This federal solicitation requests proposals for the construction of a consolidated communication center at Joint Base Andrews in Maryland. The project includes constructing a new 79,374 square foot facility to support critical communication functions for the Air Force, White House, and Defense Information System Agency. The scope of work also involves demolishing two existing buildings totaling 105,841 square feet, removing underground storage tanks and contaminated soil, and completing all other necessary construction and support work. Proposals are due by April 23, 2021. The award will be a firm-fixed-price contract. Evaluation factors include experience, safety, small business participation, and past performance. The solicitation provides detailed submission requirements for proposals under each evaluation factor.

View the file

Other files for this federal contract opportunity

Other files attached to P3003, Consolidated Communication Center, AAFB, newest first.
File Type Posted
P-3003 AMENDMENT 0009.pdf PDF
P-3003 AMENDMENT 0008.pdf PDF
P-3003 AMENDMENT 0007.pdf PDF
P-3003 AMENDMENT 0006.pdf PDF
P3003 Revised Price Schedule - 15 APR 2021.doc DOC document
P3003 AMENDMENT 0005.pdf PDF
Site Vist Sign In Sheet2.pdf PDF
Site Visit Sign In Sheet1.pdf PDF
P-3003 AMENDMENT 0004.pdf PDF
P-3003 AMENDMENT 0003.pdf PDF
Andrews Air Force Base (ADW) MD - Bing Maps.pdf PDF
P-3003 AMENDMENT 0002.pdf PDF
02 P3003 IFC Drawings Vol 4.pdf PDF
02 P3003 IFC Drawings Vol 2.pdf PDF
P-3003 AMENDMENT 0001.pdf PDF
02 P3003 IFC Drawings Vol 6.pdf PDF
02 P3003 IFC Drawings Vol 7.pdf PDF
02 P3003 IFC Drawings Vol 5.pdf PDF
02 P3003 IFC Drawings Vol 3.pdf PDF
02 P3003 IFC Drawings Vol 1.pdf PDF
Construction Experience Project Data Sheet.doc DOC document
P3003 - Hazard Analysis Report.pdf PDF
06 P3003 CCC FFE 2021 IFC.pdf PDF
03 P3003 CCC Specifications Signed.pdf PDF
HISTORICAL SMALL BUSINESS UTILIZATION.docx DOCX document
SMALL BUSINESS PARTICIPATION COMMITMENT DOCUMENT.docx DOCX document
06 P3003 CCC SID IFC.pdf PDF
SMALL BUSINESS SUBCONTRACTING PLAN.docx DOCX document
P3003 Bid Schedule - 18 Mar 2021.doc DOC document
Past Performance Questionannaire.docx DOCX document
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P-3003, DESIGN-BID-BUILD, CONSOLIDATED COMMUNICATIONS CENTER JOINT BASE ANDREWS CAMP SPRINGS, MD

MYESHIA DANIELS 202-685-8411

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

21-Mar-2021

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

X

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______15 calendar days and complete it w ithin ________745 calendar days after receiving aw ard, notice to proceed. This performance period is X mandatory, negotiable. (See _________________________

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________0 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________23 Apr 2021 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

NAVAL FACILITIES ENGINEERING SYS COMMAND

1314 HARWOOD STREET SE

WASHINGTON DC 20374

N40080

PAGE OF PAGES

1 OF

CODE N40080

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

NAVAL FACILITIES ENG COMMAND WASHINGTON

1314 HARWOOD ST

WASHINGTON DC 20374

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: (202) 685-3192 TEL: FAX:

N4008021R9670 76

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

N4008021R9670

Section 00 10 00 - Solicitation

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Each Base Bid: Construction of P3003

FFP

Basis of Bid for Item 0001 shall be the entire work complete in accordance with the RFP specifications and drawings, but excluding work described in CLIN 0002, 0003, 0004, 0005, 0006, 0007, 0008, 0009, 0010, 0011, 0013, and 0014.

FOB: Destination

NET AMT

0002 1 Each Base Bid: FF&E design services

FFP

Basis of Bid for Item 0002 is interior design services. Provide the final Furniture, Fixtures and Equipment (FF&E) package and supporting plans and procurement data in accordance with the design schedule, but excluding work described in CLIN 0001, 0003, 0004, 0005, 0006, 0007, 0008, 0009, 0010, 0011, 0013, and 0014.

0003 1 Each Base Bid: Demo of BLDGs 1558 & 1539

FFP

Basis of Bid for Item 0003 is the demolition of buildings 1558 and 1539 and associated appurtenances in accordance with the drawings and specifications, but excluding work described in CLIN 0001, 0002, 0004, 0005, 0006, 0007, 0008, 0009, 0010, 0011, 0013, and 0014.

0004 1 Each Base Bid: 20,000 UST Removal

FFP

Basis of Bid for Item 0004 is the removal of (2) 20,000 gallon underground storage tanks located beneath building 1558 in accordance with the plans and specifications, but excluding work described in CLIN 0001, 0002, 0003, 0005, 0006, 0007, 0008, 0009, 0010, 0011, 0013, and 0014.

