This document contains questions and responses related to a federal solicitation for the overhaul of a caisson and hydraulic operation system at a naval facility. The solicitation involves performing on-site work on the hydraulic operation system and caisson in two separate construction sequences, with the order to be determined. The response provides clarification that attaching pad eyes to the caisson for towing requires approval, and identifies existing rigging points. Welding and quay fees would be the contractor's responsibility. The scope of work for electric, control circuits and motor maintenance is identified. Revised specifications extend the response period to 60 days and adjust the overhaul durations to 360 days for the hydraulic system and 270 days for the caisson.
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment (4) PPI Response N4008420B6502-Amend 0005
PPI Responses-N4008420B6502-Amend 0005
NO Reference Question Government Response
1 N/A
We have received information that the drain valve actuator for Dock #1 and #2 are interlocked.
Would it be possible to obtain the schedules for Dock 1 and 2 and possible time frames of when to conduct the removal and landing of hydraulic pump.
At the moment the Government can provide a tentative schedule but it is subject to change. Work for the hydraulic pump can be performed tentatively during the period of 3 August 2021 – 7 December 2021.
2 N/A
What would be the range of related equipment to hydraulic pumps? We have in mind the whole set including the pipings. Please clarify the specific range.
See pages 45-58 of the Attachment (2) for specific range for hydraulic pump equipment. Sheet M-018 (pdf page 56) has a “Remove and Provide Equipment List”. Sheet M-019 (pdf page 47) has a “Hydraulic Cylinder System Work List”. Sheet M- 022 (pdf page 50) has a “Parts List of Hydraulic Pump for Replacement List.”
Section 01 11 00. 00 33, 1.4.1.2 a.
Is it possible to attach necessary number of Pad Eye by welding on this barge, which is for the purpose of towing and dock-in and out at Dry Dock for repairing?
Yes, it is possible to attach pad eyes to the caisson for towing purposes. Prior to attaching the Contractor will need to submit an install plan to include strength calculation, position, etc. and it will need to be approved by the Contracting Officer.
Additionally there are for rigging points on the top of the Caisson. See photos DSC_0298, DSC_0300, & DSC_0301 for these locations.
DSC_0298
DSC_0300
SC_0301
Section 01 11 00. 00 33, 1.4.1.2 a
It is necessary to berth Caisson for ballast adjustment at a quay when the barge is towed to Dry Dock where it is repaired and also brought back to a specified place after repairing. Can we expect that the quay fee is paid by fund of this job?
Yes, the quay fee should be included in the Contractor’s price to do the work.
Attachment (4) PPI Response N4008420B6502-Amend 0005
01 11
00.00 33 1.4.1.1
Does the modification of the electric circuit and control circuit of the hydraulic pump mean a new replacement of the wirings? Would there be a need for maintenance on the motor? If it was to be maintained, shall it be overhauled? Is rewinding of the coil necessary?
Please see IFB Attachment (2) eP1559827D.
#E-017 to E-023 for the scope of electric circuit and control circuit.
#M-017 for the scope of motor.
01 11
00.00 33 1.6.2
Is it possible to change the days to:
Mailing period: 60 days Overhaul Hydraulic Operation System: 360 days Overhaul Caisson: 270 days
See revised specification, Attachment (5).