Question_10.doc
DOC document 41 KB Posted
- Attached to
- USS EMORY S. LAND (AS 39) Mid-Term Availability Federal contract opportunity
- Solicitation number
- N3220518R4552
About this file
Request for specification clarification 010 - answered.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR SPECIFICATION CLARIFICATION
SPECIFICATION ITEM NO.: 0516
PARAGRAPH / SECTION NO: 3.2.1, 7.1.2, 7.2.2, 7.2.3, 7.4-7.4.2
TITLE: NR 1 and NR 2 CHT Piping UT Gauging and Replace
QUESTION:
In order to provide a Firm Fixed Price for this Item Contractor requests additional information as follows.
1) (para. 3.2.1 & 7.2.3) What are the pipe sizes of the 500 feet to be renewed? Ref. 2.1 shows mainly 4” & 6”. How many pipe elbows and bulkhead penetrations (& sizes) should be included in the price?
2) (Para. 7.1.3) What is quantity of insulation / lagging to be removed and renewed that is to be included in price?
3) (Para. 7.2.2) How many UT readings are to be included in the price?
4) (Para. 7.4, 7.4.1 & 7.4.2) What is quantity of “disturbed” piping to receive surface preparation (SPC- SP 11) & coating? Will all new CuNi piping be required to have SPC-SP11 surface prep? Does the new CuNi piping require painting even when being covered in insulation?
ANSWER:
1. Use reference 2.1 for pipe elbows and BHD penetration.
2. Quantity is 200 linear feet of lagging.
3. Quantity is 300 UT reading.
4. All new pipe and disturbed piping shall be painted.