0005 1 Each Base Bid: 25,000 Gallon UST Removal

FFP

Basis of Bid for Item 0005 is the removal of (2) 25,000 gallon underground storage tanks located outside the building 1558 footprint in accordance with the plans and specifications, but excluding work described in CLIN 0001, 0002, 0003, 0004, 0006, 0007, 0008, 0009, 0010, 0011, 0013, and 0014.

0006 2,000 Cubic

Yard

Base Bid: Contaiminated Soil

FFP

Basis of Bid for Item 0006 is the removal of approximately 2000 cubic yards of contaminated soil associated with the removal of underground storage tanks in accordance with the specifications, but excluding work described in CLIN 0001, 0002, 0003, 0004, 0005, 0007, 0008, 0009, 0010, 0011, 0013, and 0014.

0007 1 Each Base Bid: RF Building

FFP

Basis of Bid for Item 0007 is the construction of the RF building in accordance with the plans and specifications, but excluding work described in CLIN 0001, 0002, 0003, 0004, 0005, 0006, 0008, 0009, 0010, 0011, 0013, and 0014.

0008 1 Each Base Bid: Generators

FFP

Basis of Bid for Item 0008 is to furnish and install all generators, generator enclosures, and tanks for a complete and usable system per the drawings and specifications, but excluding work described in CLIN 0001, 0002, 0003, 0004, 0005, 0006, 0007, 0009, 0010, 0011, 0013, and 0014.

0009 1 Each OPTION Option 1: A/V Design Services

FFP

Basis of Bid for Item 0009 is audiovisual design services. Design and provide the audiovisual (AV) package and to prepare the supporting plans and procurement data in accordance with the AV plans and specifications.

0010 1 Each OPTION Option 2: Equipment Cabinets

FFP

Basis of Bid for Item 0010 is to furnish and install the communication equipment cabinets and all associated equipment cabinet accessories as shown on drawing TN402 and scheduled on TN602 and TN603. Data center equipment cabinets and accessories that are associated with OSP and ISP fiber optic cabling shall be included in the base bid.

0011 1 Each OPTION Option 3: Landscaping

FFP

Basis of Bid for Item 0011 is Landscaping. Provide 30 canopy trees, 56 ornamental trees, 145 shrubs, 458 ground covers, 12 landscape boulders and brick inlay at main entrance sidewalk (vehicle loaded) in accordance with the plans and specifications.

0012 1 Each OPTION Option 4: Water Infiltration Testing

FFP

Basis of Bid for Item 0012 is water infiltration testing. Test water infiltration in accordance with ASTM E1105. Submit certified test reports showing compliance with specified performance. Test windows at 10%, 50%, 75% and 90% of installation completion.

0013 1 Each OPTION Option 5: Air Infiltration Testing

FFP

Basis of Bid for Item 0013 is air infiltration testing. Test air infiltration in accordance with ASTM E783. Submit certified test reports showing compliance with specified performance. Test windows at 10%, 50%, 75% and 90% of installation completion.

0014 1 Each OPTION Option 6: FF&E

FFP

Basis of the Bid for Item 0014 shall be the establishment of a Handling & Administrative Rate (HAR) for any possible future work associated with FF&E / Collateral Equipment. Budget = $2,638,772.00. Proposed HAR shall not exceed 5%. See price schedule for instructions.

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 N/A N/A N/A N/A

0002 N/A N/A N/A N/A

0003 N/A N/A N/A N/A

0004 N/A N/A N/A N/A

0005 N/A N/A N/A N/A

0006 N/A N/A N/A N/A

0007 N/A N/A N/A N/A

0008 N/A N/A N/A N/A

0009 N/A N/A N/A N/A

0010 N/A N/A N/A N/A

0011 N/A N/A N/A N/A

0012 N/A N/A N/A N/A

0013 N/A N/A N/A N/A

0014 N/A N/A N/A N/A

Section 00 21 13 - Instructions to Bidders

INSTRUCTIONS TO OFFERORS

1. GENERAL

1.1. THIS SOLICITATION IS BEING ISSUED AS UNRESTRICTED FOR FULL AND OPEN

COMPETITION. THE NAICS CODE FOR THIS PROCUREMENT IS 236220 AND THE

SIZE STANDARD IS $39.5M.

1.2. SOURCE SELECTION PROCESS: BEST VALUE TRADE OFF

1.3. THIS ACQUISITION WILL RESULT IN THE AWARD OF A FIRM-FIXED PRICE

(FFP) CONTRACT FOR CONSTRUCTION SERVICES.

