Question_13.doc
DOC document 39 KB Posted
- Attached to
- USS EMORY S. LAND (AS 39) Mid-Term Availability Federal contract opportunity
- Solicitation number
- N3220518R4552
About this file
Request for specification clarification 013 - answered.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR SPECIFICATION CLARIFICATION
SPECIFICATION ITEM NO.: 022
PARAGRAPH / SECTION NO: 7.2.3
TITLE: MACHINERY SPACE TURN‐OVER, DOCK TRIALS AND SEA TRIALS
QUESTION:
Paragraph 7.2.3 requires contractors to perform dock trials 15 days before sea trials.
This is an unreasonable requirement for a one hundred day MTA availability and in conflict with Work item 013 which is referenced in the contract for Milestones.
Should contractor assume that work item 013 milestones take precedence?
ANSWER:
Work item 022 has been updated to reflect conduct of dock trial at least 15 days prior to sea trials.
ATTACHMENT J – 8