contractor shall comply with all federal, state, and local environmental protection laws, regulations, and standards. The Contractor shall coordinate all environmental protection matters with the Contracting Officer. The Activity Environmental Protection Coordinator or other authorized officials may inspect any of the facilities operated or maintained by the Contractor at any time and without prior notice. If a regulatory agency assesses a monetary fine against the Government for violations resulting from Contractor actions, the Contractor shall reimburse the Government for the amount of the fine and related costs. The Contractor shall clean up any oil or chemical spills resulting from its operations at its own expense. The Contractor shall not create a nuisance or hazard to the health of military or civilian personnel.

1.19 SAFETY REQUIREMENTS AND REPORTS

1.19.1 All work and equipment shall be performed and installed in accordance with local, state, federal, and industry codes, standards, and regulations.

1.19.2 All work shall be conducted in a safe manner and shall comply with all requirements of the U.S.

Army Corps of Engineers Safety and Health Requirements Manual, EM-385-1-1. The Contractor shall be responsible for instructing its employees in appropriate safety measures and shall not permit them to place machines and other equipment in traffic lanes or other locations in such a manner as to create safety hazards. The Contractor shall employ a competent person as defined in EM-385-1-1 to function as the Site Safety and Health Officer (SSHO). The following paragraphs denote minimum safety requirements. Contractor shall consult EM-385-1-1 for additional information or any safety issues not discussed in this specification.

1.19.2.1 Personal Protective Equipment Minimum Requirements

(a) Head Protection: All persons working in or visiting hard-hat areas shall be provided with and required to wear Type I or Type II, Class G meeting the requirements of ANSI Z89.1 Hardhat areas are those areas with potential hazard of head injury.

(b) Clothing: Employees shall wear clothing suitable for the weather and work conditions: the minimum for work sites shall be short sleeve shirt, long pants (excessively long or baggy pants are prohibited).

(c) Protective Footwear: Employees shall wear safety–toed boots meeting ANSI Z41 while working on work sites.

(d) Eye and Face Protection: All eye and face protection shall meet the requirements of ANSI/ASSE Z87.1, employees shall also use eye side protection.

(e) High visibility vests shall be worn when working around work equipment or when working on highways.

1.19.2.2 Display of Safety Information: Within one calendar day after commencement of work, erect a safety bulletin board at the job site. The following information shall be displayed on the safety bulletin board in clear view of the on-site work personnel, maintained current, and protected against the elements and unauthorized removal.

(a) Map denoting the route to the nearest emergency care facility.

(b) Emergency phone numbers.

(c) Copy of Activity Hazard Analysis (AHA).

(d) Occupational Safety and Health Administration (OSHA) 300A form. A copy of this form shall also be given to NSWCPD Safety department.

1.19.2.3 Emergency Medical Treatment: Contractor shall arrange for its own emergency medical treatment. The Government has no responsibility to provide emergency medical treatment.

1.19.2.4 Use of Hand and Power Tools: Hand and power tools shall be of a manufacturer listed by a nationally recognized testing laboratory for the specific application for which they shall be used.

(a) Use, inspection, and maintenance:

1.19.2.4.a.1 Hand and power tools shall be used, inspected, and maintained in accordance with the manufacturers’ instructions and recommendations and shall be used only for the purpose for which designed.

1.19.2.4.a.2 Hand and power tools shall be inspected, tested, and determined to be in safe operating condition before use. Continued periodic inspections shall be made to assure safe operating condition and proper maintenance.

1.19.2.4.a.3 Hand and power tools shall be in good repair and with all required safety devices installed and properly adjusted. Tools having defects that shall impair its strength or render them unsafe shall be removed from service.

1.19.2.4.a.4 Loose and frayed clothing, loose long hair and dangling jewelry (including dangling earrings, chains and wristwatches) shall not be worn while working with any power tools.

(b) Guarding—Power tools designed to accommodate guards shall be equipped with such guards:

1.19.2.4.b.1 All guards shall be functional.

1.19.2.4.b.2 Reciprocating, rotating, and moving parts of equipment shall be guarded if exposed to contact by employees or otherwise create a hazard.

1.19.2.5 Portable Extension Cords: Portable extension cords shall be sized in accordance with manufacturer ratings for the tool to be used and shall be protected from damage. All damaged extension cords shall be immediately removed from service. Portable extension cords shall meet the requirements of National Fire Protection Association (NFPA) 70 and shall contain GCFI in all runs (pigtails allowed).

1.19.2.6 Ladders: All portable ladders shall be of sufficient length and shall be placed so that workers shall not stretch or assume a hazardous position. The top or top step of a stepladder shall not be used as a step unless it has been designed to be so used by the manufacturer. Ladders may be used as work platforms only when use of small hand tools or handling of light material is involved.