1. 4. PRIMARY POINT OF CONTACT: The primary point of contact for this procurement is Myeshia Daniels at Myeshia.daniels@navy.mil. SECONDARY POINT OF CONTACT:

Lindsay Brown at Lindsay.naill@navy.mil

1.5. GENERAL OVERVIEW OF PROCUREMENT PROCESS

1.5.1 This solicitation is formatted as a Request for Proposal (RFP) in accordance with the requirements designated by sections of the FAR 15.203. This method permits evaluation of proposals based on price competition, technical merit and other factors; permits impartial and comprehensive evaluation of offerors' proposals; permits discussions if necessary; and ensures selection of the source whose performance provides the best value to the Government. This acquisition will be solicited as a competitively negotiated procurement.

1.5.2 The Government reserves the right to reject any or all proposals at any time prior to award;

to negotiate with any or all offerors; to award the contract to other than the offeror submitting the lowest total price; to award to other than the offeror submitting the highest technically rated proposal; and to award to the offeror submitting the proposal determined by the Government to be the most advantageous (best value) to the Government. OFFERORS ARE ADVISED THAT

AWARD MAY BE MADE WITHOUT DISCUSSION OR ANY CONTACT CONCERNING

THE PROPOSALS RECEIVED. Therefore, proposals should be submitted initially on the most favorable price and technical terms. Offerors should not assume that they will be contacted or afforded an opportunity to qualify, discuss, or revise their proposals. However, the Government reserves the right to clarify certain aspects of proposals or conduct discussions providing an opportunity for the offeror to revise its proposal.

2. GENERAL OVERVIEW OF THE PROJECT

P-3003, Design-Bid-Build, Consolidated Communication Center, Joint Base Andrews, Camp Springs, MD:

* Solicitation Section 01 00 00 will include the General Requirements for the project.

3. BASIS FOR AWARD

1. The Government reserves the right to eliminate from consideration for award any or all offers at any time prior to award of the contract; to negotiate with offerors in the competitive range; and to award the contract to the offeror submitting the proposal determined to represent the best value—the proposal most advantageous to the Government, price and other factors considered.

2. As stated in the solicitation, the Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)).

The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. In addition, if the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.

3. The tradeoff process is selected as appropriate for this acquisition. The Government considers it to be in its best interest to allow consideration of award to other than the lowest priced offeror or other than the highest technically rated offeror.

4. As stated in the solicitation, all technical factors when combined are of equal importance to the performance confidence assessment (past performance) rating; and all technical factors and the performance confidence assessment (past performance) rating, when combined are approximately equal to price.

5. Any proposal found to have a deficiency in meeting the stated solicitation requirements or performance objectives will be considered ineligible for award, unless the deficiency is corrected through discussions. Proposals may be found to have either a significant weakness or multiple weaknesses that impact either the individual factor rating or the overall rating for the proposal. The evaluation report must document the evaluation board’s assessment of the identified weakness(s) and the associated risk to successful contract performance resulting from the weakness(s). This assessment must provide the rationale for proceeding to award without discussions.

4. EVALUATION FACTORS FOR AWARD

1. The solicitation requires the evaluation of Price and the following non-cost/price factors:

Factor 1 – Experience Factor 2 – Safety Factor 3 – Small Business Utilization Factor 4 – Past Performance

The distinction between experience and past performance is that experience pertains to the volume of work completed by a contractor that are comparable to the types of work described under the definition of recent, relevant projects, in terms of size, scope, and complexity. Past performance pertains to both the relevance of recent efforts and how well a contractor has performed on the contracts.

2. The relative order of importance of the non-cost/price evaluation factors is the technical factors, Factors 1, 2, and 3 are of equal importance to each other and, when combined are equal in importance to the past performance evaluation/performance confidence assessment factor, Factor 4. When the proposal is evaluated as a whole, the technical factors and past performance/performance confidence assessment factor combined (i.e., the non-cost/price evaluation factors) are approximately equal to price.

The importance of price will increase if the Offerors’ non-cost/price proposals are considered essentially equal in terms of overall quality, or if price is so high as to significantly diminish the value of a non-cost/price proposal’s superiority to the Government. Award will be made to the responsible Offeror(s) whose offer conforms to the solicitation and represents the best value to the Government, price and non-price factors considered.

Factor 1 – Experience

(1) Solicitation Submittal Requirements:

The Offeror shall submit the following information:

Submit a minimum of three (3) and a maximum of five (5) construction projects for the Offeror that best demonstrates your experience on relevant projects that are similar in size, scope, and complexity to the RFP. For purposes of this evaluation, a relevant project is further defined as a project similar to the size, scope, and complexity characteristics set forth below. The overall relevancy will be determined by considering all three characteristics.

Size: 50,000 Square Feet (SF) or larger and/or a final construction cost of $30,000,000 or greater

Scope: New construction of a communication center (i.e. facility that serves as a node for a communications network) or data center (i.e. facility dedicated to hosting and running servers), or new construction of administrative facilities (e.g. offices, conference rooms, training rooms, etc.). Note: At least one project must be or contain a Communication Center or a Data Center of 7,500 square feet or greater.

