Attachment (4) PPI Response-N4008420B6502-Amend 0006.pdf

PDF 97 KB Posted

Attached to
Overhaul Caisson DD2 at CFAS Federal contract opportunity
Solicitation number
N4008420B6502
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

This document contains questions and answers regarding a federal solicitation for the overhaul of a caisson and hydraulic operation system at a naval facility. The scope of work involves overhauling the hydraulic operation system for sluice valves under construction sequence one, and overhauling the caisson at dry dock two under construction sequence two. Bidders must perform the on-site work for each sequence separately and cannot work on both simultaneously. The document provides clarification that contractors can attach pad eyes to the caisson by welding for towing purposes with prior approval. It also confirms that quay fees for berthing the caisson during transport and repair should be included in the contractor's price. Revised specification attachments adjust the schedule timelines. Contractors may request non-cost time extensions if the exclusionary time period exceeds the maximum of 90 days due to delays outside their control.

View the file

Other files for this federal contract opportunity

Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment (4) PPI Response N4008420B6502-Amend 0006

PPI Responses-N4008420B6502-Amend 0006

NO Reference Question Government Response

1 N/A

We have received information that the drain valve actuator for Dock #1 and #2 are interlocked.

Would it be possible to obtain the schedules for Dock 1 and 2 and possible time frames of when to conduct the removal and landing of hydraulic pump.

At the moment the Government can provide a tentative schedule but it is subject to change. Work for the hydraulic pump can be performed tentatively during the period of 3 August 2021 – 7 December 2021.

2 N/A

What would be the range of related equipment to hydraulic pumps? We have in mind the whole set including the pipings. Please clarify the specific range.

See pages 45-58 of the Attachment (2) for specific range for hydraulic pump equipment. Sheet M-018 (pdf page 56) has a “Remove and Provide Equipment List”. Sheet M-019 (pdf page 47) has a “Hydraulic Cylinder System Work List”. Sheet M- 022 (pdf page 50) has a “Parts List of Hydraulic Pump for Replacement List.”

Section 01 11 00. 00 33, 1.4.1.2 a.

Is it possible to attach necessary number of Pad Eye by welding on this barge, which is for the purpose of towing and dock-in and out at Dry Dock for repairing?

Yes, it is possible to attach pad eyes to the caisson for towing purposes. Prior to attaching the Contractor will need to submit an install plan to include strength calculation, position, etc. and it will need to be approved by the Contracting Officer.

Additionally there are for rigging points on the top of the Caisson. See photos DSC_0298, DSC_0300, & DSC_0301 for these locations.

DSC_0298

DSC_0300

SC_0301

Section 01 11 00. 00 33, 1.4.1.2 a

It is necessary to berth Caisson for ballast adjustment at a quay when the barge is towed to Dry Dock where it is repaired and also brought back to a specified place after repairing. Can we expect that the quay fee is paid by fund of this job?

Yes, the quay fee should be included in the Contractor’s price to do the work.

Attachment (4) PPI Response N4008420B6502-Amend 0006

01 11

00.00 33 1.4.1.1

Does the modification of the electric circuit and control circuit of the hydraulic pump mean a new replacement of the wirings? Would there be a need for maintenance on the motor? If it was to be maintained, shall it be overhauled? Is rewinding of the coil necessary?

Please see IFB Attachment (2) eP1559827D.

#E-017 to E-023 for the scope of electric circuit and control circuit.

#M-017 for the scope of motor.

01 11

00.00 33 1.6.2

Is it possible to change the days to:

Mailing period: 60 days Overhaul Hydraulic Operation System: 360 days Overhaul Caisson: 270 days

See revised specification, Attachment (5).

The Delivery information in solicitation is indicating 780 days ADC. When adding the Exclusionary time of maximum 90 days and the Construction sequence days of 690 days will become 780 days. In case after completing the overhaul of Hydraulic operation system, and if we cannot immediately start with overhaul of caisson, we may go past 780 days ADC. For example, due to other vessels dry docking at DD2, and could not remove dock gate for few months, dead time will occur. In that case, could we submit a condition report for time extension for that span?

If the Exclusionary Time Period (ETP) exceeds the maximum of 90 calendar days, the Contractor may request and the Government would provide a non-cost time extension for each day in excess of 90 calendar days.