1.19.2.7 Fall Protection: Fall protection shall be provided for safe access for all work activities as required. For confined space, fall protection shall be provided for safe access to enter, exit, and potentially emergently be removed from confined space per 29 CR 1910.146.

For above entries, a min of a tripod with winch extraction capabilities shall be used.

1.19.2.8 Lockout/Tag Out: Coordinate all control activities with the designated NSWCPD TPOC. Apply, monitor, and remove proper lockout and tag out devices per contractors established Lockout/Tag Out procedures and 29 CR 1910.147.

1.19.2.9 Asbestos Abatement: No asbestos based products shall be used on this project. If there is potential for activities to disturb ACM, an asbestos abatement plan shall be developed.

The plan shall be in accordance with 29 CFR 1910.1001; 29 CFR 1926.1101; and 40 CFR 61, Subpart M The written plan(s) shall be submitted for acceptance by TPOC and local Safety office before beginning work.

1.19.2.10 Lead Abatement: No lead Paint shall be used on this project. If there is potential for activities to generate unacceptable occupational exposure to LBP, a written lead compliance plan shall be written. The lead compliance plan shall be in accordance with

29 CFR 1910.1025 and 29 CFR 1926.62. The written plan(s) shall be submitted for acceptance by TPOC and local Safety office before beginning work.

1.19.2.11 Sanitation Requirements: Provide drinking water and toilets as needed for work personnel.

1.19.2.12 Fire Protection: Provide two ABC fire extinguishers at the work site to guard against potential fires.

1.19.2.13 Fuel-Powered Tools: When fuel-powered tools are used, they shall not be fueled while running, while hot, or near an open flame.

1.19.2.14 Machinery and Mobile Equipment: The Contractor shall complete an equipment checklist (SOW Attachment 5) for any work equipment (backhoes, lift trucks, bobcats) that shall be used on site.

1.19.3 Activity Hazard Analysis (AHA): The principle purpose of an AHA (SOW Attachment 6) is to reduce the overall risk of the hazards associated with the work. An AHA shall be developed by the Contractor for every operation involving a type of work presenting hazards not experienced in previous project operations or where a new work crew or subcontractor is to perform work. The analysis shall identify and evaluate hazards and outline the proposed methods and techniques for the safe completion of each phase of work. At a minimum, define activity being performed (can use the definable features of work). A definable feature of work (DFOW) is a task which is separate and distinct from other tasks, has the same control requirements and work crews, sequence of work, specific safety and health hazards anticipated (slip or trips, cuts, dust or chips in eyes), control measures (to include personal protective equipment) to eliminate or reduce each hazard to acceptable levels, equipment to be used (hand tools, backhoe), inspection requirements (list the inspection requirements for the activity to ensure the controls are working, and equipment is inspected to ensure proper operation), training requirements for all involved (any unique training required to make the established controls work), and the competent person in charge of that phase of work. The AHA shall be continuously reviewed and, when appropriate, modified to address changing site conditions or operations. The analysis shall be used during daily inspections to ensure the implementation and effectiveness of the activity’s safety and health controls. Activity Hazard Analysis shall be updated as necessary to provide an effective response to changing work conditions and activities.

1.19.4 Accident Reports and Notifications

1.19.4.1 Accident Reports: For recordable injuries, illnesses, and property damage accidents resulting in a least $2,000 in damages, the prime Contractor shall conduct an accident investigation to establish the root cause of the accident, complete the Navy Contractor Significant Incident Report (CSIR), and provide the report to the Contracting Officer within five calendar days of the accident. The Contracting Officer shall provide copies of any required or special forms.

1.19.4.2 Accident Notification: Notify the Contracting Officer as soon as practical, but no later than four hours after any accident meeting the definition of recordable injuries or illnesses, high visibility accidents, or property damage equal to or greater than $2,000.

Information shall include Contractor name, contract title, type of contract, name of activity, installation or location where accident occurred, date and time of accident, names of personnel injured, extent of property damage (if any), extent of injury (if known), and brief description of accident (to include type of work equipment used, Personal Protective Equipment (PPE) used, etc.). Preserve the conditions and evidence on the accident site until the Government investigation team arrives on site and Government investigation is conducted.

1.19.4.3 Definition of a Recordable Injury or Illness: Any work related injury or illness that results in:

(a) Death, regardless of the time between the injury and death, or the length of the illness;

(b) Days away from work;

(c) Restricted work;

(d) Transfer to another job;

(e) Medical treatment beyond first aid;

(f) Loss of consciousness;

(g) A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result as listed above.

1.19.5 The Contractor's workspace may be inspected periodically for OSHA and Navy violations.

Abatement of violations shall be the responsibility of the Contractor and/or the Government as determined by the Contracting Officer. The Contractor shall provide assistance to the Safety Office escort and the federal or state OSHA inspector if a complaint is filed. Any fines levied on the Contractor by federal or state OSHA offices due to safety/health violations shall be paid promptly.