Complexity: New construction of one of the facilities indicated in Scope above, inclusive of one or more of the following:

Installation of equipotential ground plane systems.

United States Government certified secure facilities that meet the Intelligence

Community Directive #705 (ICD 705) and UFC 4-010-05.

Projects submitted for the Offeror shall be completed within the past ten (10) years prior to the date of issuance of this RFP. Projects that have not attained beneficial occupancy will not be considered.

A project is defined as a construction project performed under a single task order or contract.

For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project; rather Offerors shall submit the work performed under a task order as a project.

The attached Construction Experience Project Data Sheet is MANDATORY and SHALL be used to submit project information. Except as specifically requested, the Government will not consider information submitted in addition to this form. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed one (1) 8.5” x 11” double-sided page (or two (2) single-sided 8.5” x 11” pages).

For all submitted projects, the description of the project shall clearly describe the scope of work performed and the relevancy to the project requirements of this RFP (i.e., unique features, area, construction methods). In addition, the description should also address any sustainable features for the project, including specific descriptions of those features. Provide applicable documentation on projects that were validated and/or certified through U.S. Green Building Council (USGBC) or the equivalent organization or process.

If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have shared experience, projects may be submitted for the JV members. If a project was performed by a JV, and not all partners from that JV are on the JV proposed for this contract, the offeror shall clearly demonstrate what portion of the work was performed by the JV partner offering on this contract and shall not include work performed by the JV as a whole. The JV member proposed for this contract shall specifically address field work performed by that JV member including field staffing and direct field work oversight. The JV member proposed for this contract shall also address home office management performed by that JV member including the number/percent of employees provided for the overall contract by the JV member as well as the overall percentage of work performed by the JV member. This same information shall also be provided for the task orders listed under IDIQ contracts on the Construction Experience Project Data Sheet. If the Offeror does not specifically address what portion of the work under the submitted project was performed by the JV member offering on this contract, the project will not be evaluated. Offerors are still limited to a total of five (5) projects combined.

If an Offeror is utilizing experience information of affiliates/subsidiaries/parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement in the performance of the contract in order for the past performance information of the affiliate/subsidiary/parent/LLC/LTD member companies to be considered. The proposal shall state specific commitments of technical resources (e.g. personnel, equipment) that the affiliate/subsidiary/parent/LLC/LTD member companies commit to the performance of this contract. In particular, the proposal will clearly state the specific commitments of resources of the affiliate/subsidiary/parent/LLC/LTD member that will be located at the worksites and company offices in the city/area of the project. The proposal shall also describe specific roles of the affiliate/subsidiary/ parent/LLC/LTD member companies in terms of the work it will either self-perform or manage on behalf of the Offeror in performance of the contract. Failure to provide this information may result in a lower rating. Any projects submitted in excess of the five (5) will not be considered.

The Offeror may utilize experience of a subcontractor that will perform major or critical aspects of the requirement to demonstrate construction experience under this evaluation factor. The Offer must provide the supporting subcontractor agreement or letter of commitment and an explanation of the meaningful involvement that the subcontractor will have in performance of this contract. The agreement or letter of commitment must be signed by officers with authority to bind the companies, and should clearly identify the company names, DUNS numbers, and point of contact information (address, email, phone, and fax). The proposal must state specific commitments of resources (e.g. personnel, equipment) that the subcontractor commits to the performance of this contract. The proposal shall also describe specific roles of the subcontractor in terms of the work it will either self-perform or manage on behalf of the Offeror in performance of the contract. Failure to submit this information may result in a lower rating.

More weight may be given to the Offeror’s projects than to those submitted for subcontractors.

(2) Basis of Evaluation:

The basis of evaluation will include the Offeror’s demonstrated experience and depth of experience in performing relevant construction projects as defined in the solicitation submittal requirements. The assessment of the Offeror’s aggregate experience will be used as a means of evaluating the capability of the Offeror to successfully meet the requirements of the RFP. A minimum of three (3) construction projects must be submitted, but the Government will only review a maximum of five (5) projects. Any projects submitted in excess of the five (5) will not be considered.

Proposal may be strengthened if the submitted projects possess:

Construction of stand-alone data centers and systems meeting TIA-942A Tier III or TIA-942B Rated 3 requirements, with associated satisfactory performance records in CPARS, if available, and scope meeting or exceeding the size and complexity of this project. Buildings submitted for consideration that have a higher tier rating under TIA-942 will be considered more favorably by the Government.

Experience with new construction projects where the Contractor was required to provide a secure construction zone and all construction personnel are required to be US persons (individuals lawfully admitted for permanent residence as defined in 8 U.S.C. 1101(a)(20) or protected individuals as defined in 8 U.S.C. 1324b(a)(3)).

Experience with the demolition of a whole building 65,000 sq. ft. or larger.

Experience with design and construction of deep foundation aggregate piers for ground improvement, specifically with 100 or more aggregate piers for a single project.

Experience with stormwater management and/or phased grading under Maryland Department of the Environment (MDE) jurisdiction.

Experience with removal of used underground storage tanks containing fuel under Maryland Department of the Environment (MDE) jurisdiction.

Experience with permitting and installing generators under Maryland Department of the Environment (MDE) jurisdiction.

Experience with the removal and disposal of hazardous material (lead, asbestos, etc.)

to a certified hazardous waste management facility from a building 50,000 sq. ft. or larger.

Experience with new construction projects of comparable size, scope and complexity, which required contingency planning due to unscheduled limited site access and/or work stoppage due to airfield operations.

Factor 2 – Safety

(1) Solicitation Submittal Requirements:

The Offeror shall submit the following information: The Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate; and Total Case Rate (TCR) for the specified five (5) Calendar Years (CY), as well as a safety narrative, as described further below. For a partnership or joint venture, the Offeror shall submit separate DART rates and TCR for the specified five (5) CY for each contractor who is part of the partnership/joint venture; however, only one safety narrative is required. Any fatalities experienced within this 5-year timeframe must be explained in detail, to include root cause and corrective actions.

NOTE: DART and TCR shall not be submitted for subcontractors

1. DART Rate: Submit five (5) previous complete calendar years’ [CY2016, CY2017, CY2018, CY2019, and CY2020] worth of data (not an overall average). If the Offeror has no DART rate, for any year, affirmatively state so and explain why. Should a negative trend occur above moderate risk levels, an acceptable/detailed explanation is required that includes any corrective actions taken for improvement.

a. DART cases include injuries or illnesses resulting in death, days away from work, and/or restricted work or transfer to another job days beyond the day of injury/illness.

b. Calculation of DART rate: Multiply the total number of DART cases by 200,000, and then divide by the number of employee labor hours worked.

2. TCR Rate: Submit five (5) previous complete calendar years’ [CY2016, CY2017, CY2018, CY2019, and CY2020] worth of data (not an overall average). If the Offeror has no TCR rate, for any year, affirmatively state so and explain why. Should a negative trend occur above moderate risk levels, an acceptable/detailed explanation is required that includes any corrective actions taken for improvement.

a. TCR cases include injuries or illnesses resulting in death, days away from work, restricted work or transfer to another job days beyond the day of injury/illness, medical treatment beyond first aid, or loss of consciousness.

b. Calculation of TCR rate: Multiply the total number of TCR incidents by 200,000, and then divide by the number of employee labor hours worked.

3. Technical Approach to Safety: Submit a narrative that addresses the following:

a. Describe the Offeror’ s approach to implementing and executing a Safety Management System (SMS) including Management/Leadership involvement, Employee involvement, Hazard prevention, Hazard control, Worksite analysis, and Safety and health training, to include the standard(s) used to benchmark the SMS.

b. Describe the evaluation process used to select potential subcontractors.

c. Describe the processes of how the Offeror will oversee safety compliance of subcontractors at all levels throughout performance of the contract (to include the Offeror’s own in-house workforce).

d. The Technical Approach to Safety narrative shall be limited to two (2) single-sided pages or one (1) double-sided page.

4. The Government reserves the right to review other available sources (public/Government internal) of information. These may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), Electronic Contract Management System (eCMS), etc.

(2) Basis of Evaluation:

The Government is seeking to determine that the Offeror has consistently demonstrated a commitment to safety and that the Offeror plans to properly manage and implement safety procedures for itself and its subcontractors. The evaluation will collectively consider the DART rate, TCR, Technical Approach to Safety, and other sources of information available to the Government as part of such collective evaluation. The board will evaluate the DART rates and TCR to determine if the Offeror has demonstrated a history of safe work practices taking into account any negative trends and extenuating circumstances that impact the rating.

1. DART Rate: The board will evaluate trends over the last five years considering changes that take it from one risk level (or more) to the next up or down. Negative trends occurring above moderate risk levels require the offeror to provide a detailed explanation that includes any corrective actions taken for improvement.

a. Missing data without an explanation is considered a deficiency.

b. Declining trends that push the risk levels from Moderate Risk (MR) or higher to Low Risk (LR) or Very Low Risk (VLR) would indicate a strength.

c. An increasing DART rate trend could be considered a weakness (i.e. MR or better to High Risk (HR) or Extremely High Risk EHR)) if an acceptable explanation is not provided for any trends that rise above Moderate.

d. This chart correlates the DART rate to the level of risk:

Risk DART Rate Very Low Risk Less Than 1.0 Low Risk From 1.0 to 1.99 Moderate Risk From 2.0 to 2.99 High Risk From 3.0 to 4.0 Extremely High Risk Greater than 4.0

2. TCR Rate: The board will evaluate trends over the last five years considering changes that take it from one risk level (or more) to the next up or down. Negative trends occurring above moderate risk levels require the offeror to provide a detailed explanation that includes any corrective actions taken for improvement.