1.19.6 If the Contractor fails or refuses to promptly comply with safety requirements, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such stop order shall be made the subject of claim for extension of time or for excess costs or damages to the Contractor.

1.19.7 The Contracting Officer shall investigate all complaints of unsafe or unhealthful working conditions received from Contractor's employees, federal civilian employees, or military personnel. The Contracting Officer shall notify the Safety group of the results of such investigations.

1.20 HOT WORK: For all hot work, a hot-work permit is required and a permit shall be obtained through the

Government Fire Inspector. Requests for hot work permits shall be submitted to the NSWCPD TPOC with a 48-hour notice for review. Hot work in electrical- or mechanical-room space shall require a gas-free test prior to the Government fire inspector granting approval. In accordance with the Government fire inspector’s requirements, the Contractor shall perform this test daily. The Government fire inspector shall approve the instrument used. Fire extinguishers shall be provided by the Contractor at ALL locations where cutting is performed.

1.21 CONFINED SPACE: The Contractor shall comply with 29 CFR 1910.146 regarding permit-required confined space entry. The contractor shall provide a competent person to write all confined space permits.

1.22 HAZARDOUS MATERIAL: The Contractor is responsible for the handling, storage, removal, and disposal of hazardous material. Hazardous material waste shall be collected, stored, and disposed of in accordance with Navy, Federal, State, and Local requirements.

1.23 ELECTRICAL SAFETY: The contractor shall comply with Electrical Safety procedures in accordance with 29 CFR 1926. For additional information, refer to Chapter 12, of NAVSSESINST 5100.14G.

1.24 LOCK-OUT, TAG-OUT: The contractor shall comply with NSWCPD Lock-out/Tag-out procedures in accordance with Chapter 11 of NAVSSESINST 5100.14G and 29 CFR 1926. Only authorized NSWCPD personnel shall perform the Lock-Out and Tag-Out of Electrical, Mechanical, Piping, Machinery, or Equipment.

Section 01 42 00 – Sources for Reference Publication

1.25 REFERENCES: The publications listed below form a part of this Statement of Work and are incorporated by reference. Provision and installation of the materials and components comprising this Statement of Work shall be in compliance with applicable or relevant and appropriate requirements, including the following industry standards and regulations:

1.25.1 American National Standards Institute (ANSI), latest revision.

1.25.2 National Fire Protection Association (NFPA), latest revision.

1.25.3 Underwriters Laboratories (UL), latest revision. All material shall be Underwriters Laboratories

(UL) listed unless otherwise indicated.

1.25.4 National Electrical Manufacturers' Association (NEMA), latest revision.

1.25.5 American Society for Testing and Materials (ASTM), latest revision.

1.25.6 Insulated Cable Engineers Association (ICEA), latest revision.

1.25.7 Institute of Electrical and Electronic Engineers (IEEE), latest revision.

1.25.8 Builders Hardware Manufacturers Association (BHMA), latest revision.

1.25.9 National Electrical Safety Code (NESC), latest revision.

1.25.10 International Building Code (IBC), except as modified by Unified Facilities Criteria (UFC) 1-200- 01, DoD Building Code.

1.25.11 EM-385-1-1, US Army Corps of Engineers S&H Manual.

1.25.12 NFPA 70 NEC, current revision

1.25.13 ASME Section IX, latest revision

1.26 LIST OF ATTACHMENTS: The following attachments form part of this Statement of Work and are incorporated by reference:

1.26.1 Attachment 1, Site Map PNBC (1 page);

1.26.2 Attachment 2, NSWCPD Entry Screening Assessment (1 page);

1.26.3 Attachment 3, Contractor Production Report (1 page);

1.26.4 Attachment 4, Requirements for Contractor Lift Operations (8 pages);

1.26.5 Attachment 5, Mobile Construction Equipment Checklist (2 pages);

1.26.6 Attachment 6, Activity Hazard Analysis (3 pages);

1.26.7 Attachment 7, Photographs (5 pages):

1.26.8 Attachment 8, Power Panel PPE Lab Rm 410 (1 page); and,

1.26.9 Attachment 9, Power Riser Diagram (1 page).

Section 01 45 00.10 20 – Quality Control for Minor Construction

1.27 QUALITY CONTROL (QC) AND DAILY PRODUCTION REPORTS: The Contractor shall submit a

“Contractor Production Report” (SOW Attachment 3) for each day work is performed for review and approval by the NSWCPD TPOC. This is required to account for each calendar day throughout the life of the Contract. The reporting of work shall be identified by terminology consistent with the work schedule. Enter pertinent information including directions received, problems encountered during work, work progress and delays, conflicts or errors in the drawings or specifications, field changes, safety hazards encountered, instructions given and corrective actions taken, a record of visitors to the work site, quality control problem areas, deviations from the QC Plan, work deficiencies…