a. Missing data without an explanation is considered a deficiency.

b. Declining trends that push the risk levels from Moderate Risk (MR) or higher to Low Risk (LR) or Very Low Risk (VLR) would indicate a strength.

c. An increasing TCR rate trend could be considered a weakness (i.e. MR or better to High Risk (HR) or Extremely High Risk EHR)) if an acceptable explanation is not provided for any trends that rise above Moderate.

d. This chart correlates the TCR rate to the level of risk:

Risk TCR Rate Very Low Risk Less Than 2.49 Low Risk From 2.5 to 3.49

Moderate Risk From 3.5 to 4.49 High Risk From 4.5 to 5.99 Extremely High Risk Greater than 6.0

3. The Technical Approach to Safety Narrative. To determine the degree to which the Offeror:

a. Describes a viable SMS that addresses elements; such as Management/Leadership involvement, Employee involvement, Hazard prevention, Hazard control, Worksite analysis, and Safety and health training, to include the standard(s) used to benchmark the SMS.

b. Describes a methodical process of evaluating subcontractor’s safety performance in their selection process.

c. Describes a logical management plan to hold themselves and their subcontractors accountable for adhering to the safety requirements of the contract.

d. The Technical Approach to Safety narrative shall be limited to two (2) single-sided pages or one (1) double-sided page. Information on pages beyond this will not be considered.

4. The Government reserves the right to review other available sources (public/Government internal) of information. These may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), Electronic Contract Management System (eCMS), etc.

Factor 3 - Small Business Utilization:

It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to Small Business (SB) concerns, including Historically Underutilized Business Zone Small Business (HUBZone SB), Woman-Owned Small Business (WOSB), Small Disadvantaged Business (SDB), Veteran-Owned Small Business (VOSB), Service-Disabled Veteran-Owned Small Business (SDVOSB), and other small business concerns. Furthert is the policy of the Government that such concerns will have the maximum practicable opportunity to participate in contract performance consistent with its efficient performance.

This Factor assesses both the historical achievements in utilizing small business concerns and the proposed small business participation commitment for this requirement. The Offeror is required to demonstrate its previous commitment to SBs through its record of past utilization of SBs and its planned level of commitment to small business if awarded a contract under this solicitation.

(1) Solicitation Submittal Requirements:

1. All Offerors (both Other than Small Businesses (OTSB) AND SBs shall use the attached Historical Small Business Utilization form to demonstrate their historical utilization of SBs. The Historical Small Business Utilization form shall be provided for each project submitted under Factor 1, Experience. Failure to submit the Historical Small Business Utilization form for each project submitted under Factor 1, Experience, or the failure to fully complete the Historical Small Business Utilization form may result in a deficiency.

2. All Offerors (both OTSBs and SBs) shall use the attached Small Business Participation Commitment Document (SPCD) to submit the following required information for evaluation of this factor:

• To demonstrate commitment to use small business concerns in the performance of this contract, identify all planned subcontractors by name that will be used to support each specific small business category (i.e., SB, HUBZone SB, WOSB, SDB, VOSB, and SDVOSB). Identify the type and complexity of product/service to be subcontracted, the estimated subcontract value, and the type of commitment (i.e., teaming agreement, letter of commitment, etc.) with each subcontractor.

• To demonstrate maximum practicable participation of small businesses, identify (in terms of dollar value and percentage of the total contract value) the Offeror’s proposed small business participation. The minimum required small business participation (i.e. work to be performed by small business as the prime contractor and/or work to be performed by small business subcontractors) is 20%. All Offerors who are not able to meet the minimum total small business participation rate of 20% (of the total contract value) shall provide a detailed explanation why the minimum total small business participation rate cannot be achieved.

Large business Offerors may achieve the minimum total small business participation rate through subcontracting to small businesses. Small business Offerors may achieve the minimum total small business participation rate through their own performance/participation as a prime and also through a joint venture, teaming arrangement, and/or subcontracting with other small business concerns.

Offerors are encouraged to exceed this percentage and seek meaningful levels of participation in each of the small business categories (i.e., SB, HUBZone SB, WOSB, SDB, VOSB, and SDVOSB) consistent with efficient contract performance. Offerors are required to provide a detailed explanation for the methods used to develop the small business participation rates.

Offerors simply proposing a 20% total small business participation rate without describing the methods used may be rated lower.

If the Offeror does not intend to subcontract, provide a detailed explanation why subcontracting would not result in efficient contract performance.

(2) Basis of Evaluation:

The Government will evaluate the realism and likelihood of success in achieving the small business objectives of this acquisition based on the following:

• The extent to which the Offeror is able to demonstrate a history of supporting Government policies concerning the utilization of small business concerns (including all of the various socioeconomic categories of small business, HUBZone SB, WOSB, SDB, VOSB, SDVOSB) and the success in achieving goals established by subcontracting plans on prior contracts.

• The extent to which the Offeror has demonstrated an achievable commitment to use small businesses (including HUBZone SB, WOSB, SDB, VOSB, SDVOSB) in the performance of this contract in the SBPCD. The SBPCD will be evaluated to determine the extent to which small business concerns are specifically identified by name and socioeconomic category in the document and the quantitative degree to which small business concerns (including HUBZone, WOSB, SDB, VOSB, and SDVOSB) will participate relative to the total contract value. The complexity and variety of the work small business concerns will perform and the degree of commitment to use named sources through formal teaming agreements, letters of intent/commitment will be evaluated to assess achievability of the commitment. This minimum small business participation rate, through work performed by the small business prime and/or subcontracting with small businesses, shall exceed 20% of the total contract value, unless the Offeror provides a reasonable and well-documented explanation for why 20% small business participation rate cannot be achieved.

Factor 4 - Past Performance:

(1) Solicitation Submittal Requirements:

Recent, relevant projects for past performance are defined as follows:

Recency: Construction projects completed within the past ten (10) years of the date of issuance of this RFP.

Relevancy: Communication center, data center, and/or administrative facilities with construction cost of $15,000,000 or greater

IF A COMPLETED CPARS EVALUATION IS AVAILABLE, IT SHALL BE SUBMITTED

WITH THE PROPOSAL. IF THERE IS NOT A COMPLETED CPARS EVALUATION, the Past Performance Questionnaire (PPQ) included in the solicitation is provided for the offeror or its team members to submit to the client for each project the offeror includes in its proposal for Factor 1, Experience. AN OFFEROR SHALL NOT SUBMIT A PPQ WHEN A COMPLETED

CPARS IS AVAILABLE.

IF A CPARS EVALUATION IS NOT AVAILABLE, ensure correct phone numbers and email addresses are provided for the client point of contact. Completed PPQs should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ (Attachment C), which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government's point of contact, Myeshia Daniels, via email at Myeshia.daniels@navy.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal

PPQs or CPARS previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.

Offerors may provide any information on problems encountered and the corrective actions taken on projects submitted under Factor 1 – Experience. Offerors may also address any adverse past performance issues. Explanations shall not exceed two (2) double-sided 8.5” x 11” pages (or four (4) single-sided 8.5” x 11” pages) in total.

In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all CAGE/ DUNS/Entity Identifier numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror.

While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.”

A copy of the blank Past Performance Questionnaire to be used for requesting client references is included as an Attachment.

Performance award or additional information submitted will not be considered.

(2) Basis of Evaluation:

Basis of Evaluation: The degree to which past performance evaluations and all other past performance information reviewed by the Government (e.g., PPIRS, Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), performance recognition documents, and information obtained from any other source) reflect a trend of satisfactory performance considering:

- A pattern of successful completion of tasks;

- A pattern of deliverables that are timely and of good quality;

- A pattern of cooperativeness and teamwork with the Government at all levels (task managers, contracting officers, auditors, etc.); and

- Recency of tasks performed that are identical to, similar to, or related to the task at hand

The Government will consider the currency and relevance of the information, the source of the information, context of the data, and general trends in the Contractor’s performance. This evaluation is separate and distinct from the Contracting Officer’s responsibility determination.

The assessment of the Offeror’s team’s past performance will be used as a means of evaluating the Offeror’s team’s probability to successfully meet the requirements of the RFP.

In the case of an Offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the Offeror may not be evaluated favorably or unfavorably on past performance. Therefore, the Offeror shall be determined to have unknown past performance.

Offerors lacking relevant past performance history will receive a NEUTRAL Confidence rating.

PRICE

(1) Solicitation Submittal Requirements:

The Offeror shall submit the following information:

The price proposals shall be separate from the techincal proposal. The price proposal shall contain the following:

• Cover page with solicitation number, solicitation title, offerors name, address, phone number, DUNS, CAGE code, Point of Contact (POC), POC phone number, and POC email address

• Completed SF 1442 signed with all amendments acknowledged.

• P3003 Price Schedule

• Copy of Online Representation and Certifications and proof of registration in System for Award Management (SAM)

• Confirmation of filing of Veterans' Employment and Training (VETS) VETS 4212 for the 2020 filing cycle.

• Bid Guarantee in accordance with FAR Clause 52.228-1 Bid Guarantee. Amount shall be at least 20 percent of the bid price but shall not exceed $3 million.

• Responsibility Determination Information (see below).

• Small Business Subcontracting Plan. (see blow).

The offeror is required to submit a complete Price Proposal Form that includes completion of all contract line items numbers (CLINs). Pricing information is not required to be completed under Section 00010 – Solicitation Contract Form in SF 1442. All required proposal documents shall be submitted in accordance with FAR 15.208.

(i) Executed SF1442. Offeror shall insert its company name and address in Block #14, telephone number in Block #15, acknowledge all amendments in Block #19 (if applicable), name and title of person authorized to sign in Block #20A, signature in Block #20B, and offer date in Block #20C of the SF1442. In addition, Offeror shall provide its DUNS Number, CAGE code, and Federal Tax ID number with its proposal.

(ii) Bid bond (SF-24). Offeror shall submit a bid bond (SF-24) in the amount of 20% of total project bid price for the project or $3M, whichever amount is less. The bid bond shall be in the name of the offeror identified on the SF1442.

(iii) SAM registration. Offeror shall ensure current registration on the SAM Website, www.sam.gov, including Annual Representations and Certifications are complete and updated for this procurement. If a Representation or Certification required by Section 00 45 00 of the RFP is not provided in SAM, include the representation or certification in your price proposal.

(iv) FAPIIS Certification. Offeror shall ensure Federal Awardee Performance and Integrity Information System (FAPIIS) Certification as required by FAR 52.209-7, Information Regarding Responsibility Matters.

(v) VETS-4212 registration. Offeror shall ensure a current VETS-4212 report has been submitted to the Department of Labor (DOL) website, http://www.dol.gov/vets/vets4212.htm, if the Offeror is required to submit. An email confirmation of submission can be requested and received by the Offeror from the DOL website and submitted in the price proposal. If the Offeror is not required to submit a report to VETS-4212, include a brief statement and justification explaining why the Offeror is not required to submit a report. Visit the VETS-4212 website for details concerning if your company is required to submit a VETS-4212 report and to request an email confirmation of submission.

ADDITIONAL INFORMATION TO BE SUBMITTED WITH PRICE PROPOSAL

PACKAGE:

RESPONSIBILITY DETERMINATION INFORMATION - In order to be eligible for award, the offeror must be determined responsible in accordance with FAR Part 9, specifically 9.104-1, General Standards. The offeror shall provide the following information in the price proposal package:

1. One (1) Signed Bank Reference demonstrating adequate financial resources. If offeror’s firm has a line of credit – provide information on how many figures offeror can borrow against the line of credit (i.e. medium 6 figures – exact line of credit is not required).

2. The offeror shall provide the latest three complete fiscal year financial statements for the prime contractor, certified by an independent accounting firm, if practicable, or signed by an authorized officer of the organization. Submit evidence of availability of working/operating capital, which will be used for the performance of the resultant contract. For Joint Venture arrangements, submit the latest three complete fiscal year financial statements for each company in the Joint Venture and discuss the financial responsibilities among the companies.

The Government may also utilize Dun & Bradstreet reports to evaluate the financial capacity of the offeror.

3. Description of offeror’s facilities and equipment.

4. Other offeror’s work presently under contract.

Although required to be submitted with offeror’s price proposal, this information will not be evaluated as part of the price proposal. This information forms the basis of your firm’s responsibility determination should your firm be considered for award. Proposal packages from unsuccessful offerors will not be returned to the offeror, but shall be destroyed by the Contracting Officer. No certificate of destruction will be issued.

SMALL BUSINESS SUBCONTRACTING PLAN INFORMATION:

In accordance with FAR 19.7, all other than small businesses shall submit a Small Business Subcontracting Plan (SBSP) utilizing the attached Small Business Subcontracting Plan template.

Acceptability of the SBSP will be considered a responsibility matter. The SBSP will not be evaluated or rated by the SSEB, but reviewed by a Small Business Professional/Authorized Representative and the Contracting Officer for acceptability. The SBSP shall be negotiated and/or accepted within the time specified by the Contracting Officer. Failure to negotiate an acceptable subcontracting plan within the time limit prescribed by the Contracting Officer will render the offeror ineligible for award of the contract. The SBSP will be incorporated into the resulting contract.

NAVFAC’s command-wide small business subcontracting targets are shown below. These may be higher or lower than percentages that would represent realistic, challenging, small business subcontracting goals for this acquisition consistent with efficient and effective performance of the contract. These targets are based on a percentage of total planned subcontract dollars.

Small Business: 37.44% HUBZone: 8.75%

SDVOSB: 4.22%

SDB: 23.57%

WOSB: 6%

The SBSP shall be consistent with the commitments offered in the Small Business Utilization and Participation Factor (Attachment E). In accordance with DFARS 215.304(c)(i), when an evaluation assesses the extent that small businesses are specifically identified in proposals, those small businesses considered in the evaluation shall be listed in the SBSP.

Please note that SBSP goals and the participation rates provided in the Small Business Participation Commitment Document (SBPCD) WILL NOT be the same. The participation rates within the SBPCD are provided as percentages of the total contract value; subcontract plan goals are provided as a percentage of planned subcontracting dollars.

While the percentages will differ, the types of products/services identified in the SBSP, should be the same as those products/services identified in the SBPCD. Likewise, the planned small business subcontract dollars in the SBSP will be equal to (or in some cases greater than) the extent of small business participation identified in the SBPCD.

(2) Basis of Evaluation:

The Government will evaluate price based on the total price.